BILL ANALYSIS                                                                                                                                                                                                    Ó          1







                SENATE ENERGY, UTILITIES AND COMMUNICATIONS COMMITTEE
                                 ALEX PADILLA, CHAIR
          

          AB 1990 -  Fong                                   Hearing Date:  
          July 3, 2012               A
          As Amended:         June 26, 2012            FISCAL       B

                                                                        1
                                                                        9
                                                                        9
                                                                        0

                                      DESCRIPTION
           
           Current federal law  grants exclusive authority to the Federal 
          Energy Regulatory Commission (FERC) over wholesale electric 
          rates in interstate commerce except where an investor-owned 
          utility (IOU) purchases electricity from a qualifying facility 
          at the incremental costs to an electric utility of electric 
          energy or capacity or both which, but for the purchase from the 
          qualifying facility such utility would generate itself or 
          purchase from another source.  This is commonly referred as the 
          "avoided cost" and it does not apply to local publicly-owned 
          utilities (POUs).

           Current law  requires all IOUs and POUs, that serve more than 
          75,000 retail customers, to develop a standard contract or 
          tariff (aka feed-in-tariff or FiT) available for renewable 
          energy facilities up to three megawatts (MWs).  Statewide 
          participation is capped at 750 MWs. 

           Current law  requires the FiT contract price for IOUs to include 
          all current and anticipated environmental compliance costs, 
          including but not limited to, mitigation of emissions of 
          greenhouse gases and air pollution offsets associated with the 
          operation of new generating facilities in the local air 
          pollution control or air quality management district where the 
          electric generation facility is located.

           This bill  requires IOUs and POUs to offer a FiT for facilities 
          sized up to 500 kilowatts (kWs) that are located in, and that 
          encourage the hiring of employees from, the state's most 
          impacted and disadvantaged communities at tariff rates that are 
          sufficient to stimulate market demand for the FiT and to achieve 
          the targets and benefits of the program while maintaining 









          ratepayer indifference.  The program cost would be capped at 
          0.375% of the total cost of each utility's forecast retail sales 
          in 2020.

           This bill  establishes a procurement goal of 375 MWs for IOUs and 
          375 MWs for POUs over six years to be allocated in proportion to 
          each utility's percentage share of the state's total peak demand 
          and for contracts of 20 years duration.

           This bill  would permit utilities to deny a FiT contract if grid 
          interconnection is inadequate, the facility is not up to 
          required standards, or the additional load of the facility would 
          adversely impact utility operation and local distribution 
          restoration.  The utility would be required to assist any 
          contractor in avoiding contract denial by recommending specific 
          and reasonable actions or project design modifications that 
          would lead to approval of the contract.  The developer for any 
          contract denied by an IOU could appeal the denial to the CPUC 
          and, for a POU, the developer could appeal the denial to the 
          utility's governing board.  
           This bill  defines "most impacted and disadvantaged community" 
          (aka E.J. communities) as those census tracts in the top 20 
          percent of the results of a specified screening methodology 
          developed for the South Coast Air basin subject to modification 
          by the California Public Utilities Commission (CPUC), in 
          consultation with the California Air Resources Board (CARB).

                                      BACKGROUND
           
          What is a Feed-in-Tariff? - A FiT is a simple, comprehensible, 
          transparent contracting mechanism for small renewable generators 
          to sell power to a utility at predefined terms and conditions, 
          without contract negotiations. For the IOUs, the FiT operates as 
          a "must-take" contract in its portfolio. If the participant 
          generates the power, the IOU must take it and pay for it 
          according to the pre-defined terms of the FiT.

          Small renewable generator FiTs are available in the territories 
          of the three largest IOUs and provide a 10, 15, or 20-year 
          fixed-price, non-negotiable contract for systems sized up to 1.5 
          MW.  The CPUC has just concluded a rulemaking to implement the 
          terms of SB 32 (Negrete McLeod, 2009) and expand the IOU FiT to 
          3 MWs.  The total program allocation between the three IOUs is 
          approximately 500 MWs. ÝSee Re-MAT below.]











          Federal FiT Restriction - The Federal Power Act grants exclusive 
          jurisdiction to the FERC over wholesale electric sales and 
          pricing in interstate commerce, including sales made entirely 
          intrastate and sales delivered locally to a distribution system. 
           An exception allows the CPUC to set rates as long as the rates 
          are based on the avoided cost for a utility's wholesale 
          purchases from qualifying facilities which are generally small 
          renewable facilities of 80 MWs or less.  This statute therefore 
          limits the ability of the CPUC to set fixed prices in FiTs for 
          renewable energy.  If a fixed price is set, that price must be 
          based on the avoided costs in terms of costs that the electric 
          utility avoids by virtue of purchasing from the renewable 
          facility.  

          What costs is the electric utility is avoiding?  Under FERC's 
          regulations, a state may determine that capacity is being 
          avoided, and may rely on the cost of such avoided capacity to 
          determine the avoided cost rate. Further, in determining the 
          avoided cost rate, just as a state may take into account the 
          cost of the next marginal unit of generation, the state may also 
          take into account obligations imposed by the state that, for 
          example, utilities purchase energy from particular sources of 
          energy or for a long duration.  Therefore, the CPUC may take 
          into account actual procurement requirements, and resulting 
          costs, imposed on utilities in California.  

          The CPUC has litigated the issue of FiT pricing at the FERC and 
          based on that proceeding has determined that it can 
          differentiate renewable pricing based on the generation 
          characteristics of particular sources of energy (e.g. 
          based-load, peaking) but cannot, under federal law, establish 
          technology-specific pricing.  

          Competitive Procurement v. Fixed Price - Since the restructuring 
          of the electricity industry in California in the 1990s, the CPUC 
          has relied on a "competitive market first" approach for the 
          procurement of electricity.  The IOUs develop an annual 
          procurement plan which includes plans under which the IOUs 
          solicit bids for electricity deliveries.  The underlying premise 
          of wholesale competitive procurement is that ratepayers benefit 
          as a result of lower cost electricity deliveries.  Competitive 
          procurement also underlies the Renewable Portfolio Standard 
          (RPS) program which requires IOUs to establish a competitive 










          process to select renewable contracts based on least cost and 
          best fit.  Competitive markets are generally thought to benefit 
          ratepayers by using competitive pressures to lower total costs.

          In contrast, a textbook FiT uses administrative processes to set 
          a fixed price for the purchase of electricity by the IOU, the 
          price of which does not benefit from competition.  Although a 
          FiT may result in lower transaction costs to renewable 
          developers, it is not clear that it will result in the best 
          price for renewable electricity deliveries for ratepayers.  It 
          is difficult if not impossible to administratively set the right 
          price for a FiT.  If the FiT price is too high, the FiT results 
          in a gold rush for renewable developers at the expense of 
          ratepayers who will overpay; if the FiT price is too low the FiT 
          will not attract new investment.  What is the chance that a 
          regulatory agency can set just the right price which will 
          protect ratepayers and bring new projects online?

          Additionally, under a traditional FiT structure the utility 
          generally has no control over where power is built, whether it's 
          needed, or whether it is consistent with its renewable 
          procurement plan.  This is particularly critical for renewable 
          resources, some of which (e.g. solar and wind) do not provide 
          base load power but are intermittent and must be firmed and 
          shaped by the IOU or ISO.  

          Renewable Market Adjusting Tariff aka REMAT - The Legislature 
          has adopted a FiT to encourage electrical generation from small 
          distributed generation that qualifies as "eligible renewable 
          energy resources" under the RPS Program with an effective 
          capacity of three MW or less and, among other things, 
          strategically located on the distribution grid.  The program was 
          initially enacted in 2006 and applied only to public water and 
          wastewater customers on a first-come, first-served basis until 
          the electrical corporation met its proportionate share of a 250 
          MW statewide procurement limit.  Since 2007, the Legislature has 
          adopted several amendments to this program to cover a broad 
          range of issues, including increasing the maximum project size 
          to 3 MW from 1.5 MW and including some POUs in the FiT 















          mandate.<1>  The IOUs and POUs share a procurement goal of 750 
          MWs.

          In May the CPUC revised the FiT for IOUs and expanded the 
          program and developed a new pricing mechanism referred to as the 
          "Renewable Market Adjusting Tariff" or "Re-MAT" which includes 
          two principle components. First, a starting price based on the 
          weighted average contract price of the three largest electric 
          utility's highest priced executed contract resulting from the 
          commission's Renewable Auction Mechanism auction held in 
          November 2011. This starting price will apply to three FiT 
          product types: baseload, peaking as-available, and non-peaking 
          as-available.  The price can be adjusted every two-months and 
          increase or decrease for each product type based on the market 
          response.  Each accepted project will be paid a time-of-delivery 
          adjustment based on the generator's actual energy delivery 
          profile and the individual utility's time-of-delivery factors.

          In the two-plus years since the FiT was mandated for the nine 
          POUs, only four have attempted to comply with the program 
          requirement.  There is no penalty under current law if the POU 
          fails to adopt the program.  With the exception of the RPS 
          statutes, POUs have not been subject to penalties for failure to 
          comply with energy mandates including energy efficiency and the 
          California Solar Initiative.  As a consequence, many utilities 
          have ignored the mandates or interpreted them in ways unintended 
          by the Legislature.

                                       COMMENTS
           
              1.   Author's Purpose  .  According to the author, California's 
               most vulnerable communities - those that have suffered 
               first and worst from pollution - have not benefited much 
               from renewable energy policy.  SB 32 (Negrete McLeod, 2009) 
               established a FiT to spur the development of distributed 
               renewable electric generation in California. SB 32 amended 
               a prior feed-in tariff established by AB 1969 (Yee, 2006), 
             --------------------------
          <1> Current law requires that only the largest POUs adopt a FiT 
          and specifies that those serving a population of 75,000 
          customers or more make a FiT available to renewable developers 
          in those territories. The affected POUs are: Anaheim, Glendale, 
          Imperial, Los Angeles, Modesto, Riverside, Turlock, and 
          Sacramento.  The total program allocation between the nine POUs 
          is approximately 250 MWs.










               and raised the project size cap from 1.5 megawatts to 3 
               megawatts.  These project sizes are too large to be 
               installed in the urban core and poor rural communities, and 
               SB 32 has no requirements to address the specific needs of 
               these communities.

               The California Solar Initiative (CSI) is a program 
               authorized by SB 1 (Murray, 2006) and the CPUC with a goal 
               to install 1940 megawatts of new solar capacity in the 
               service territories of California's IOUs.  Two low income 
               rebate programs for small-scale solar electric power 
               generation exist within CSI: 1) the Single-family 
               Affordable Homes (SASH) program for low-income residents 
               that own their own single-family home and 2) the 
               Multi-family Affordable Solar Housing (MASH) program for 
               multi-family affordable housing.  MASH and SASH are very 
               small programs-with a combined total of about 45 megawatts- 
               that by law will be expiring at the end of 2016.  The high 
               volume of applications for the MASH program has led to the 
               establishment of wait lists; and the programs are so full 
               that the wait lists are being closed to new applicants.  
               While there is still about 7 megawatts left in the SASH 
               program, participants usually need to have a minimum 
               utility bill of $150, a threshold that is often not met by 
               most low-income community members, who try to limit their 
               energy use.  SASH is dependent on a volunteer-run solar 
               installation program, and while it provides training 
               opportunities, it does not create paid jobs in low-income 
               communities.

              2.   FERC Restrictions  .  The procurement mandates of this 
               bill seek to further an important policy goal for E.J. 
               communities, but it is very likely that they are prohibited 
               under federal law.  The bill references FERC decisions 
               affirming that "where a state requires a utility to procure 
               energy from generators with certain characteristics, 
               generators with those characteristics appropriately 
               constitute the sources that are relevant to the 
               determination of the utility's avoided cost for that 
               procurement requirement."  However those characteristics 
               are not characteristics based on social policy proposed by 
               this bill.  The permissible characteristics are the 
               generation characteristics which affect the value of the 
               power to the grid such as baseload vs. intermittent 










               resources or geographical proximity to transmission.

               FERC regulations specifically state that the utility can 
               "differentiate among qualifying facilities using various 
               technologies on the basis of the supply characteristics of 
               the different technologies."  There is no indication that 
               societal characteristics are included.  As an example of 
               the application of this regulation, FERC specifically found 
               that a tariff price could be increased "to reflect the 
               avoided costs of the construction of distribution and 
               transmission upgrades that would otherwise be needed" 
               compared to other generation.
              3.   Costs of Small Scale Renewables  .  The bill does require 
               that ratepayers be held indifferent to the costs of the FiT 
               mandated by this bill but its provisions are internally 
               inconsistent.  Although the bill defines ratepayer 
               indifference as meaning that ratepayers should not be 
               subject to increased rates or reduced service as a result 
               of the bill and the tariff complies with the avoided-cost 
               requirement of FERC, other provisions contradict this 
               standard.  

               First, the program would require the tariff payment be 
               "sufficient to stimulate the market demand?to achieve the 
               targets" of the program which are to locate the facilities 
               in EJ communities and hire employees from those 
               communities.  These conditions have nothing to do with the 
               price of electricity and are difficult to quantify and 
               implement.  The author does provide a cost-cap for the 
               program but that too is not consistent with the ratepayer 
               indifference standard referenced.  

               As an example, applying the cost cap in this bill to PG&E, 
               the FiT cost would be capped at a minimum of $0.34 kWh.<2>  
               The CPUC reports that this number is far higher than other 
               renewable generation available on the market:

          ---------------------------
          <2> This number was derived by applying the formula in this bill 
          to PG&E's 2013 forecast revenues of $4.4 billion, PG&E's 
          estimated 44.6% of MWs under the program which would require the 
          purchase of 167 MW of generation over six years at 27.9 MW per 
          year, and a capacity factor of 20%.  Note that the bill sets the 
          cap based on 2020 retail sales so that the actual cost cap would 
          be higher than $0.34 kWh.










                    Under the CPUC's Large-Scale RPS Solicitation, the 
                    primary program to procure renewable generation to 
                    meet Renewables Portfolio Standard mandates, contracts 
                    average less than $0.10/kWh; under the CPUC's 
                    Renewable Auction Mechanism, the bi-annual auction for 
                    distributed renewable generation, contracts average 
                    less than $0.08/kWh.  By contrast, under AB 1990, 
                    contracts would begin at approximately $0.26/kWh and 
                    rise from there.

               The author responds that "because of the interaction with 
               other programs, customers will see a de minimis impact on 
               their utility bill from AB 1990.  The AB 1990 program is 
               contained in the RPS program, which is constrained by an 
               overall cost cap, thus procurement through AB 1990 could be 
               partially or fully offset by lower cost procurement from 
               other renewable energy projects."

              4.   E.J. Metrics  . Developing a metric to identify what are 
               commonly referred to as environmental justice communities 
               has been challenging and controversial.  This bill requires 
               the use of one specific model developed for the South Coast 
               Air Quality District.  The identified screening methodology 
               is to be used in determining the most impacted and 
               disadvantaged communities appears to be just the first step 
               in identifying a community and may not be determinative.  
               In fact the authors of this model state "this is screening 
               not assessment, so neighborhood monitoring and ground truth 
               verification is needed."  

               Some opine that this model is too narrow and is too 
               "air-centric" focusing on communities with air and economic 
               impacts but does not screen for other environmental 
               concerns and a more comprehensive tool should be used that 
               incorporates all impacts of pollution.  Nowhere else in 
               statute is one model singled out and some are concerned 
               about the precedent of memorializing this particular model. 
                Two other models are in development by the CARB and the 
               Environmental Protection Agency (EPA).  

               Although this bill does permit the CPUC to consult with the 
               CARB and to modify the screening metrics used in 
               determining the most impacted and disadvantaged 
               communities, the necessity of mandating one metric is not 










               clear and may in the long-run limit the commission in its 
               ability to choose a screening tool that is the most current 
               and reliable.  To ensure that the commission has the 
               latitude needed to utilize the best screening tools 
               available, the committee may want to consider striking the 
               screening tool mandated in this bill and instead have the 
               CPUC consult with the EPA and CARB in identifying the 
               communities eligible for this tariff.

              5.   Fundamental Issue & Alternative  .  At the heart of the 
               debate over this bill is whether the commission should 
               establish administratively-determined prices for contracts 
               for specific renewable electric generation resources 
               located in the state's most impacted and disadvantaged 
               communities and also pay a premium for the electricity to 
               not only ensure the siting of plants in those areas but to 
               require the hiring of employees from those communities.

               Current FiT statutes and policies of the CPUC very clearly 
               require the commission to use a competitive, market-based 
               approach but the sponsors of this bill argue that this 
               mechanism does not account for the societal benefits to 
               ratepayers and the environment from encouraging the 
               development of generation in these communities.  

               There is no opposition to placing renewables in these 
               communities nor is there any question of the challenges 
               that they face with regard to unemployment and poverty.  
               However, the costs associated with this program and the 
               administrative challenges of actually overlaying the 
               geographic and employment mandates on the renewable 
               procurement process would be administratively complex. The 
               result of the tariff under this program would be 
               renewable's costs several times more than what can be 
               obtained using the competitive pricing models in place 
               through the Re-Mat and other programs.  Consequently, to 
               ensure that there are opportunities for EJ communities to 
               participate in the market and not get crowded out by other 
               more sophisticated developers, but still try to secure the 
               best price for those renewables for ratepayers, the 
               committee may wish to consider amendments that would 
               require the IOUs to set-aside capacity for those 
               communities, in essence, a separate bucket.  











               Additionally the total Re-mat is only 500 MWs yet this bill 
               calls for a 375 MW set-aside.  The committee may wish to 
               consider amendments to set-aside an additional 25% in 
               capacity for this program brining the Re-MAT total to 625 
               MWs.  

               It is not clear whether this approach would pass muster 
               under federal law either since the set-aside would be based 
               on societal characteristics, not generation 
               characteristics, but the program would still have a 
               competitive pricing mechanism which could help.

              6.   POUs  .  Although it appears that the author may intend 
               that the POUs also direct their tariff to E.J. communities, 
               the bill could be interpreted as only requiring the POUs to 
               launch a FiT directed at small scale renewable facilities 
               sized less than 500 kW.  

               If intended for the E.J. communities, the foregoing 
               alternative of the Re-Mat would only be available for IOUs. 
                The POUs are also required to implement the terms of this 
               measure but the POUs are not subject to the same federal 
               pricing restrictions as the IOUs.  Nevertheless, the model 
               mandated by this bill would be a cost-burden to POU 
               ratepayers and, for many POUs, especially those of small 
               size and be very difficult to implement since the smaller 
                                                   POUs may not even have E.J. communities that fall under the 
               defined metric in their jurisdictions.  The author did try 
               to accommodate this factor with an adjustment formula but 
               the math is confusing and the mandate still costly.

               To address these concerns, at a minimum, the committee may 
               wish to consider amendments which would exclude POUs of 
               less than 75,000 customer connections from the mandate 
               which is consistent with the FiT program under SB 32 and 
               lower the 375 MW target to a 25% increase as suggested for 
               the IOUs in the preceding comment.  Additionally, the 
               committee may wish to consider striking the mandates of 
               this bill and simply direct that the POUs modify and expand 
               their SB 32 FiTs to ensure a set-aside for bids from E.J. 
               communities.  In the alternative, the bill should be 
               amended to clarify that the POUs are to use the same E.J. 
               metrics and program goals as the IOU program if that is the 
               author's intent.











                                    ASSEMBLY VOTES
           
          Assembly Floor                     (49-27)
          Assembly Appropriations Committee  (12-5)
          Assembly Utilities and Commerce Committee                      
          (9-4)

                                       POSITIONS
           
           Sponsor:
           
          California Environmental Justice Alliance

           Support:
           
          Asian & Pacific Islander Obesity Prevention Alliance
          Asian Pacific Policy & Planning Council
          Asian Neighborhood Design
          California Healthy Nail Salon Collaborative
          California for Clean Energy and Jobs
          California Interfaith Power & Light
          Capretz & Associates
          Center on Policy Initiatives
          Climate Protection Campaign
          Communities for Clean Ports
          Ella Baker Center's Green collar Jobs Campaign
          EndOil
          Environment California
          Environmental Justice Committee of the Asian Pacific Policy & 
          Planning Council
          Fresno Center for New Americans
           Support (continued):
           
          Khmer Girls in Action
          Korean Resource Center
          Koreatown Immigrant Workers Alliance
          Kyocera Solar, Inc.
          Los Angeles Business Council
          Little Tokyo Service Center Community Development Corporation
          Local Clean Energy Alliance
          Pacific Environment
          P" (a Pacific Island sorority)
          Peoples CORE










          Search to Involve Pilipino Americans
          Sierra Club California
          Solar Energy Industries Association
          Solaria
          South Coast Air Quality Management District
          Southeast Asian Assistance Center
          Students for Economic and Environmental Justice at Berkeley Law
          The Filipino American Coalition
          The Vote Solar Initiative
          To'utupu'o e 'Out Felenite Association
          USGBC California
          Several individuals

           Oppose:
           
          California Chamber of Commerce
          California Council for Environmental and Economic Balance
          California Farm Bureau Federation
          California Independent Oil Marketers Association
          California League of Food Processors
          California Manufacturers & Technology Association
          California Municipal Utilities Association
          California Public Utilities Commission
          Chemical Industry Council of California
          Consumer Specialty Products Association
          Division of Ratepayer Advocates
          Pacific Gas and Electric Company
          Sacramento Municipal Utility District
          San Diego Gas and Electric
          Southern California Edison
          Western Growers Association
          Western Plant Health Association
          Western State Petroleum Association

          Kellie Smith 
          AB 1990 Analysis
          Hearing Date:  July 3, 2012