BILL ANALYSIS Ó ------------------------------------------------------------ |SENATE RULES COMMITTEE | AB 2498| |Office of Senate Floor Analyses | | |1020 N Street, Suite 524 | | |(916) 651-1520 Fax: (916) | | |327-4478 | | ------------------------------------------------------------ THIRD READING Bill No: AB 2498 Author: Gordon (D) Amended: 8/14/12 in Senate Vote: 21 SENATE TRANSPORTATION & HOUSING COMMITTEE : 9-0, 6/26/12 AYES: DeSaulnier, Gaines, Harman, Kehoe, Lowenthal, Pavley, Rubio, Simitian, Wyland SENATE APPROPRIATIONS COMMITTEE : 7-0, 8/6/12 AYES: Kehoe, Walters, Alquist, Dutton, Lieu, Price, Steinberg ASSEMBLY FLOOR : 71-0, 5/25/12 - See last page for vote SUBJECT : Construction Manager/General Contractor procurement SOURCE : Department of Transportation DIGEST : This bill authorizes the Department of Transportation (Caltrans) to use an alternative procurement method referred to as Construction Manager/General Contractor (CM/GC) for up to four projects. ANALYSIS : Under the State Contract Act, public entities must fully complete the design of a project prior to awarding a construction contract and must award that contract to the "lowest responsible bidder." This process, commonly known as design-bid-build, is intended to ensure CONTINUED AB 2498 Page 2 that the project is built for the lowest possible cost. Although this is by far the most common method of public contracting, for certain projects it may not result in the lowest cost, nor be the most efficient method of delivery. Under design-bid-build, the project designer (whether consultants or employees of a public entity) has sole ownership of the project design and does not have the benefit of consultation with the contractor that will ultimately be responsible for construction of the project. Thus, there may be significant construction issues that the designer does not anticipate which can result in change orders later in the process. This can drive up the project cost and shift all the risk to the agency commissioning the project. Moreover, because under design-bid-build, all design, permits, right-of-way acquisition, etc., must occur prior to contract award, the opportunity to save time by fast-tracking certain elements of a project while work continues on other elements is lost. Existing law establishes the Design-Build Demonstration Program, which authorizes Caltrans to use the design-build method of procurement for up to ten projects, subject to the California Transportation Commission (CTC) approval. The design-build entity is made up of a design firm and a construction firm. This ensures collaboration between the designer and the contractor. It also allows the design-build firm to fast track aspects of a project as issues around other elements are resolved. However, the potential weakness of this method is that the owner of the project relinquishes substantial control over the design. Collaboration occurs between the design and construction members of the design-build team, but design-build limits the role of the project owner. This bill: 1. Defines a CM/GC method of procurement as one in which Caltrans selects the construction manager to provide preconstruction services during the design phase of a project, plus actual construction services when the project is being built. 2. Authorizes Caltrans to use CM/GC procurement method for CONTINUED AB 2498 Page 3 four projects, with at least three of the projects having a construction value greater than $10 million each. 3. Selection of the CM/GC team is a competitive procurement process where Caltrans evaluates bids on the basis of qualifications of the firm, proposed approach to design, experience, and other factors. 4. Requires Caltrans to prepare and submit a status report to the Legislature no later than July 1 of each year during which a CM/GC project is underway or completed, as specified. Comments Purpose of the bill . According to Caltrans, the bill's sponsor, the purpose of the bill is to use CM/GC to expedite project delivery. Caltrans states that it intends to use CM/GC "where unusual constructability issues are likely to emerge. In such cases, having the insight and cooperation of the construction contractor early in the process can yield innovative solutions that save significant time and cost." Alternative project delivery methods . In the last several years, public agencies have been adopting alternative project delivery methods. The principal reason for this is the desire to shift construction risk from the agency/owner to the project contractor. The most widely used alternative project delivery technique is design-build. The CM/GC. The CM/GC project delivery method allows an agency to engage a construction manager during the design process to provide assistance to the design team, including advice regarding scheduling, pricing, phasing, and other matters that helps the owner design a more constructible project. According to the Federal Highway Administration (FHWA), when design reaches approximately 60-90% completion, the agency and the construction manager negotiate a guaranteed maximum price for the construction of the project based on the defined scope and schedule. If this price is acceptable to both parties, a contract is executed for construction services, and the construction CONTINUED AB 2498 Page 4 manager becomes the general contractor. The FHWA has found that the benefits of this procurement method include that the public agency does not sacrifice control over the design of the project and during the construction phase, the contractor is very familiar with the project design resulting in less disputes over design issues. FISCAL EFFECT : Appropriation: No Fiscal Com.: Yes Local: Yes According to the Senate Appropriations Committee, unknown project costs or savings to Caltrans (State Highway Account and federal funds) by providing authority to use a new project delivery method. Caltrans costs to administer and report on the new contracting method would be minor. Caltrans anticipates significant long term savings, based on other states' experience. However, that early experience with any new project delivery method usually proves to be more costly than traditional design-bid-build in the initial implementation period. In addition, since a contract for preconstruction and construction services for CM/GC is a negotiated process with the most qualified construction manager, rather than a traditional "lowest responsible bidder" process, it is difficult to determine whether the negotiated price would be lower or higher than project delivery costs through a traditional design-bid-build process. It is expected that use of the CM/GC method would minimize change orders, which is currently a significant factor in unexpected cost escalation on Caltrans projects. SUPPORT : (Verified 8/13/12) Department of Transportation (source) Associated General Contractors Automobile Club of Southern California ASSEMBLY FLOOR : 71-0, 5/25/12 AYES: Achadjian, Alejo, Allen, Ammiano, Beall, Block, Blumenfield, Bonilla, Bradford, Brownley, Buchanan, Butler, Charles Calderon, Campos, Carter, Cedillo, CONTINUED AB 2498 Page 5 Chesbro, Conway, Cook, Davis, Dickinson, Donnelly, Eng, Feuer, Fong, Fuentes, Furutani, Beth Gaines, Galgiani, Garrick, Gatto, Gordon, Gorell, Hagman, Halderman, Harkey, Hayashi, Roger Hernández, Hill, Huber, Hueso, Huffman, Jeffries, Jones, Lara, Logue, Bonnie Lowenthal, Mansoor, Mendoza, Miller, Mitchell, Monning, Morrell, Nestande, Nielsen, Norby, Olsen, Pan, V. Manuel Pérez, Portantino, Skinner, Smyth, Solorio, Swanson, Torres, Valadao, Wagner, Wieckowski, Williams, Yamada, John A. Pérez NO VOTE RECORDED: Atkins, Bill Berryhill, Fletcher, Grove, Hall, Knight, Ma, Perea, Silva JJA:m 8/13/12 Senate Floor Analyses SUPPORT/OPPOSITION: SEE ABOVE **** END **** CONTINUED