BILL ANALYSIS                                                                                                                                                                                                    



                                                                  AB 1954
                                                                  Page  1

          Date of Hearing:   April 5, 2010

                    ASSEMBLY COMMITTEE ON UTILITIES AND COMMERCE
                               Steven Bradford, Chair
                AB 1954 (Skinner) - As Introduced:  February 17, 2010
          
          SUBJECT  :   Electrical transmission: renewable energy resources.

           SUMMARY  :   Requires the California Public Utilities Commission  
          (CPUC) to make a finding that new transmission lines from  
          designated renewable energy zones are reasonably necessary or  
          appropriate, and allows the CPUC to provide assurance to the  
          utility that it can recover the costs of building transmission  
          prior to a determination of rate recovery by the Federal Energy  
          Regulatory Commission (FERC).   Specifically,  this bill  :  

          1)Requires the CPUC, when acting upon an application by an  
            electrical corporation for a certificate of public convenience  
            and necessity (CPCN), to deem new transmission facilities  
             reasonably  necessary or appropriate to provide electric  
            service if the CPUC finds that the transmission facilities  
            facilitate the achievement of the renewables portfolio  
            standard (RPS).

          2)Requires the CPUC to provide assurance to the transmission  
            owner of the eligibility for recovery of costs in retail  
            rates, prior to a determination of rate recovery by the FERC  
            for costs that are subject to FERC jurisdiction, and  
            conditioned upon the CPUC's subsequent determination that FERC  
            did not approve the costs and the CPUC determines that the  
            costs were prudently incurred and complies with public notice  
            requirements of rate changes.

          3)Requires the CPUC to approve an advice letter seeking  
            assurance of cost recovery if either:

             a)   The new transmission line will primarily deliver  
               electricity generated within a designated renewable energy  
               zone.

             b)   The new transmission line is needed to deliver  
               electricity where the interconnection requests include at  
               least 50% from renewable energy generators, and all of the  
               interconnection requests are for generation facilities that  
               are designed to comply with the greenhouse gasses emission  
               performance standard for baseload electric generation  
               facilities.






                                                                  AB 1954
                                                                  Page  2

          4)Provides that the approval of an advice letter is not binding  
            upon the CPUC in making its determination whether nor not to  
            approve an application for a CPCN.

          5)Defines renewable energy credit as a certificate of proof  
            associated with the generation of electricity from an eligible  
            renewable energy resource.

          6)Precludes renewable energy sources from the creation of a REC  
            if the amount of nonrenewable fuel used exceeds a de minimis  
            quantity for  each renewable energy   technology  , as determined  
            by the California Energy Commission (CEC).  

           EXISTING LAW  

          1)Precludes a gas corporation, an electrical corporation, and  
            other public utilities from beginning the construction of a  
            line, plant, or system without having first obtained from the  
            CPUC a CPCN.

          2)Allows the CPUC to recover in retail rates any increase in  
            transmission costs resulting from the construction of the  
            transmission facilities that are not approved for recovery in  
            transmission rates by the FERC after the CPUC determines that  
            the costs were prudently incurred.

          3)Precludes electricity generated from a renewable energy source  
            from the creation of a renewable energy credit (REC) if the  
            amount of nonrenewable fuel used exceeds a de minimis quantity  
            as determined by the CEC.  

          4)States legislative intent to increase the amount of  
            electricity generated from eligible renewable energy resources  
            per year, so that it equals at least 20 percent of total  
            retail sales of electricity by December 31, 2010.  

           FISCAL EFFECT  :   Unknown.

           COMMENTS  :   According to the author, the purpose of this bill is  
          to smooth a couple of small issues that could have big impacts  
          on the renewable development community and on the achievement of  
          our long-term goals.  "As we move toward California's current  
          renewable energy goals and pursue a higher standard, it has  
          become clear that there are limitations to the statutory  
          authority to accommodate new and improved technologies, and the  
          current tight credit market, which, in turn, affects financing  
          of these projects.






                                                                  AB 1954
                                                                  Page  3

          "This bill addresses a relatively technical issue that  
          inadvertently presents impediments to financing of renewable  
          energy - and another issue which may unintentionally serve to  
          limit the efficient production of renewable energy."

          1)   Background:   Current law creates a RPS that requires  
          utilities to procure at least 20% of their electricity  
          generation from renewable energy generators.  Two bills were  
          introduced last year (AB 64, Krekorian, and SB 14, Simitian) and  
          one bill this year (SB 422, Simitian) to increase the RPS to 33%  
          by 2020.

          Thirty-three percent of the combined utilities' portfolios  
          equates to about 28,000 megawatts (MW).  This goal can't be  
          attained by roof-top solar alone, which requires about 13-20  
          homes to generate just 1 MW.  (Most rooftop solar is close to  
          50-75 kW, where 1,000 kW equals 1 MW.)  As such, the utilities  
          are reaching to remote areas of the state that possess ample  
          wind, solar, and geothermal potential to contribute to the  
          majority of its portfolio of renewable generation.

          To determine which areas of the state would render the greatest  
          potential to generate renewable energy, the CEC at the staff  
          level initiated the Renewable Energy Transmission Initiative  
          (RETI) to identify optimal renewable energy designation zones  
          and the transmission corridors necessary to access the renewable  
          generation facilities.  The CEC contracted with an entity that  
          represents renewable developers to conduct the stakeholder  
          process to identify the zones and related transmission  
          corridors.  According to the CEC, RETI will assess all  
          competitive renewable energy zones in California and possibly  
          also in neighboring states that can provide significant  
          electricity to California consumers by the year 2020.

          The California Independent System Operator (CAISO) identified 6  
          transmission projects that included 7 new or upgraded  
          transmission lines, at a total cost of about $6.5 billion  
          (preliminary estimate), for the IOUs within the CAISO balancing  
          authority area to meet 33% RPS target in 2020.  A 2008 RPS  
          report from the CPUC concludes that the state needs 7 new major  
          transmission lines (15,900 MW) at a cost of $6.4 billion to  
          attain a 33% RPS by 2020. 

          According to the CEC, in September 2009, RETI revised the  
          renewable energy zones, including cost and environmental  
          information.  In addition, the RETI stakeholders are currently  
          creating development scenarios to be provided to the California  
          Transmission Planning Group (CTPG, coordinated by the California  





                                                                  AB 1954
                                                                  Page  4

          Independent System Operator, or CAISO) for use as sensitivities  
          for their proposed statewide transmission planning effort.  

          On September 15, 2009, the CAISO launched its "Getting to 33%  
          RPS" initiative outlining a new framework for comprehensively  
          planning the transmission upgrades that will be needed to reach  
          the RPS targets. Over the past year the CAISO has been  
          collaborating with the other transmission planners and operators  
          in California, including the municipal utilities, to assess  
          transmission needs for the state as whole and developing a  
          cost-effective, statewide transmission plan for 33% RPS building  
          upon the RETI findings.  After completing the public stakeholder  
          process the CAISO expects the final statewide plan to be  
          developed by December 2010. The plan will include a set of "no  
          regrets" transmission upgrades that will be needed with high  
          confidence based on committed new renewable generation, as well  
          as "conditional" lines whose needs will be re-evaluated based on  
          the future course of renewable generation development. The  
          conditional category helps mitigate the risks to project  
          developers of incurring unrecoverable costs, by allowing cost  
          recovery for pre-construction activities undertaken for  
          conditional projects that do not ultimately receive final  
          approval.  

          2)   Transmission siting  : The investor-owned utilities are  
          responsible for building and owning transmission lines.  They  
          submit their plans to the CAISO, which then develops the  
          statewide transmission plan.  Prior to building any needed  
          transmission, the CPUC must issue a CPCN (which can take 3 to 4  
          years), and the transmission owner must request cost-recovery  
          for the transmission line from the Federal Energy Regulatory  
          Commission (FERC).

          Although current law allows the CPUC to allow recovery of  
          construction costs in retail rates, the transmission owner must  
          first seek recovery from the FERC, and the FERC must have denied  
          the request for cost recovery.  Until either the CPUC issues the  
          CPCN, or the FERC determines that the costs are recoverable in  
          federal transmission rates, renewable energy developers are  
          presumed responsible for financing the substantial cost of new  
          or upgraded transmission.  

          Renewable developers need to secure project financing well  
          before the CPUC and FERC determine whether to allow transmission  
          owners cost recovery.  Without preliminary CPUC or FERC  
          assurance, financers must assume that developers will incur all  
          costs of the new or upgraded transmission needed to tie the  
          generation facility to the grid, which significantly increases  





                                                                 AB 1954
                                                                  Page  5

          the developer's project costs.  Greater project costs (or  
          unknown project costs) narrow the gap between costs and  
          projected revenue, which increases risk to potential investors.   
          As a result, either investors balk, or provide capital at higher  
          cost in the form of up-front costs or a higher interest rate to  
          compensate for their risk.  Higher costs of capital are likely  
          built into the generator's bid to supply electricity to the  
          utility, which gets passed on to ratepayers.

          3)   Why an Advice Letter  :  This bill would allow the CPUC to  
          assure cost recovery through an advice letter process prior to  
          construction of the transmission line if the line is needed to  
          access renewable energy generated in a RETI-designated zone.  An  
          advice letter is a filing to implement a previously decided  
          policy question at the CPUC.  Advice letters can also be used to  
          implement a policy decision of the Legislature.  Other  
          non-advice letter applications would seek authority to do  
          something that the CPUC has not already authorized.  

          4)   Renewable Energy Credits  :  A REC represents the renewable  
          attributes of renewable generation. A REC can remain bundled  
          with the associated energy.  If bundled, the utility buys the  
          renewable electricity and uses the RECs to meet its RPS  
          obligation and uses the associated electricity to meet its own  
          load.   RECs can also be traded as a separate asset from the  
          underlying electricity (tradable RECs or tRECs).  In this case,  
          one retail seller purchases the tREC and applies it toward its  
          RPS obligation and another retail seller purchases the  
          associated electricity to meet its own load.  The second retail  
          seller cannot count that electricity toward its own RPS  
          obligations.

          Existing law provides the CEC with authority to determine a de  
          minimis quantity of fossil fuel that renewable energy generation  
          can utilize and still qualify their output as renewable energy.   
          Small quantities of fossil fuel are used by different  
          technologies to improve reliability and operations, as well as  
          to increase the efficiency of their conversion of renewable  
          fuels into electrical energy.   The CEC has determined the de  
          minimis quantity needed to stabilize a biomass plant and uses  
          that quantity as its baseline for all renewable technologies.   
          This quantity may not be applicable to the quantity needed to  
          stabilize other renewable technologies such as solar, wind, or  
          geothermal.  This bill would require the CEC to make its de  
          minimis determination on a technology-specific basis, and  
          require the CEC to make its determination at the amounts needed  
          to enhance reliability and renewable energy output in order to  
          have the electricity include a REC component.





                                                                  AB 1954
                                                                  Page  6


           REGISTERED SUPPORT / OPPOSITION  :   

           Support 
           
          Abengoa Solar
          Amonix
          Ausra
          BrightSource Energy
          First Solar
          FRV
          Infinia
          Large-Scale Solar Association 
          NextLight
          Solel
          SunPower
          Suntech
          Tessera Solar/Stirling Energy

           Opposition 
           
          None on file.
           
          Analysis Prepared by  :    Gina Adams / U. & C. / (916) 319-2083