BILL ANALYSIS                                                                                                                                                                                                    



                                                                AB 144
                                                                Page  1

        (Without Reference to File)
         
        CONCURRENCE IN SENATE AMENDMENTS
        AB 144 (Hancock)
        As Amended July 6, 2005
        2/3 vote.  Urgency
         
         
         ---------------------------------------------------------------------- 
        |ASSEMBLY: |     |(May 5, 2005)   |SENATE: |34-3 |(July 7, 2005)       |
         ---------------------------------------------------------------------- 
                   (vote not relevant)


         ------------------------------------------------------------------------ 
        |COMMITTEE VOTE:  |11-0 |(July 12, 2005)     |RECOMMENDATION: |concur    |
        |                 |     |                    |                |          |
         ------------------------------------------------------------------------ 
          (Transportation)

         ---------------------------------------------------------------------- 
        |          |     |                |        |     |                     |
         ---------------------------------------------------------------------- 


         ------------------------------------------------------------------------ 
        |COMMITTEE VOTE:  |13-2 |(July 13, 2005)     |RECOMMENDATION: |concur    |
        |                 |     |                    |                |          |
         ------------------------------------------------------------------------ 
        (Appropriations)

        Original Committee Reference:    BUDGET  

         SUMMARY  :  Provides a financing plan to address the current $3.6  
        billion shortfall in funding for the Toll Bridge Seismic Retrofit  
        Program (TBSRP) and establishes new project management, oversight  
        and reporting requirements.  Identifies the sources and amounts of  
        funding, including the authority to increase the seismic retrofit  
        surcharge on state-owned toll bridges in the Bay Area, provides for  
        a timeline of contributions, and establishes numerous other  
        financial and programmatic requirements to complete TBSRP.  
         
        The Senate amendments  delete the prior contents of this bill and  
        insert the following provisions regarding TBSRP:  









                                                                AB 144
                                                                Page  2

        1)Find and declare that on August 16, 2004, the Department of  
          Transportation (Caltrans) reported to the Legislature that the  
          current sources of funding that have been identified for TBSRP  
          are insufficient to complete seismic retrofit and replacement  
          work on state-owned toll bridges, including replacement of the  
          San Francisco-Oakland Bay Bridge (Bay Bridge) due to cost  
          overruns in the program that are now estimated at $3.6 billion.  

        2)Identify the sources and amounts of the additional funds needed  
          to fund the new $3.6 billion cost overrun, as follows:

           a)   Not less than $2.15 billion derived from an additional $1  
             toll on state-owned toll bridges located in the Bay Area  
             region.  The additional $1 toll would commence no sooner than  
             January 1, 2007;

           b)   Not less than $820 million made available through the  
             consolidation of all toll revenues and the refinancing of  
             existing bonds under the Bay Area Toll Authority (BATA);

           c)   $300 million to fund the cost of demolition of the existing  
             East span of the Bay Bridge, from state funding sources that  
             support the State Highway Operations and Protection Program  
             (SHOPP), project savings, or the federal Highway Bridge  
             Replacement and Rehabilitation (HBRR) Program; and,

           d)   $330 million from the following state sources:  

             i)     $130 million from accumulated budget savings by  
               Caltrans from better efficiency, operational savings or  
               lower costs;

             ii)    $125 million from gasoline sales tax spillover revenues  
               in 2006-07, if available, otherwise from additional Caltrans  
               operational savings; and,

             iii)   An appropriation of $75 million from the Motor Vehicle  
               Account (MVA) fund reserve.  

        3)Provide that if the new cost overruns are  less  than $3.6 billion,  
          then the savings shall be returned to state transportation funds  
          and toll funds in shares that are proportional to the original  
          contribution to the cost overruns.  

        4)Authorize BATA to increase the toll bridge seismic retrofit  








                                                                AB 144
                                                                Page  3

          surcharge to complete TBSRP and meet its obligations under the  
          act, but not before January 1, 2007.  

        5)Authorize the consolidation of all toll revenues under BATA's  
          administration and management, and allows BATA to refinance the  
          current program debt that is secured by toll revenues.  Require  
          that Caltrans and the California Infrastructure and Economic  
          Development Bank (Infrastructure Bank) to promptly defease  
          existing debt obligations as part of the consolidation upon  
          BATA's request.  

        6)Specify that if the cost overruns  exceed  $3.6 billion, then BATA  
          would provide the additional financial resources under the toll  
          consolidation and other powers granted to it by this bill,  
          including the authority to increase the toll.  The state would  
          not be responsible for any additional cost overruns.  

        7)Reaffirm and reference that the funds for the retrofit program  
          for the replacement of the east span of the Bay Bridge shall only  
          be used for the self-anchored suspension (SAS) design in current  
          law.  

        8)Transfer responsibility for funding the maintenance costs of the  
          state-owned toll bridges in the Bay Area from the state to BATA  
          and require that these costs be paid for by toll revenues,  
          commencing with the completion of the seismic retrofit or  
          replacement work on individual bridges.

        9)Authorize Caltrans to include incentives and/or disincentives in  
          bid documents to maximize the number of retrofit program bidders,  
          and to encourage the timely completion of contracts.  

        10)Require the California Transportation Commission (CTC), by  
          December 1, 2005, to adopt a schedule for the payment of the  
          remaining state financial contributions to the retrofit program,  
          beginning in 2005-06, that insures that those contributions  
          provide a timely balance between state resources and the toll  
          revenue contribution.  State contingency funding provided under  
          AB 1171 (Dutra), Chapter 907, Statutes of 2001, would be used  
          commencing in 2008-09 as provided in the adopted Fund Estimate  
          for the 2004 State Transportation Improvement Program (STIP).  

        11)  Require the establishment of a Toll Bridge Program Oversight  
          Committee (Oversight Committee), consisting of the Executive  
          Director of BATA, the Director of Caltrans and the Executive  








                                                               AB 144
                                                                Page  4

          Director of CTC.  The Oversight Committee will perform project  
          status reviews, program costs and schedules, resolve project  
          issues, evaluate project changes, and develop and update cost  
          estimates, risk assessments and cash-flow requirements.  The  
          Oversight Committee also will review project staffing levels and  
          consultant and contractor services, review contract bid  
          specifications and documents, review and approve all significant  
          change orders and claims and prepare project reports.  

        12)  Authorize the Oversight Committee to create a project  
          management team to assist the committee in performing its duties.  
           BATA would also be authorized to contract with one or more  
          consulting firms to provide the technical and day-to-day  
          oversight functions of the committee.  

        13)  Require the Oversight Committee to report quarterly, within 45  
          days, to CTC and the Transportation and fiscal committees in both  
          houses of the Legislature in detail on the status of TBSRP,  
          including program progress, construction costs and expenditures  
          and adherence to budgets, project milestones, etc.  Require  
          Caltrans to report monthly to the Oversight Committee on the  
          construction status, actual expenditures and forecasted costs and  
          schedules of the retrofit program, including the Benicia-Martinez  
          Bridge project.  

        14)  Declare that the Oversight Committee shall not be considered a  
          governmental entity for purposes of complying with the  
          Bagley-Keene Open Meetings Act.  

        15)Require Caltrans to establish a comprehensive risk management  
          plan to identify and quantify project risks, implement and track  
          risk response activities, and monitor and control risks  
          throughout the duration of the retrofit program.  

        16)Continue the provisions established for the program under the  
          California Environmental Quality Act (CEQA) until the toll bridge  
          seismic retrofit and replacement projects are complete.  

        17)Continue the use of the current $1 state seismic retrofit toll  
          surcharge for the repayment of existing bonds and debt  
          obligations until those bonds have been defeased and the debt  
          obligations retired.  Subsequently, those revenues can be used  
          toward the new program bonds and financing authorized under this  
          bill and its consolidation and refinancing provisions.  









                                                                AB 144
                                                                Page  5

        18)Make numerous technical and conforming changes related to the  
          provisions.  

        19)Declare that the provisions of this act are severable and that  
          if any provision of this act or its application is held invalid,  
          that invalidity shall not affect other provisions or applications  
          that can be given effect without the invalid provision or  
          application.  

        20)Declare an urgency, allowing this bill to take effect  
          immediately.  

         EXISTING LAW  :  

        1)Specifies that Caltrans has full and sole responsibility for  
          completion of all seismic retrofit projects on the bay area  
          bridges.  

        2)Estimates the cost to seismically retrofit the state-owned toll  
          bridges and to replace the east span of the Bay Bridge at $4.6  
          billion, including $2.6 billion for replacement of the Bay Bridge  
          East span.  

        3)Identifies funding to be made available for this purpose from  
          various funding sources, including a $1 per vehicle toll  
          surcharge on Bay Area state-owned toll bridges and Proposition  
          192 seismic repair bond funds, among other sources.  

        4)Specifies the powers and duties of Caltrans, the Metropolitan  
          Transportation Commission (MTC), in its capacity as BATA, with  
          respect to state-owned Bay Area bridge toll revenue and  
          expenditure, and the financing of the toll bridge seismic  
          retrofit and replacement program.  

        5)Sets forth requirements for the solicitation and evaluation of  
          bids and the awarding of contracts by public entities for the  
          erection, construction, alteration, repair, or improvement of any  
          public structure, building, road, or other public improvement.  

         AS PASSED BY THE ASSEMBLY  , this bill declared legislative intent  
        regarding the 2005 Budget.  

         FISCAL EFFECT  :  This bill would result in the allocation of $630  
        million from various statewide transportation fund sources,  
        including $430 million from SHA ($300 million for East span  








                                                                AB 144
                                                                Page  6

        demolition costs attributed to SHOPP and $130 million attributed to  
        Caltrans operational savings), $125 million from spillover funds  
        that are projected to be available for the Public Transportation  
        Account (PTA) or from SHA depending on fuel prices and/or actions  
        taken during the 2006-07 Budget deliberations, and an appropriation  
        of $75 million from MVA.  

        This bill identifies no less than $2.15 billion from an additional  
        "fourth $1" on state-owned toll bridges and $820 million from the  
        authorized consolidation and refinancing of tolls by BATA.  

         COMMENTS  :  As passed by the Assembly, this bill was authored by the  
        Assembly Budget Committee and contained provisions that would have  
        declared the Legislature's intent to enact statutory changes  
        relating to the Budget Act of 2005-06.  This bill was amended later  
        and designated Assemblymember Hancock as the author, deleted the  
        prior contents and inserted new language regarding TBSRP that has  
        not been heard by the Assembly Transportation Committee.  

        This bill reflects a compromise agreement to provide funding and  
        project management, oversight and reporting reforms for the  
        completion of TBSRP.  This bill includes three main elements:  1) a  
        plan to provide a financial solution to the current and potentially  
        ongoing funding problems of TBSRP; 2) new reporting requirements  
        aimed at reforming the current pattern of chronic cost escalations  
        and poor accountability by Caltrans; and, 3) consolidated control  
        of toll revenues by BATA and ongoing responsibility to fund  
        maintenance of state-owned toll bridges.  

        Following the October 17, 1989, Loma Prieta earthquake, the state  
        undertook an analysis and research effort to determine the  
        vulnerability of state-owned toll bridges and other transportation  
        structures to seismic activity.  Caltrans entered into contracts  
        with private consulting firms, the University of California and  
        other research institutions to assess bridge and structure  
        vulnerabilities and produce action plans for addressing the  
        deficiencies.  Governor George Deukmejian created a Board of  
        Inquiry to investigate the collapse of various bridge and highway  
        structures and the Legislature convened special hearings to examine  
        the earthquake's effects and develop solutions to avoid or mitigate  
        similar seismic damage to the transportation system in the future.   


        The various boards, inquiries, studies and analyses concluded that  
        the state needed to retrofit thousands of bridge structures  








                                                                AB 144
                                                                Page  7

        throughout the state, both on highways and over water, including  
        retrofit strategies for state-owned toll bridges.  A strong  
        emphasis was placed on completing the retrofit work at an  
        accelerated pace to reduce the prospects of future catastrophic  
        loss, both in human and economic terms.  Work on highway bridges  
        proceeded relatively quickly but the retrofit of toll bridges  
        languished for numerous reasons, including the age and complexity  
        of bridge structures, securing adequate financing, environmental  
        issues, traffic, utilities, design, location and other concerns.  

        SB 60 (Kopp), Chapter 327, Statutes of 1997 and SB 226 (Kopp)  
        Chapter 328, Statutes of 1997):

        The Legislature enacted SB 60 and SB 226 which established a plan  
        and the financing mechanisms for the seismic retrofit of  
        state-owned toll bridges.  The plan consisted of the retrofit of  
        seven toll bridges (five in the Bay Area and two in southern  
        California) and the replacement of two bridges (the East span of  
        the Bay Bridge and the westbound Carquinez Bridge), the latter  
        funded from Bay Area Regional Measure 1 toll funds.  The estimated  
        cost of the replacement and retrofit work at that time (1997),  
        developed by Caltrans, was $2.62 billion, as follows:  

        (1) Benicia Bridge:  $101 million;
        (2) Carquinez Bridge (Eastbound span):  $83 million;
        (3) Richmond-San Rafael Bridge:  $329 million;
        (4) San Mateo-Hayward Bridge:  $127 million;
        (5) San Pedro-Terminal Island (Vincent Thomas) Bridge:  $45  
        million;
        (6) San Diego-Coronado Bridge:  $95 million;
        (7) Bay Bridge (West span):  $553 million; and,
        (8) Bay Bridge (East span):  $1,285 million.

        SB 60 and SB 226 prescribe the funding sources and the amounts from  
        each source to pay for the bridge seismic work.  The state's share  
        of funding included $790 million in seismic bond funds (Seismic  
        Retrofit Bond Fund of 1996-Proposition 192) and $875 million in  
        state transportation funds (SHA:  $795 million and PTA:  $80  
        million).  

        The regional/local share total was set at $955 million, of which  
        $907 million was to come from a $1 per vehicle toll surcharge  
        imposed by SB 60 for passage on the Bay Area toll bridges through  
        January 1, 2008, or until the $907 million was realized, whichever  
        occurred first.  SB 60 authorized the collection of toll revenues  








                                                                AB 144
                                                                Page  8

        beyond the $907 million to pay for the costs of "amenities"  
        approved by MTC.  (The so-called amenities included a change in the  
        Bay Bridge design, the relocation or replacement of the transbay  
        bus terminal in San Francisco, or the addition of  
        bicycle/pedestrian access on the Bay Bridge replacement span).  

        SB 60 made MTC the responsible agency for selecting the design of  
        the Bay Bridge replacement span.  SB 60 also required that if the  
        seismic retrofit costs were less than originally estimated, there  
        would be a proportional reduction in the funding provided by tolls  
        and state transportation account funds.  If the actual costs of the  
        toll bridge work were determined by Caltrans to exceed its original  
        estimates, however, it was required to report the reasons for the  
        cost overruns to the Legislature within 60 days and propose a  
        financial plan to pay for that increase, with the Legislature  
        subsequently to adopt a financial plan to pay for the increase.  



        2001 Cost Overrun Determined:

        SB 60 and SB 226 required Caltrans to report to the Legislature  
        within 60 days of any determination that the toll bridge retrofit  
        and replacement actual cost would exceed the codified cost estimate  
        of $2.62 billion.  In April 2001, Caltrans reported that the bridge  
        seismic retrofit work would incur substantial cost overruns of  
        approximately $2.019 billion, including an increase of $1.315  
        billion on the Bay Bridge East span replacement alone, another $557  
        million for 6 other toll bridges, and $147 million for the Bay  
        Bridge West span retrofit, as indicated:  

                        2001 Seismic Retrofit Cost Overruns
                                  (Millions of $)
        
         ----------------------------------------------------------------- 
        |                                |                                |
        |--------------------------------+--------------------------------|
        |Bridge                          |Amount                          |
        |--------------------------------+--------------------------------|
        |Richmond-San Rafael             |$ 336                           |
        |--------------------------------+--------------------------------|
        |Benicia-Martinez                |$   89                          |
        |--------------------------------+--------------------------------|
        |San Mateo-Hayward               |$   63                          |
        |--------------------------------+--------------------------------|








                                                                AB 144
                                                                Page  9

        |Carquinez                       |$   42                          |
        |--------------------------------+--------------------------------|
        |Vincent Thomas                  |$   17                          |
        |--------------------------------+--------------------------------|
        |San Diego-Coronado              |$   10                          |
        |--------------------------------+--------------------------------|
        |Non-Bay Bridge subtotal         |($557)                          |
        |--------------------------------+--------------------------------|
        |                                |                                |
        |--------------------------------+--------------------------------|
        |Bay Bridge - East Span          |$1,315                          |
        |replacement                     |                                |
        |--------------------------------+--------------------------------|
        |West Span                       |$   147                         |
        |--------------------------------+--------------------------------|
        |Total Cost Overrun, All Bridges |$2,019                          |
        |                                |                                |
         ----------------------------------------------------------------- 
        
        The Caltrans report attributed the cost overruns to several  
        factors, including:  1) inadequate original (department) estimates  
        with unrefined environmental, engineering and planning support  
        costs and the omission of escalation (inflation) and project  
        contingency costs; 2) a significant rise in construction costs,  
        including an 18% increase in the federal construction cost index in  
        1999-2000 alone; 3) accelerated design work; 4) the MTC's choice of  
        bridge design; 5) a one-year delay in receiving United States Navy  
        permission to conduct sample drillings on Yerba Buena Island, and,  
        6) another year's delay in completing environmental analyses in  
        concert with federal highway, environmental and engineering  
        agencies.  In addition, issues had arisen among local jurisdictions  
        and officials regarding the location of the Bay Bridge replacement  
        span and its final design elements.  

        The April 2001 report from Caltrans included a plan for resolving  
        the cost overruns on the six bridges other than the Bay Bridge,  
        proposing that $557 million from the state's share of federal HBRR  
        funds be used on those bridges.  The report, however, did not  
        include a proposal to fund the $1.315 billion cost overrun for the  
        replacement of the eastern span of the Bay Bridge.  

        On August 15, 2001, Caltrans submitted a followup letter to the  
        Legislature outlining a proposal to fund all of the Bay Bridge and  
        other bridges' cost increases through an extension of the toll  
        surcharge and the use of the $557 million in federal bridge repair  








                                                                AB 144
                                                                Page  10

        funds.  




        AB 1171 (Dutra), Chapter 1171, Statutes of 2001: 

        AB 1171 proposed a plan to finance the cost overruns reported by  
        Caltrans on state-owned toll bridges.  After extensive  
        deliberations and hearings on the bill's original and alternate  
        proposals, the Legislature enacted a revised version of AB 1171 to  
        fund the financial shortages and modify the seismic retrofit  
        financing plan.  AB 1171 did the following:  

        1)Authorized the extension of the $1 seismic retrofit toll  
          surcharge beyond its January 1, 2008 expiration and repeal date  
          until a total of $2.282 billion, plus interest, was collected  
          from the seismic retrofit surcharge.  

        2)Provided that if the projects' costs exceeded $4.637 billion,  
          Caltrans could program up to $448 million in contingency funds  
          from project savings or other available statewide resources from  
          the Interregional Transportation Improvement Plan (ITIP), SHOPP,  
          or the state's share of federal HBRR funds for that purpose.  

        3)Allocated a minimum of $642 million in state transportation funds  
          from the HBRR Program.  

        4)Provided that, if Caltrans determined that the actual retrofit  
          costs again exceeded projections, it was required to report to  
          the Legislature, within 90 days of the determination, the amount  
          of difference (overrun) and the reason for the cost increase.  

        5)Declared that AB 1171's provisions could not harm any project  
          that was programmed in STIP before January 1, 2002.  

        2004 Cost Estimates and Overruns:
                                                                
         On August 16, 2004, Caltrans submitted a Toll Bridge Seismic Safety  
        Retrofit Program Report and related material stating that total  
        seismic retrofit program costs had increased from $4.64 billion to  
        a projected $7.4 billion (and from $5.1 billion to $8.3 billion  
        when contingency costs were included).  The report stated that  
        several factors and complications were responsible for the cost  
        increases, including the SAS design, time delays and construction  








                                                                AB 144
                                                                Page  11

        complexities, insufficient initial analyses of cost, external  
        global cost escalation factors, including rising insurance,  
        financing and bonding costs, steel and construction costs, steel  
        industry consolidation and a significantly-lengthened construction  
        schedule (four additional years).  

        In addition the report provided a bridge-by-bridge comparison of  
        the new cost estimates versus those used in 1997 for SB 60 and in  
        2001 in enacting AB 1171, as follows:  











                  2004 TOLL BRIDGE SEISMIC RETROFIT COST ESTIMATES
                               (dollars in millions)

        
         ----------------------------------------------------------------- 
        |       Bridge        |    SB 60    |  AB 1171   |     August     |
        |                     |   (1997)    |   (2001)   |(2004)          |
        |---------------------+-------------+------------+----------------|
        |Benicia-Martinez     |    $101     |    $190    |      $160      |
        |Existing             |             |            |                |
        |---------------------+-------------+------------+----------------|
        |Carquinez            |     $83     |    $125    |      $115      |
        |(eastbound)          |             |            |                |
        |---------------------+-------------+------------+----------------|
        |Richmond-San Rafael  |    $329     |    $665    |      $914      |
        |---------------------+-------------+------------+----------------|
        |San Mateo-Hayward    |     $95     |    $190    |      $165      |
        |---------------------+-------------+------------+----------------|
        |Vincent Thomas       |     $45     |    $62     |      $59       |
        |---------------------+-------------+------------+----------------|
        |Bay Bridge - West    |    $553     |    $700    |      $737      |
        |Span                 |             |            |                |
        |---------------------+-------------+------------+----------------|
        |Bay Bridge - New     |   $1,285    |   $2,600   |     $5130      |
        |East Span            |             |            |                |








                                                               AB 144
                                                                Page  12

        |---------------------+-------------+------------+----------------|
        |Total                |   $2,620    |   $4,637   |     $7,405     |
        |---------------------+-------------+------------+----------------|
        |Program Contingency  |     n/a     |    $448    |      $900      |
        |---------------------+-------------+------------+----------------|
        |                     |             |            |                |
        |---------------------+-------------+------------+----------------|
        |Grand Total          |   $2,620    |   $5,085   |$8,305          |
        |                     |             |            |                |
         ----------------------------------------------------------------- 
        
        On May 26, 2004, Caltrans had received only one bid on the SAS  
        bridge (tower) contract.  The bid contained two separate amounts,  
        depending on whether foreign steel or domestic steel was used for  
        the bridge.  The $ 1.4 billion (foreign steel) and $1.8 billion  
        (domestic steel) bids both far exceeded Caltran's estimate of $740  
        million for the contract.  

        The August report stated that there was insufficient expenditure  
        authority remaining in the AB 1171 financing legislation to award  
        the tower contract and advised the Legislature and the Governor  
        that a revised funding solution needed to be enacted in order to  
        complete with the Bay Bridge replacement project.  

        The Schwarzenegger Administration proposed that the new cost  
        overruns should be financed through a diversion of the Regional  
        Measure 2 (RM2) toll funds (the "third $1") approved by the Bay  
        Area voters in March 2004 and that authority should be granted for  
        a subsequent toll increase to backfill redirected RM2 funds and  
        preserve the regional traffic relief plan associated with RM2.  

        A counter-proposal, AB 2366 (Dutra) of 2004, was developed to  
        provide interim supplemental financing for the bridge retrofit  
        program, but neither that bill nor the Administration's proposal  
        was enacted by the end of the legislative year.  

        The single bid for the SAS tower, which had been extended once, was  
        allowed to expire on September 30, 2004.  The Administration stated  
        that in lieu of accepting the bid, it would explore alternatives to  
        re-bid the SAS design or consider reopening the bridge design  
        process.  In December 2004, Caltrans completed its review of six  
        bridge alternatives, one of several review efforts undertaken from  
        September through December time period, and recommended  
        re-advertising the SAS design with several modifications and  
        enhancements to make the contract more biddable and buildable.   








                                                                AB 144
                                                                Page  13

        Caltrans also recommended further consideration of the skyway  
        design proposal because of potential cost savings.  

        On December 10, 2004, the Secretary of Business, Transportation &  
        Housing announced that the administration was proposing a change in  
        the design of the east span bridge project by endorsing the skyway  
        option instead of the current SAS design specified in statute.  

        Later in December of 2004, the Bureau of State Audits issued a  
        report which concluded in part, that Caltrans's management of the  
        program has been inadequate and that it has failed to keep the  
        Legislature and others informed of developing problems in the  
        program, which now faces a $3.2 billion cost overrun, its second  
        major overrun in three years.  The State Auditor found that  
        Caltrans neglected important aspects of generally accepted project  
        management standards, failed to establish a comprehensive risk  
        management plan, and lacked processes to identify and track risks.   
        Additionally, the Auditor concluded that capital and support costs  
        were not regularly updated and that Caltrans ignored numerous  
        indications that the toll bridge seismic retrofit program was in  
        trouble.  

        Legislation was introduced in the 2005-06 Regular Session to  
        reflect the administration's proposal and alternate proposals were  
        introduced to preserve the current design and provide funding  
        through a mix of increased toll funding and state contributions  
        from a general obligation bond.  Both proposals, listed below, are  
        currently pending.  

        Related legislation:  

        SB 1024 (Perata), pending in the Senate, would authorize the sale  
        of $7.688 billion in general obligation bonds and allocate funding  
        for various categories of transportation expenditures, including  
        $1.363 billion for the toll bridge seismic retrofit program.

        SB 172 (Torlakson), pending in the Assembly, would require Caltrans  
        to develop a comprehensive risk management plan for the toll bridge  
        seismic retrofit program and establish a time limit for submitting  
        quarterly seismic reports.  The bill would also establish shared  
        oversight and project management responsibilities between Caltrans  
        and BATA for seismic retrofit and other toll related programs.  

        AB 1714 (Plescia), was held on the suspense file in the Assembly  
        Appropriations Committee.  As introduced, this bill sought to  








                                                                AB 144
                                                                Page  14

        provide a financing plan for the completion of TBSRP and authorize  
        a redesign of the East span of the Bay Bridge.  The bill was later  
        amended to strike the original provisions and insert intent  
        language.  

        Questions/Clarifications:

        1)This bill identifies $125 million in potential "spillover"  
          revenues as a contribution to the $630 million state share of the  
          cost overruns.  This bill also specifies that if those funds are  
          not available, then the $125 million contribution may come from  
          operational savings, or "from other state transportation fund  
          accounts as determined by the director in consultation with the  
          commission (CTC)."  It is not clear what types of state  
          transportation funds are captured under the term "other state  
          transportation fund accounts."  If there is an opportunity to  
          enact clarifications to this bill, it may be preferable to revise  
          this provision by providing a more specific reference to the  
          particular transportation funds that would potentially make a  
          contribution in place of the spillover funds and to require  
          approval from the CTC rather than "consultation."  

        2)This bill would exempt the Oversight Committee from open meeting  
          requirements under the Bagley-Keene Act.  The committee may wish  
          to seek clarification on why this is necessary.  

        3)This bill would authorize Caltrans to provide incentives and  
          disincentives to maximize the number of bidders and encourage  
          timely delivery and thorough completion of TBSRP contracts.  This  
          bill also includes a requirement for Caltrans to summarize the  
          expenses that it incurs in providing these incentives and  
          disincentives.  The committee may wish to consider whether this  
          reporting requirement should be expanded to require Caltrans to  
          provide more detailed accounting of the exact types and amounts  
          of incentives and disincentives that are provided.  


         Analysis Prepared by  :    Andrew Antwih / TRANS. / (916) 319-2093 




                                                                FN: 0011632