BILL ANALYSIS                                                                                                                                                                                                    



                                                                  SB 629
                                                                  Page  1

          Date of Hearing:   June 30, 2009

                           ASSEMBLY COMMITTEE ON JUDICIARY
                                  Mike Feuer, Chair
                       SB 629 (Liu) - As Amended: June 23, 2009
                            
           SENATE VOTE  :  31-6
           
          SUBJECT  :  Private Works of Improvement: Retention Proceeds

           KEY ISSUE  :  Should the retention proceeds withheld by an owner  
          from payment owed to an original contract, or by an original  
          contractor from a subcontractor, be limited to 5% of the amount  
          otherwise due for a private work of improvement?

           FISCAL EFFECT  :  As currently in print this bill is keyed  
          non-fiscal.

                                      SYNOPSIS 

          In most contracts for private works of improvement (e.g.  
          remodeling and construction projects) the property owner makes  
          "progress payments" to the general contractor as the work  
          proceeds, rather than pay the full contract price up front or  
          not pay anything until after completion.  The general contractor  
          then typically pays subcontractors, if any, a portion of the  
          progress payment.  However, an owner may hold back a certain  
          amount of the payment due, known as "retention proceeds," until  
          45 days after the work is fully completed.  General contractors  
          may in turn, hold retention proceeds owed to the subcontractor  
          until after the entire project is completed.  Retention proceeds  
          developed as a means by which owners and general contractors  
          could motivate general contractors and subcontractors,  
          respectively, to complete the work, and to soften the blow if  
          the work is not completed or shoddily done.  Although existing  
          law does not place any cap on the percentage of the contract  
          amount that can be held as retention proceeds, current  
          construction industry practices appear to set the amount at  
          about 10% of the amount owed.  However, retention proceeds can  
          be negotiated in the contract, the percentage held can vary  
          based on things like the subcontractor's reputation and whether  
          he or she is bonded.  This bill would impose a statutory cap of  
          5% of the contract amount on all private construction contracts  
          - the contract between the owner and general contractor, and the  
          contracts between the general and the subcontractors, and  








                                                                  SB 629
                                                                  Page  2

          between subcontractors.  This bill is supported by dozens of  
          subcontractor associations, who claim that subcontractors often  
          do not receive retention payments until well after their part of  
          the project has been completed.  Moreover, they argue that while  
          10% may sound like a small figure, it might represent some  
          subcontractors' entire profit margin.  The bill is opposed by  
          general contractor and builder associations, who claim that  
          retention proceeds serve an important purpose and, in the  
          private market at least, should be negotiable rather than set  
          statutorily. 

           SUMMARY  :  Prohibits an owner or general contractor from  
          withholding "retention proceeds" that exceed 5% the amount  
          otherwise under a contract for a private work of improvement.  
          Specifically,  this bill  :   

          1)Provides that, for private works of improvement contracted on  
            or after January 1, 2010, retention proceeds withheld from any  
            payment made by an owner to a general contractor shall not  
            exceed 5% of the amount of the contract amount.  Provides that  
            retention proceeds withheld from any payment made by the  
            general contractor to a subcontractor, or by a subcontractor  
            to a subcontractor, or between subcontractors, shall not  
            exceed 5% of the amount otherwise due under the contract, or a  
            percentage determined under the contract, whichever is less.   
            In no event shall the total amount of retention proceeds  
            withheld under all payments made under the contract exceed 5%  
            of the total contract price. 

          2)Provides that any retention proceeds withheld by an owner from  
            a general contractor, by a general contractor from a  
            subcontractor, or by a subcontractor from another  
            subcontractor, shall be released within 45 days after the  
            party seeking the payment of any retained amounts completes  
            its scope of work and serves the other party with a designated  
            form demanding release of the retained proceeds.

          3)Specifies that it shall be contrary to public policy for any  
            party to require any other party to waive any provision of  
            this bill.

          4)Specifies that this bill does not prohibit the withholding of  
            funds in the event of a dispute, as provided in subdivisions  
            (e) and (f) of Section 3260 of the Civil Code (see below).  









                                                                  SB 629
                                                                  Page  3

          5)Provides that the provisions of this bill shall not apply if  
            the owner or general contractor provides written notice to the  
            general contractor or subcontractor, respectively, at the time  
            of the bid request, that performance or payment bonds may be  
            required, and the general contractor or subcontractor  
            subsequently is unable or refuses to provide the owner or  
            general contractor with a performance or payment bond issued  
            by an admitted surety insurer.  

           EXISTING LAW  : 

          1)Requires an owner to pay "progress payments" within 30 days  
            following a demand made in accordance with the terms of the  
            contract.  (Civil Code Section 3260.1) 

          2)Requires a general contractor or subcontractor, under a  
            contract for a private work of improvement, to pay any amount  
            owed under the contract within 10 days after the receipt of a  
            progress payment from the owner.  (Business & Professions Code  
            Section 7108.5)

          3)Requires any retention proceeds withheld by an owner or  
            general contractor, under a private work of improvement, to be  
            released within 45 days the project's date of completion, as  
            defined.  (Civil Code Sections 3260(a), 3086, and 3093.)

          4)Provides that in the event of a dispute over work performed,  
            an owner or general contractor may withhold from any payment  
            due to the general contractor or subcontractor an amount equal  
            to 150% of the amount in dispute.  (Civil Code Section 3260  
            (e) and (f).) 

          5)Specifies that the above provisions relating to retention  
            proceeds do not apply to retentions withheld by a lender  
            pursuant to a construction loan contract.  (Civil Code Section  
            3260 (i).) 

          6)Prohibits Caltrans from withholding  any  retention proceeds  
            when making progress payments to a contractor for work  
            performed on a transportation project.  (Public Contracts Code  
            Section 7202.)

           COMMENTS  :  In most contracts for private works of improvement  
          (e.g. remodeling and construction projects) the property owner  
          makes "progress payments" to the general contractor as the work  








                                                                  SB 629
                                                                  Page  4

          proceeds, rather than pay the full contract price up front or  
          not pay anything until after completion.  The general contractor  
          then typically pays any subcontractors a portion of the progress  
          payment.  However, an owner may hold back a certain amount of  
          the payment due, known as "retention proceeds," until 45 days  
          after the work is fully completed.  General contractors may in  
          turn hold retention proceeds owed to the subcontractor until  
          after the entire project is completed.  Retention proceeds have  
          long been used in the construction industry as a means by which  
          owners and general contractors could motivate general  
          contractors and subcontractors, respectively, to complete the  
          work, and to soften the blow if the work is not completed.   
          Although existing law does not place any cap on the percentage  
          of the contract amount that can be held as retention proceeds,  
          current construction industry practices appear to set the amount  
          at about 10% of the amount owed.  Amounts can vary, however,  
          depending upon a number of factors, including the reputation of  
          the subcontractor and the extent to which the subcontractor is  
          bonded.
           
          As most recently amended, this bill would limit retention  
          proceeds to 5% of the value of the contract for any private work  
          of improvement.  In addition, whereas existing law requires  
          release of retention proceeds within 45 days after the "date of  
          completion" - meaning completion of the entire project - this  
          bill would require release of retention proceeds within 45 days  
          after the party seeking payment of proceeds completes the scope  
          of its work under the contract and has served the withholding  
          party with a prescribed demand form.  Recent amendments also  
          clarify that the provisions of this bill do not affect the  
          amounts that may be withheld in the event of a dispute over the  
          performance of the contract, nor would it apply where a lender  
          requires a higher retention proceed as part of a construction  
          loan contract.  Finally, recent amendments clarify that the 5%  
          cap will not apply if the bid request specifies that surety  
          bonds may be required, but the subcontractor is subsequently  
          unable or refuses to provide the bonds. 

           ARGUMENTS IN SUPPORT  :  According to the author, the purpose of  
          this measure is to "halt the counterproductive, unnecessary, and  
          harmful practice of holding back on monies owed on construction  
          projects to primary contractors and subcontractors for work that  
          they have already performed and which has been approved."   
          Noting that under existing industry practices retention proceeds  
          typically equal 10% of the contract price or more, the author  








                                                                  SB 629
                                                                  Page  5

          contends that "retentions in excess of even 5% exceed most  
          contractors' and subcontractors' profit margin and so holding it  
          back means they may not be able to make payroll, provide  
          employee benefits and buy supplies.  This jeopardizes the entire  
          project."  The author also argues that the current practice of  
          not releasing retention proceeds until the entire project has  
          been completed is especially unfair to subcontractors, like  
          earth graders for example, who complete their portion of the  
          work very early on in the life of the project, but do not get  
          paid until much later, when the entire project is complete.  

          This bill is supported by dozens of subcontractor associations  
          and individual companies that perform subcontracting work.  They  
          point to several perceived flaws and inequities in the existing  
          system, but generally their arguments fall into one or more of  
          the following categories:

           For many subcontractors, the 10% retention fee is equal to or  
            greater than a subcontractor's profit margin.  This, along  
            with the fact that proceeds are not released until the entire  
            project has been completed, even if the subcontractor has  
            completed its portion of the work, creates serious cash flow  
            problems.  This may mean that a subcontractor is unable to  
            meet its payroll or buy supplies, thereby potentially delaying  
            completion of the project (and thereby further delaying the  
            eventual release of the proceeds.)

           Retention proceeds ultimately drive up the total costs of  
            construction projects, since both the general and  
            subcontractors must drive up their bids in order to compensate  
            for the cash flow and other problems created by retention  
            proceeds.

           Many supporters of this bill also contend that retention  
            proceeds are not really necessary in the current construction  
            market.  First, supporters argue that existing law already  
            permits an owner or general contractor to withhold 150% of any  
            disputed amount in the event that questions arise over amounts  
            owed or the non-performance or inadequate performance of parts  
            of the contract.  Second, most subcontractors carry surety  
            bonds that protect the owner and general contractor against  
            default or inadequate performance on the part of the  
            subcontractor. 

           Finally, supporters point to trends in the laws governing  








                                                                  SB 629
                                                                  Page  6

            public work contracts and industry guidelines suggesting that  
            retentions proceeds are both unfair and unnecessary.  For  
            example, the federal government has, since 1983, prohibited  
            retention proceeds for any public work projects that it funds.  
             In California, SB 593 (Chapter 341, Stats. of 2008)  
            prohibited Caltrans from withholding retention proceeds from  
            any contractors working on public transportation projects.  In  
            addition, supporters claim, even the guidelines approved by  
            the national Associated General Contractors (ACG) organization  
            provide that "whenever possible, retainage should be  
            eliminated or reduced."  In sum, the state and federal  
            government, as well as the industry itself, recognizes that  
            there are more appropriate alternative means of protecting the  
            investments of owners and general contractors than retention  
            proceeds. 

           ARGUMENTS IN OPPOSITITION  :  This bill is opposed the Associated  
          General Contractors (ACG) of California, the California Business  
          Properties Association, and various builders' associations,  
          though it is not clear at the time of this writing how many of  
          the groups listed as opposition below have changed their  
          position in light of the most recent amendments.  In general,  
          however, the opponents make the following common cluster of  
          arguments:

           Retention proceeds are a long-established practice in the  
            construction industry that protect the considerable  
            investments of property owners and general contractors from  
            defaulting subcontractors; provide incentives for contractors  
            to complete work in a timely manner; and "soften the blow"  
            that the owner or general contractor suffer if the defaulting  
            subcontractor is judgment proof. 

           Retention proceeds always have been, and should remain,  
            negotiable.  Opponents claim that this bill is unnecessary  
            because general contractors will already contract for lower  
            retention proceeds if the subcontractor is someone they have  
            worked with before, has a good reputation, and/or carries  
            sufficient performance and payment surety bonds.  Because  
            every work of private improvement is different, opponents  
            contend, retention proceeds should be negotiated by the  
            contracting parties rather than determined by legislative  
            fiat. 

           Finally, opponents point to a number of specific provisions in  








                                                                  SB 629
                                                                  Page  7

            the language of bill that, they claim, do not adequately  
            address questions about how to determine the proper completion  
            date that triggers the clock for releasing retention proceeds;  
            how the presence or absence of subcontractor surety bonds will  
            affect the limitations on retention proceeds; and how a  
            lender's demand for higher retention proceeds in a  
            construction loan will affect an owner's ability to limit  
            retention proceeds that it withholds from the general  
            contractor.  As noted above, these issues appear to have been  
            addressed in the most recent amendments, though it is not  
            clear if they meet all of the opponents' concerns.  Of the  
            groups that originally opposed this bill, apparently only the  
            California Building Industry Association has agreed to remove  
            its opposition. 

           Possible Committee Amendments  :  Because stakeholders were still  
          negotiating remaining issues in good faith and apparently with  
          considerable progress at the time of this writing, the author  
          may take additional amendments in Committee.  But these  
          productive negotiations have reached a point that any amendments  
          taken in Committee would, mostly likely, involve minor  
          clarifying amendments on the issues noted in the final bullet  
          point listed above. 

           Governor's Veto of AB 1622:   The author, then a member of the  
          Assembly, carried a similar bill in 2006 that, like this bill,  
          capped retention proceeds at 5% of the contract.  That bill,  
          however, included other provisions, including a requirement that  
          the subcontractor earn interest on any retained amounts, has  
          been deleted from the bill presently before the Committee.  In  
          addition, the author has worked with all stakeholders to develop  
          specific language and has managed to remove some opposition,  
          such as that of the California Building Industry Association.   
          Therefore, this is a different and more closely negotiated bill  
          and, as such, more likely to avoid a veto. 

           Related Pending and Recent Legislation  :  AB 396 (Fuentes, this  
          session), among other things, places a 5% cap on retentions for  
          public works.  (Held in Assembly Appropriations Committee.) 

          SB 802 (Leno, this session) prohibits retention proceeds from  
          exceeding 5% of the payment, between a public entity and an  
          original contractor, between an original contractor and a  
          subcontractor, and between all subcontractors on public works  
          projects.  (Pending in Assembly Business & Professions  








                                                                  SB 629
                                                                  Page  8

          Committee.)

          AB 1622 (Liu) (2005/2006) would have capped retention proceeds  
          at 5% in on all contracts for private works of improvement.  The  
          author's prior bill - like earlier versions of the present bill  
          that were removed in the last amendments - contained provisions  
          dealing with interest accrual on withheld retention proceeds.   
          Vetoed. 

          SB 593 (Chapter 341, Stats. of 2008) prohibits the Department of  
          Transportation from withholding retention proceeds when making  
          progress payments for work performed by a contractor on  
          transportation projects.

           REGISTERED SUPPORT / OPPOSITION  :

           Support 
           
          More than seventy-five letters from various companies and  
          subcontractor associations, including the following:

          Over 75 letters of support on file at Senate Judiciary Committee  
          including: 

          California Association of Sheet Metal and Air Conditioning  
          Contractors' National Association
          Union Roofing Contractors Association 
          Engineering and Utility Contractors Association
          Golden State Builders Exchanges
          California chapters of the National Electrical Contractors  
          Association
          California Legislative Conference of the Plumbing, Heating and  
          Piping Industry
          The Blakely Co., INC.
          Burnett & Sons Planing Mill and Lumber CO., INC.
          Henley & CO.
          Rpg Enterprises
          Farrell Design-Build
          Construction Industry Legislative Council 
          A California Corporation 
          All Contractors, Inc. 
          Shapiro-Ben Basat
          American Sheet Metal Partition Co., Inc.
          Painting and Decorating Contractors of California  
           








                                                                 SB 629
                                                                  Page  9

            Opposition  (to pre-amended version)

          Construction Employers Association
          California Building Industries Association
          Associated General Contractors
          California Apartment Association
          California Business Properties Association 
          California Major Builders Council 
          California Retailers Association 
          Santa Barbara Rental Property Association 


           Analysis Prepared by  :   Thomas Clark / JUD. / (916) 319-2334