BILL ANALYSIS                                                                                                                                                                                                    



                                                                  SB 802
                                                                  Page  1

          Date of Hearing:   June 30, 2009

                   ASSEMBLY COMMITTEE ON BUSINESS AND PROFESSIONS
                                 Mary Hayashi, Chair
                  SB 802 (Leno) - As Introduced:  February 27, 2009

           SENATE VOTE  :   35-0
           
          SUBJECT  :   Public contracts:  retention periods. 

           SUMMARY  :   Prohibits a public entity from retaining more than 5%  
          of a contract price until final completion and acceptance of a  
          project.   Specifically,  this bill  :   

          1)Defines "public entity" to mean the state, including every  
            state agency, office, department, division, bureau, board, or  
            commission, the California State University, the University of  
            California (UC), a city, county, city and county, including  
            chartered cities and chartered counties, district, special  
            district, public authority, political subdivision, public  
            corporation, or nonprofit transit corporation wholly owned by  
            a public agency and formed to carry out the purposes of the  
            public agency.


          2)Requires that retention proceeds between an original  
            contractor and a subcontractor, or between two subcontractors,  
            shall not exceed 5% of payment or contract price.  Does not  
            apply if the contractor provides written notice to the  
            subcontractor, prior to or at the time that the bid is  
            requested, that a bond may be required and the subcontractor  
            subsequently is unable or refuses to furnish to the contractor  
            a performance or payment bond issued by an admitted surety  
            insurer.


          3)Provides that these provisions shall apply to all contracts  
            entered into on or after January 1, 2010, between a public  
            entity and an original contractor, between an original  
            contractor and a subcontractor, and between all  
            subcontractors, relating to public works projects.

           EXISTING LAW  : 










                                                                  SB 802
                                                                  Page  2

          1)Requires payments on contracts with progress payments to be  
            made as the awarding department prescribes; provides that  
            state and public agencies shall withhold at least 5% of the  
            contract price until final completion and acceptance of the  
            project, and that progress payments upon public contracts  
            shall not be made in excess of 95% of actual work completed,  
            except as follows:

             a)   At any time after 95% of the work has been completed on  
               a state project, the state may reduce the funds withheld to  
               an amount not less than 125% of the estimated value of the  
               work yet to be completed, as specified.
            
             b)   Allows a public entity to withhold 150% of the value of  
               any disputed amount of work from the final payment.

             c)   At any time after 50% of a local government project is  
               completed and the legislative body finds that satisfactory  
               progress is being made, it may reduce or eliminate  
               withholding.

          2)Provides that retention proceeds between a original contractor  
            and a subcontractor, or between two subcontractors, not exceed  
            the percentage specified in the contract between the public  
            entity and the original contractor, and requires an original  
            contractor to distribute retention proceeds to subcontractors  
            within seven days of receiving retention proceeds from the  
            public agency.

          3)Requires a contractor in a public works contract to file a  
            performance bond with the public entity in specified amounts,  
            depending on the value of the contract.

          4)Requires every original contractor who is awarded a contract  
            by a state entity involving expenditures greater than $5,000  
            for any public works project, to file a performance bond with  
            the state entity in a sun equal to or greater than the  
            contract's total payable amount. 

           FISCAL EFFECT  :   Unknown

           COMMENTS  :   

           Purpose of the bill  .  According to the author's office, "SB 802  
          aims to help smaller California contractors compete for bids on  








                                                                  SB 802
                                                                  Page  3

          public works projects by capping the amount of retention funds  
          which can be withheld.  Existing law requires that not less than  
          5% of the total payment for time and materials on a public works  
          project be withheld (Public Contract Code (PPC) Section 10261).   
          This policy unnecessarily disadvantages small contractors who,  
          on many occasions, find the amount of retention withheld exceeds  
          10% of the total cost of the project.  While this might not  
          sound like much at first, in reality the typical profit margin  
          for the construction industry on these projects is only about 3%  
          or 4%.  This means that contractors must finance up to 7% of the  
          total project on their own dime.  This is a classic pay-to-play  
          scenario in which large contractors benefit and small  
          contractors with fewer resources bear an undue burden.  They  
          must either cover the costs of labor themselves or take out  
          lines of credit while they wait for payments on work completed  
          to be released.  In some cases, contractors pay the interest on  
          loans for years before being fully paid for their work.  

          "As a result of the current retention policy, any contractor who  
          bids on a public works job must anticipate the financing of a  
          substantial portion of the total value of the contract for an  
          undefined period of time.  For example, if a contract is worth  
          $5 million, a small business contractor will have to anticipate  
          taking out a loan of up to $350,000 to cover their payroll and  
          material expenses in building the project.  Many qualified small  
          businesses simply cannot afford to tie up their own capital or  
          operate on costly loans for an indefinite period of time.  This  
          limits the pool of available and willing contractors and keeps  
          otherwise fully qualified and capable contractors from  
          participating."

           Background  .  Retention proceeds represent a percentage of the  
          amount of a contract that is withheld from a progress payment by  
          the public entity to the original contractor, or the original  
          contractor to one its subcontractors.  By withholding a  
          percentage of a contract, the public entity or the original  
          contractor maintains a degree of financial control over a  
          project.  In general, the public entity or the original  
          contractor withholds at least 5% of payment until the contract  
          is completed to the satisfaction of the public entity or  
          original contractor.

          Current law allows for the retention of a percentage of a  
          contract price to guaranty a contractor's completion and  
          acceptance of a project.  All California contractors working on  








                                                                  SB 802
                                                                  Page  4

          a public works project are required to possess performance bonds  
          that cover up to 150% of the cost of any disputed work.   
          Contractors have an incentive to complete projects without  
          conflict, because it becomes more difficult to find a bonding  
          agency willing to bond a contractor who has failed a project.  

          Performance bonds can be one option a public entity uses to  
          guarantee that a project will continue to proceed, should a  
          contractor fail.  If a contractor does not meet the contract  
          obligations and the public entity seeks to use the performance  
          bonds, the bonding company will seek selects the replacement  
          contractor to complete the remainder of the contract obligations  
          at the lowest cost.  

          According to the author's office, the following states have  
          capped retention rates at 5%:  Arizona, Delaware, Hawaii, Idaho,  
          Iowa, Maine, Massachusetts, Minnesota, Mississippi, Missouri,  
          Montana, New York (for bonded contractors), Oregon, Rhode  
          Island, Utah, Virginia, and Washington. 

          Supporters argue that retention ties up capital in the current  
          economy and that there are already many protections in place to  
          guarantee project completion.  The sponsor contends that failure  
          to complete a project ruins a contractor's reputation and  
          results in occupational suicide.  According to supporters, in  
          order for contractors to compensate for the additional loan  
          interest for labor and materials resulting from retention,  
          contractors may factor in these costs in their contract bids and  
          therefore increase taxpayer costs for a project.  The sponsor  
          also notes that the federal government does not use retention on  
          Caltrans projects and that some cities and counties already cap  
          retention at 5%.  

          Opponents argue that schools need a guarantee that projects will  
          be completed on time because schools need to be built according  
          to strict specifications because they are also used as emergency  
          shelters.  Opponents contend that schools will usually leave a  
          "punch list" of outstanding concerns to work with the contractor  
          towards the end of a project as to not hold the project up; the  
          opponents claim that discretionary retention is appropriate  
          because retention of 5% or less, depending on the situation, may  
          not be financially enough to commit the contractor to complete  
          the remainder of the project according to specifications.  

           Arguments in support  .  According to the sponsors, "Current state  








                                                                  SB 802
                                                                  Page  5

          law requires the withholding from contractors of not less than  
          5% of the contract price.  Often times this retention amount can  
          be as much as 10% or more.  The typical profit margin in the  
          construction industry for public works projects is 3%.  In some  
          cases, contractors must wait for years before being fully paid  
          for their work.  Thus, any contractor who bids on a public works  
          job must anticipate the financing of as much as 7% of the total  
          value of the contract for an undefined period of time just to  
          make payroll and pay suppliers.  This includes a non-reliance on  
          the realization of a 3% profit? 

          "The current payment retention policy constitutes an unfair and  
          unreasonable requirement for licensed, responsible and bonded  
          California contractors.  The total cost to taxpayers for public  
          works improvement projects increase as a result of 1) the loss  
          of bids from qualified local small businesses, and 2) the bid  
          inflation that occurs due to the fact that the cost of these  
          capital loans are built into the cost of the project.  

          "Public agencies are protected from problems associated with  
          contractor 'non-compliance' through a variety of mechanisms  
          rendering the existing retention codes obsolete.  In fact under  
          PCC Section 20129, contractors on public works of improvement  
          must post 'performance bonds' to ensure completion of the  
          project.  Further, PCC Section 7107 allows a public agency to  
          withhold an amount up to 150% of the value of the disputed work  
          from the final payment.  These protections, pre-qualification  
          procedures and others allow public agencies more than adequate  
          assurances of contractor compliance." 

          According to the California Landscape Contractors Association  
          (CLCA), "For many smaller contractors, delays in final payment  
          can be fatal if credit is unavailable or the delay becomes so  
          lengthy that interest expenses erase anticipated profits.  CLCA  
          believes that retention amounts of more than 5% are unnecessary  
          to ensure satisfactory performance of a contract because of the  
          overlapping protections provided by the performance bond.  We  
          also note that CalTrans, which has eliminated retentions on  
          federally-funded highway projects, has not encountered any  
          difficulties with contractor performance.  In addition, because  
          of the risk of a long retention of proceeds after completion of  
          a public works project, contractors tend to factor these  
          additional costs into their bids resulting in taxpayer costs  
          that are higher than necessary.









                                                                  SB 802
                                                                  Page  6

          "Reforms in public works retention policy are particularly  
          needed now because of tight credit markets and the need to  
          expeditiously bid and award infrastructure projects targeted for  
          federal stimulus funding.  The need for this bill is  
          particularly acute for small contractors who lack the capital  
          and credit needed to survive excessive retentions and long  
          payment delays." 

          According to the State Building and Construction Trades Council,  
          "Cities and counties using design-build authorization are  
          required to hold no more than 5% retention on contractors and  
          recently the UC changed their construction practices to withhold  
          only 5% retention on its public works projects." 

          According to CSI Electrical Contractors, Inc., "The practice of  
          holding retention, along with performance bonding, forces  
          contractors to cover the costs of financing projects long after  
          the work has been approved and accepted.  Under current law, a  
          contractor is by common practice on public works, paid 90 cents  
          on the dollar for work completed and accepted, but has a  
          financial obligation close to 100 cents on the dollar.  These  
          obligations include meeting payroll, paying employee benefits,  
          paying material suppliers and all taxes on the value of the work  
          completed."

          According to the Engineering & Utility Contractors Association  
          (EUCA) and Golden State Builders Exchanges (GSBE), "SB 802  
          increases competition by allowing highly qualified California  
          contractors to bid on infrastructure jobs without being forced  
          to finance up to 7% of the total cost of the project.  This  
          measure also directs more of our taxpayer supported bond revenue  
          to purchase actual bricks-and-mortar infrastructure versus being  
          spent on costly interest rates to banks." 

           Arguments in opposition  .  According to California's Coalition  
          for Adequate School Housing, "School districts, in good faith,  
          negotiate contract provisions and typical retention amounts are  
          negotiated at approximately 10% of the contract value. If a  
          contractor and a public agency wish to limit retention proceeds  
          to 5% - as the bill seeks to achieve - current law allows for  
          it.
          Retention is necessary for public agencies to ensure 1) prompt  
          completion of a project; 2) that contractors return to a project  
          to complete all contract requirements, including small  
          unprofitable punch list items; 3) there are sufficient funds for  








                                                                  SB 802
                                                                  Page  7

          public agencies to correct defective work if a contractor fails  
          to do so; and 4) to have sufficient funds withheld in order to  
          pay workers in the event contractors have failed to properly pay  
          prevailing wage as required by state law. By prohibiting  
          contract withholdings from exceeding 5%, and removing the  
          flexibility to negotiate a good faith provision between a public  
          agency and a contractor, SB 802 significantly thwarts an  
          agency's ability to ensure that the provisions of their public  
          works contracts are fully executed.

          "Finally, contractors are currently provided the protection  
          intended by SB 802.  Existing statute requires public agencies  
          to make timely payments of both progress payments and final  
          payments unless there is a legitimate dispute over work.   
          Additionally, contractors may opt to place all retention in a  
          contractor-established escrow account and to receive the  
          interest from that account." 

          According to the California State Association of Counties (CSAC)  
          and the League of California Cities (League), the "bill removes  
          the authority of public entities to decide the appropriate  
          amount of retention?local agencies must accept the lowest  
          responsible bidder and the flexible retention rate helps to  
          ensure timely and budget-conscious project completion.  Local  
          agencies commonly reduce retention to 5% at the half-way point  
          of project completion, if adequate progress is being made and  
          the contractor is acting in good faith.  However, SB 802 would  
          require local agencies to limit retention to 5% regardless of  
          the progress or good faith of the contractor, thus protecting  
          bad actions unknown or even known to the public agency, placing  
          public interests and public funds at risk. 

          "CSAC and the League have had many discussions in recent years  
          regarding similar proposals (AB 1949:  Conroy, 1996, vetoed; AB  
          940:  Miller, 1997, vetoed; AB 806:  Keeley, 1999, vetoed; and,  
          SB 619:  Migden, 2008, held); however, we continue to express  
          concern over these measures because we have yet to see specific  
          examples where 10% retention is problematic.  On the other hand,  
          we have specific examples from cities and counties opposed to  
          these proposals because in certain instances current retention  
          of 10% is inadequate." 

          According to a project manager for the Fresno Unified School  
          District (FUSD), she has "worked in the Public Works arena for  
          FUSD for over 14 years... (and has) personally been involved in  








                                                                  SB 802
                                                                  Page  8

          numerous projects (where) a 5% withholding would not be enough  
          to compensate the District, subcontractors or employees in the  
          event of a failure on the part of the general contractor to  
          fulfill his contract responsibilities.  Many times, the State of  
          California is dependent on those retention monies to pay back  
          wages or penalties imposed by the Department of Industrial  
          Relations." 

          According to the South Bay Cities Council of Governments,  
          "Cities use retention in public contracts because it helps  
          assure that work is done in compliance with the contract  
          document and serves as a financial incentive for contractors to  
          complete a project.  In addition, should a contractor fail to  
          perform or not complete the project, the retention funds can be  
          used to cover the cost of project completion.  For many local  
          agencies, it is also common practice to reduce the retention  
          rate midway through a project to reward efficient project  
          completion.  Either way, local control over retention rates  
          should be retained as a tool to ensure project completion is  
          on-time and within budget." 

          According to the California Association of School Business  
          Officials, "Lowering the retention amount to 5% will make it too  
          easy for unscrupulous contractors to simply cut their losses and  
          move on if they choose not to complete a project.  What's more  
          is that under current provisions, the 10% retention proceeds are  
          often put into escrow and collect interest for the contractor  
          during the project.  The incentive to live up to a contract is  
          greater under current law than under SB 802 if it becomes law." 
          
           Related Legislation  . 

          AB 396 (Fuentes) modifies, recasts and, consolidates various  
          provisions governing the timely payment of progress payments,  
          retention proceeds, and final payments under a contract for a  
          public or private work of improvement.  This bill was held in  
          the Assembly Appropriations Committee.
          
          SB 629 (Liu) is a similar bill, prohibits retention proceeds  
          withheld form any payment made by an owner to the original  
          contract from exceeding five percent of the amount otherwise due  
          under the contract, applicable to all contracts entered into on  
          or after January 1, 2010.  This bill is currently pending in the  
          Assembly Rules Committee. 









                                                                  SB 802
                                                                  Page  9

           Previous Legislation  .  

          SB 619 (Migden) of 2007 was an identical bill, was held by the  
          sponsor on the Senate Floor to continue working with the  
          Administration.  

          SB 593 (Margett), Chapter 341, Statutes of 2008, prohibits the  
          Department of Transportation from withholding retention proceeds  
          to its contractors when making progress payments for work  
          performed on a public works project.

          AB 806 (Keeley) of 1999 would have limited retention proceeds on  
          public works contracts to 5%, and prohibits the state, including  
          all state agencies and political subdivisions of the state,  
          contractors, and subcontractors from withholding more than 5% of  
          a scheduled payment on a public works contract.  AB 806 was  
          vetoed by the Governor. 

          AB 2084 (Miller), Chapter 857, Statutes of 1998, provides that  
          the percentage of retention proceeds withheld by a contractor  
          from a subcontractor may not exceed the overall retention  
          percentage specified in the public works contract  between the  
          contractor and the public agency builder.

          AB 940 (Miller) of 1997 would have, among other things, limited  
          retention payments by public entities on public works to 5  
          percent.  AB 940 was vetoed by Governor Wilson, who made the  
          following statements in his veto message:

          "Regrettably, once again, I find a bill before me that  
          establishes a double-standard for the treatment of the retention  
          levels charged by public agencies.  The private sector is free  
          to establish its own level for retention in an open marketplace,  
          where building owners, contractors and subcontractors freely  
          enter into construction contracts, which often include a 10%  
          retention level.  Here before me is a bill which would  
          arbitrarily restrict public agencies to retention rates of half  
          the private sector standard.

          "As I expressed in my veto message of AB 1949 (Conroy) last  
          year, 'Government agencies must be able to protect public  
          construction projects from unnecessary risk in a fashion similar  
          to the private sector.'  I have not deviated from that stance.   
          As a public manager, I believe it is reasonable to ask public  
          agencies to manage public works projects according to the same  








                                                                  SB 802
                                                                  Page  10

          standards, criteria and level of professionalism as is practiced  
          in the private sector.  It would be irresponsible of me,  
          however, to tie the hands of public agencies with statutory  
          restrictions and expect a similar performance standard.

          AB 1949 (Conroy) of 1996, would have, among other things,  
          limited retention payments by public entities on public works to  
          5%.  AB 1949 was vetoed by Governor Wilson.

           REGISTERED SUPPORT / OPPOSITION  :

           Support 
           
          California Association of Sheet Metal and Air Conditioning  
          Contractors' National Association (CAL SMACNA) (sponsor) 
          California Legislative Conference of the Plumbing, Heating, and  
          Piping Industry (sponsor) 
          Abdulaziz, Grossbart & Rudman
                                                                                         ACH Mechanical Contractors, Inc. 
          AGC, Inc. 
          Air Conditioning Sheet Metal Association 
          Air-conditioning & Refrigeration Contractors Association (ARCA) 
          Air-Ex Air Conditioning, Inc. 
          American Subcontractors Association California, Inc. 
          Associated Plumbing & Mechanical Contractors of Sacramento
          Best Electrical Company
          Building Industry Credit Association 
          Cadri Company Inc. 
          California Chapters of the National Electrical Contractors  
          Association (NECA) 
          California Fence Contractors' Association, California Chapter
          California Landscape Contractors Association (CLCA) 
          Champion Industrial Contractors, Inc. 
          Chula Vista Electric Company
          Collins Electrical Company, Inc.
          Construction Industry Legislative Council (CILC)
          Critchfield Mechanical, Inc. 
          CSI Electrical Contractors, Inc. 
          Desert Air Conditioning, Inc. 
          Dynalectric Company
          Electric Cal Partners, Inc. 
          Engineering & Utility Contractors Association (EUCA) 
          Engineering Contractors' Association 
          Flasher/Barricade Association 
          Foothill Air Conditioning and Heating, Inc. 








                                                                  SB 802
                                                                  Page  11

          Glendale Unified School District
          Golden State Builders Exchanges (GSBE) 
          Heating & Air Conditioning, Inc. 
          Industrial High Voltage
          L&H Airco
          Lupen and Hawley, Inc. 
          Marin Builders' Association 
          Mendenhall Mfg., Inc. 
          Mike Brown Electric Co. 
          Power Communication Systems, Inc. 
          Precision Air Balance Co., Inc. 
          Ray L Hellwig Mechanical
          Ray Scheidts Electric Inc. 
          R.I.S. Electrical Contractors, Inc. 
          Schetter Electric, Inc.
          Smith Heating & Air
          State Building and Construction Trades Council, AFL-CIO 
          Southern Contracting Company 
          Tardif Sheet Metal and Air Conditioning, Inc. 
          Thermal Mechanical, Inc. 
          Western Air Limbach LP 
          Western Allied Mechanical, Inc.
           
            Opposition 
           
          California's Coalition for Adequate School Housing (CASH) 
          Anaheim City School District
          Association of California School Administrators (ACSA)
          Bonita Unified School District 
          California Association of School Business Officials (CASBO)
          California Special Districts Association (CSDA)
          California State Association of Counties (CSAC) 
          Colbi Technologies, Inc. 
          Dry Creek Joint Elementary School District 
          Dublin Unified School District
          El Dorado Irrigation District
          Evergreen School District 
          Fremont Unified School District
          Fresno Unified School District 
          Glendale Unified School District
          Global Business Solutions, Inc. 
          Hemet Unified School District
          Hibser Yamauchi Architects, Inc. 
          Humboldt County Office of Education
          League of California Cities (League) 








                                                                  SB 802
                                                                  Page  12

          Liberty Union High School District
          Los Angeles Unified School District (LAUSD)
          Milpitas Unified School District 
          Morgan Hill Unified School District
          New Haven Unified School District 
          Norwalk - La Mirada Unified School District
          Oceanside Unified School District
          Palo Verde Unified School District  
          Pleasanton Unified School District
          RGM and Associates 
          Rowland Unified School District 
          Saddleback Valley Unified School District 
          San Bernardino City Unified School District 
          San Ramon Valley Unified School District 
          Sanger Unified School District 
          SCArchitect, Inc. 
          SGI Construction Management (SGI)
          Sierra Sands Unified School District
          Solano County Board of Supervisors 
          South Bay Cities Council of Governments (SBCCOG) 
          Tahoe Truckee Unified School District 
          Three Valleys Municipal Water District 
          Travis Unified School District 
          Victor Elementary School District
          Visalia City Council 
          Western Placer Unified School District 
          Yosemite Community College District

           Analysis Prepared by  :    Joanna Gin / B. & P. / (916) 319-3301