BILL ANALYSIS                                                                                                                                                                                                    Ó



                                                                  AB 1671
                                                                  Page  1

          Date of Hearing:   April 10, 2012 

              ASSEMBLY COMMITTEE ON BUSINESS, PROFESSIONS AND CONSUMER 
                                     PROTECTION
                                 Mary Hayashi, Chair
                AB 1671 (Huffman) - As Introduced:  February 14, 2012
           
          SUBJECT  :   Department of Transportation: retention proceeds.

           SUMMARY  :   Extends, until January 1, 2012, the sunset date 
          prohibiting the Department of Transportation (CalTrans) from 
          withholding retention proceeds to its contractors when making 
          progress payments for work performed on a public works project, 
          and makes legislative findings and declarations. 

           EXISTING LAW  :

          1)Prohibits, until January 1, 2014, CalTrans from withholding 
            retention proceeds to its contractors when making progress 
            payments for work performed on a public works project.

          2)Provides that in a contract between the original contractor 
            and a subcontractor, and in a contract between a subcontractor 
            and any other subcontractor, the percentage of retention 
            proceeds withheld cannot exceed the percentage specified in 
            the contract between the public entity and the original 
            contractor, and requires the distribution of retention 
            proceeds by an original contractor to subcontractors within 
            seven days of receipt of retention proceeds from the public 
            agency.

          3)Requires a contractor in a public works contract to file a 
            performance bond with the public entity in specified amounts 
            depending on the value of the contract.

          4)Requires every original contractor who is awarded a contract 
            by a state entity involving expenditures in excess of $5,000 
            for any public work to file a performance bond with the state 
            entity in a sum not less than 100% of the total amount payable 
            by the terms of the contract.

           FISCAL EFFECT  :   Unknown

           COMMENTS  :   









                                                                  AB 1671
                                                                  Page  2

           Purpose of this bill  .  According to the author's office, 
          "Section 7202 of the Public Contracts Code was added in 2008 by 
          SB 593 (Margett), Chapter 341, Statutes of 2008.  SB 593 
          eliminated retention on all CalTrans' construction contracts and 
          contained a January 1, 2014 sunset date.  CalTrans reports that 
          this provision has worked well since its enactment and that they 
          have experienced no problems.  Since this provision has worked 
          well and because zero percent retention is important to every 
          contractor working on a CalTrans' project, this bill extends the 
          sunset provision until January 1, 2020." 
          
           Background  .  Retention proceeds represent a percentage of the 
          amount of a contract that is withheld from a progress payment by 
          the public entity to the original contractor, or the original 
          contractor to one its subcontractors.  By withholding a 
          percentage of a contract, the public entity or the original 
          contractor maintains a degree of financial control over a 
          project.
          
          CalTrans does not withhold retention proceeds on federally 
          funded projects on progress payments between CalTrans and its 
          prime contractors, and its contractors and their subcontractors. 
           SB 593 (Margett), Chapter 341, Statutes of 2008, prohibited 
          CalTrans from withholding retention proceeds to its contractors 
          when making progress payments for work performed on a public 
          works project until January 1, 2014.  While state-funded 
          projects account for a small percentage of CalTrans projects, SB 
          593 conformed both state and federal laws so there is zero 
          withholding for all contracts, easing the financial 
          administration of those contracts.  

           Support  .  According to sponsors, "Government agencies have 
          historically withheld 10% of the total contract price until all 
          of the work on the project has been completed.  Since the law 
          has always required contractors to file payment and performance 
          bonds to guarantee both the completion of the work and to ensure 
          that all workers and subcontractors have been paid, retentions 
          are unnecessarily burdensome on contractors.  Profit margins on 
          these contracts typically do not exceed two to four percent at 
          best, so retention creates significant cash flow problems for 
          many contractors. 

          "To address this issue, SB 593 (Margett) was signed into law in 
          2008, Ýprohibiting] CalTrans, until January 1, 2014, from 
          withholding retention proceeds to its contractors when making 








                                                                  AB 1671
                                                                  Page  3

          progress payments for work performed on any transportation 
          project? CalTrans has not experienced any problems since the 
          enactment of SB 593, and this bill proposes to extend that 
          sunset date until January 1, 2020.
          
           Previous Legislation  . SB 593 (Margett), Chapter 341, Statutes of 
          2008, prohibited, until January 1, 2014, CalTrans from 
          withholding retention proceeds to its contractors when making 
          progress payments for work performed on a public works project.
                                          
           REGISTERED SUPPORT / OPPOSITION  :   

           Support 
           
          Associated General Contractors (co-sponsor)
          California Fence Contractors' Association (co-sponsor) 
          Engineering Contractors' Association (co-sponsor) 
          Flasher Barricade Association (co-sponsor)  
          Marin Builders' Association (co-sponsor)
          Southern California Contractors Association (co-sponsor) 
          United Contractors (co-sponsor)
          Air Conditioning and Refrigeration Contractors Association
          Air Conditioning and Sheet Metal Association
          American Subcontractors Association of California
          Building Industry Credit Association
          California Concrete Contractors Association
          California Landscape Contractors Association 
          California Landscape and Irrigation Council
          California Legislative Conference of the Plumbing, Heating and 
          Piping Industry 
          California Precast Concrete Association
          Eberhard Roofing
          National Electrical Contractors Association, California Chapters
          State Building and Construction Trades Council

           Opposition 
           
          None on file. 
           
          Analysis Prepared by  :    Joanna Gin / B.,P. & C.P. / (916) 
          319-3301 












                                                                  AB 1671
                                                                 Page  4