BILL ANALYSIS                                                                                                                                                                                                    



                                                                  SB 879
                                                                  Page  1

          Date of Hearing:  June 16, 2010

                       ASSEMBLY COMMITTEE ON LOCAL GOVERNMENT
                                Cameron Smyth, Chair
                       SB 879 (Cox) - As Amended:  May 27, 2010

           SENATE VOTE :  24-8
           
          SUBJECT  :  Counties: cities: construction projects: alternative  
          bidding procedures: design-build.

           SUMMARY :  Extends the sunset for the use of design-build by  
          counties from January 1, 2011, 
          to January 1, 2016, and aligns the design-build statutes for  
          cities and counties.  Specifically, 
           this bill  :   

          1)Extends the sunset for the use of design-build by counties  
            from January 1, 2011, to 
          January 1, 2016.

          2)Reduces the project cost threshold for county use of  
            design-build from $2.5 million per project to $1 million per  
            project.  

          3)Requires the design-build standard questionnaire issued by  
            cities or counties to include any instance in which the  
            entity, or any of its members, owners, officers, or managing  
            employees was, during the five years preceding submission of a  
            bid pursuant to this section, determined by a court of  
            competent jurisdiction to have submitted, or legally admitted  
            for purposes of a criminal plea to have submitted any claim in  
            violation of the federal False Claims Act or the state False  
            Claims Act.

          4)Requires for city and county design-build projects, lists of  
            subcontractors, bidders, and bid awards relating to the  
            project to be submitted by the design-build entity to the  
            awarding body within 14 days of the award.  These documents  
            are deemed to be public records and are required to be  
            available for public inspection pursuant to this chapter and  
            the Public Records Act.

          5)Removes the requirement that certain specified minimum factors  
            be weighted equally when cities are evaluating competitive  








                                                                  SB 879
                                                                  Page  2

            proposals.

          6)Requires each county that uses the design-build method on a  
            public works project to submit to the Legislative Analyst's  
            Office (LAO) before December 1, 2014,  a report containing a  
            description of each public works project procured through the  
            design-build process and completed after November 1, 2009,   
            and before November 1, 2014.

          7)Requires the LAO, by January 1, 2015, to do another report to  
            the Legislature on the use 
          of design-build at the county level.  

          8)Requires cities that elect to use design-build to report to  
            the LAO the estimated and actual length of time to complete  
            the project.

           

          EXISTING LAW  :

          1)Requires local officials, under the Local Agency Public  
            Construction Act, to invite bids 
          for construction projects and then award contracts to the lowest  
            responsible bidder under the traditional design-build project  
            delivery system.

          2)Defines "design-build" as a procurement process in which both  
            the design and construction of a project are procured from a  
            single entity.

          3)Defines "best-value" as a value determined by objective  
            criteria related to price, features, functions, and life cycle  
            costs.

          4)Defines "project" as the construction of a building and  
            improvements directly related to the construction of a  
            building, and specifies that construction of other  
            infrastructure, including, but not limited to, streets and  
            highways, public rail transit, or water resources facilities  
            and infrastructure are not to be considered "projects."

          5)Authorizes counties to use the design-build method for  
            projects costing more than 
          $2.5 million.  








                                                                  SB 879
                                                                  Page  3


          6)Authorizes cities to use the design-build method for projects  
            costing more than $1 million.

          7)Authorizes the Sonoma Valley Health Care District to use  
            design-build contracting for the construction of buildings and  
            improvements in excess of $2.5 million directly related to a  
            hospital or health facility building, which is required to be  
            reviewed and inspected according to the standards of the  
            Alfred E. Alquist Hospital Facilities Seismic Safety Act of  
            1983.

          8)Authorizes the Orange County Sanitation District to use  
            design-build contracting for projects, including, but not  
            limited to, public wastewater facilities, in excess of $6  
            million.

          9)Authorizes the Santa Clara Valley Water District to use  
            design-build contracting for building contracts.

          10)Requires local officials to prepare documents describing the  
            project and its specifications; 
          to prepare a detailed request for proposals that invites  
            competitive bids; to establish a detailed procedure to  
            pre-qualify design-build entities; and, to establish the  
            procedures to select the design-build entity.

          11)Requires the legislative body to establish and enforce labor  
            compliance programs.

          12)Requires local officials to collect specified types of  
            information when pre-qualifying design-build entities.

          13)Requires a prospective design-build entity to list its  
            proposed mechanical subcontractors and licenses; report past  
            worker safety violations, contracting problems, contract  
            defaults, license violations, payroll violations, and  
            bankruptcies; and, verify this information under oath.

          14)Requires local officials to select the design-build entity by  
            using either a competitive bidding process in which the award  
            goes to the lowest responsible bidder or a best value  
            competition in which local officials set the criteria.

          15)Requires that price, expertise, life cycle costs, skilled  








                                                                  SB 879
                                                                  Page  4

            labor force availability, and safety records account for at  
            least 10% each of the total weight of consideration of all  
            best value factors.

          16)Requires the local agency to rank the top three responsive  
            bidders; award the contract to the responsible bidder whose  
            proposal county or city officials rank as "the most  
            advantageous;" and, identify the second- and third-ranked  
            bidders after it publicly announces the award.

          17)Requires that skilled labor force availability be determined  
            by the existence of an agreement with a registered and  
            approved apprenticeship program.

          18)Requires the winning design-build entity to be bonded and  
            carry errors-and-omissions insurance to cover its design and  
            architectural services.

          19)Requires the entity to adhere to the local agency's  
            performance criteria and design standards and obtain the local  
            agency's written consent for any deviations from these  
            standards, and authorizes the local agency to hire a design  
            professional to ensure compliance.

          20)Authorizes the winning design-build entity to use  
            subcontractors not listed in its original bid, but requires  
            the entity to award these subcontracts by following a process  
            set by the local agency, including publishing notices and  
            setting deadlines.

          21)Permits the local agency to retain no more than 5% of the  
            contract if the local agency's bid request required the  
            design-build entity to carry a performance and payment bond.

          22)Requires any local agency that uses design-build contracting  
            to submit a report to the LAO containing specified information  
            that includes, but is not limited to, a description of the  
            Labor Force Compliance Program and an assessment of the  
            project impact of "skilled labor force availability."

          23)Repeals the authorization for counties, the Orange County  
            Sanitation District, the Santa Clara Valley Water District,  
            and the Sonoma Valley Health Care District to use design-build  
            contracts on January 1, 2011.  









                                                                  SB 879
                                                                  Page  5

          24)Repeals the authorization for cities to use design-build  
            contracts on January 1, 2016.

           FISCAL EFFECT  :  Unknown

           COMMENTS  :   

          1)The Local Agency Public Construction Act requires local  
            officials to invite bids for construction projects and then  
            award contracts to the lowest responsible bidder.  This  
            design-bid-build method is the traditional approach to public  
            works construction.

          2)Private companies often use the design-build method for  
            construction projects.  Under the design-build method, a  
            single contract covers the design and construction of a  
            project with a single company or consortium that acts as both  
            the project designer and builder.  The design-build entity  
            arranges all architectural, engineering, and construction  
            services, and is responsible for delivering the project at a  
            guaranteed price and schedule based upon performance criteria  
            set by the public agency.  The design-build method can be set  
            by the public agency.  The design-build method can be faster,  
            and therefore, cheaper, than the design-bid-build method, but  
            it requires a higher level of management sophistication since  
            design and construction may occur simultaneously.

          3)Advocates for the design-build method of contracting for  
            public works contend that project schedule savings can be  
            realized because only a single request for proposals is needed  
            to select the project's designer and builder.  The more  
            traditional design-bid-build project approach requires the  
            separate selection of the design consultant or contractor,  
            completion 
          of design, and then advertising for bids and selection of the  
            construction contractor.  Proponents add that design-build  
            allows the overlap of design and construction activities,  
            resulting in additional time savings and lower project costs.   
            By avoiding the delays and change orders that result from the  
            traditional design-bid-build method of contracting, proponents  
            argue that officials can deliver public works faster and  
            cheaper.

          4)The design-build language in current law is based on a  
            compromise struck in 2000 among local officials, labor groups,  








                                                                  SB 879
                                                                  Page  6

            and contractors.  Local officials wanted the flexibility and  
            potential cost savings offered by design-build contracts.   
            Labor unions wanted to ensure that counties pre-qualify  
            employers to protect workers' interests.  Contractors wanted  
            to be sure they had fair access to county contracts.  Further  
            changes to the language, consistent with the principles of the  
            2000 compromise were made by SB 287 (Cox), Chapter 376,  
            Statutes of 2005; SB 416 (Ashburn), Chapter 585, Statutes  
            2007, which extended this authority to use design-build  
            contracting for the construction of buildings and directly  
            related improvements to all 58 counties in the state; AB 642  
            (Wolk), Chapter 314, Statues 2008, which extended this  
            authority to use design-build contracting for the construction  
            of buildings and directly related improvements to all cities  
            in the state; and, SB 1699 (Wiggins), Chapter 415, Statutes of  
            2008, which extended this authority to use design-build  
            contracting for the construction 
          of buildings and improvements in excess of $2.5 million directly  
            related to a Sonoma Valley Health Care District hospital or  
            health facility building.

          5)The LAO issued a report to the Legislature on February 3,  
            2005, titled "Design-Build: An Alternative Construction  
            System."  After analyzing the claims of proponents and  
            opponents and reviewing the experience of counties that were  
            authorized to use design-build at the time, LAO recommended  
            "the Legislature grant design-build authority only to  
            buildings and directly related infrastructure.  There are more  
            complex issues associated with other public works projects  
            such as transportation, public transit, and water resources  
            facilities.  Evaluation of design-build as a construction  
            delivery option for these other infrastructure facilities is  
            beyond the scope of this report." 

            In January of this year the LAO issued a second report, this  
            time updating the Legislature on the use of design-build by  
            counties in California, based on data received from counties  
            who utilized this methodology.  In the report, LAO states that  
            "although it was difficult to draw conclusions from the  
            reports received about the effectiveness of design-build  
            compared to 

            other project delivery methods, we do not think that the  
            reports provide any evidence that would discourage the  
            Legislature from granting design-build authority to local  








                                                                  SB 879
                                                                  Page  7

            agencies on an ongoing basis.  In doing so, however, we  
            recommend the Legislature consider some changes such as  
            creating uniform design-build statute, eliminating cost  
            limitations, and requiring project cost to be a larger factor  
            in awarding the design-build contract."

           6)Support Arguments  :  The County of Sacramento, in its letter of  
            support, reports that the Sacramento County Airport System has  
            been using design-build construction method for several years  
            to design and construct the New Central Terminal B at  
            Sacramento International Airport ( a county ran airport).   
            Without the use of design-build for this project, there would  
            have been an additional $100 to $150 million dollars in  
            project costs. 
           
             According to the California State Association of Counties  
            (CSAC) and the Regional Council for Rural Counties (RCRC),  
            approximately nine counties have used or plan to use the  
            design-build method for project delivery for a variety of  
            projects ranging from parking facilities to parks and  
            recreation projects to fire stations to name a few.  CSAC and  
            RCRC argue that "counties and taxpayers in general benefit  
            from the use of design-build authority resulting from cost  
            savings produced by this method of project delivery." 

             Opposition Arguments  :  The American Federation of State,  
            County and Municipal Employees (AFCSME), AFL-CIO, in its  
            letter of opposition states that "in the last year,  
            design-build has been extended to redevelopment agencies,  
            state buildings, wastewater systems, and correctional  
            facilities.  The Legislature should let these projects  
            proceed, finish, and play out, to get a broader sense of  
            cost-effectiveness and efficiency of the system before  
            contemplating new authorization for a comprehensive  
            design-build program."

            AFCSME goes on to say that it "does not believe the  
            design-build program to be faster, cheaper, or any more  
            innovative for the taxpayer than traditional contract bidding.  
             AFCSME believes this contracting system to be much less  
            cost-effective because we end up having a small group of  
            individuals having authority to grant large public contracts  
            to [a] small group of  hand-picked firms from the private  
            sector essentially eliminating competitive bidding." 









                                                                  SB 879
                                                                  Page  8

           
















          REGISTERED SUPPORT / OPPOSITION  :

           Support 
           
          American Institute of Architects, CA Council
          CA Chamber of Commerce
          CA Special Districts Association
          CA State Association of Counties
          CA State Sheriffs' Association
          CH2M Hill
          Counties of Imperial, Monterey, Orange, Sacramento, San  
          Bernardino, Santa Clara, 
               and San Diego
          Design-Build Institute of America, Western Pacific Region
          Greater Riverside Chambers of Commerce
          Regional Council of Rural Counties
          Santa Clara Valley Water District
           
            Neutral
           
          Associated Builders and Contractors of CA

           Opposition 
           
          American Federation of State, County and Municipal Employees,  
          AFL-CIO
          CA State Pipe Trades Council
          Professional Engineers in CA Government 








                                                                  SB 879
                                                                  Page  9

          Service Employees International Union CA State Council
          State Association of Electrical Workers
          Western States Council of Sheet Metal Workers

           Analysis Prepared by  :    Katie Kolitsos / L. GOV. / (916)  
          319-3958