BILL ANALYSIS                                                                                                                                                                                                    Ó



                                                                  AB 2498
                                                                  Page  1

          (  Without Reference to File  )

          CONCURRENCE IN SENATE AMENDMENTS
          AB 2498 (Gordon)
          As Amended  August 31, 2012
          Majority vote
           
           ----------------------------------------------------------------- 
          |ASSEMBLY:  |71-0 |(May 25, 2012)  |SENATE: |21-13|(August 31,    |
          |           |     |                |        |     |2012)          |
           ----------------------------------------------------------------- 
            
           Original Committee Reference:   TRANS  .  

           SUMMARY  :  Authorizes the California Department of Transportation 
          (Caltrans) to use an alternative procurement method referred to 
          as Construction Manager/General Contractor (CM/GC) for up to 
          four projects.  

           The Senate amendments:

           1)Add legislative findings and declarations citing the benefits 
            of Caltrans' use of CM/GC.   

           2)Require Caltrans to advertise, award, and administer CM/GC 
            contracts and prohibits Caltrans from delegating the CM/GC 
            contracting authority.   

           3)Increase from four to six the number of projects for which 
            Caltrans can use the CM/GC method.  
             
          4)Require that, of the six projects for which Caltrans may use 
            CM/GC, at least five of the projects have to have construction 
            costs greater than $10 million.   

           5)Require that, on at least four of the six projects, all of the 
            design and engineering services have to be performed by 
            Caltrans employees or Caltrans consultants.  Similarly, on all 
            six contracts, all construction inspection services have to be 
            performed by Caltrans employees or Caltrans consultants.  
            Require Caltrans' capital outlay support program budget to 
            reflect the needed resources for these contracts.   

           6)Prescribe elements of the report required to be submitted by 
            Caltrans at the completion of the CM/GC contracts.   








                                                                 AB 2498
                                                                  Page  2

           
           FISCAL EFFECT  :  According to the Senate Appropriations 
          Committee, pursuant to Senate Rule 28.8, negligible state costs. 
           

           AS PASSED BY THE ASSEMBLY  , this bill was substantially similar 
          to the version passed by the Senate.  

           COMMENTS  :  For decades, the traditional process for procuring 
          public works projects has been the design-bid-build process.  
          This process relies on:  1) a design entity preparing complete 
          project design specifications and estimates; 2) the project 
          owner putting the complete package out to bid for construction; 
          and, 3) awarding the construction contract to the lowest 
          responsible bidder.  The design-bid-build process was developed 
          to protect taxpayers from extravagance, corruption, and other 
          improper practices by public officials as well as to secure a 
          fair and reasonable price for public works construction by 
          injecting competition amongst bidders into the process.  

          Although design-bid-build generally results in the lowest cost 
          construction contract, it is not without its drawbacks, 
          including:  

          1)Projects generally take longer to complete because designs 
            must be entirely completed, permits obtained, and right-of-way 
            acquired before the construction contract can be bid and 
            awarded.  

          2)Designs prepared for a competitive low-bid procurement are 
            developed to allow for a broad range of construction 
            approaches.  As a result, low-bid designs do not always equate 
            to the most efficient design possible, depending on a 
            particular contractor's particular strengths or capabilities.  


          3)Because the project designer does not have the benefit of 
            consulting with the entity that will ultimately be responsible 
            for construction of the project, there may be significant 
            issues that the designer does not anticipate, particularly 
            constructability issues.  This can result in change orders 
            that ultimately drive up the price of the contract.  

          4)Low-bid is not always the least expensive option, once change 
            orders and contractor claims are factored into the overall 








                                                                  AB 2498
                                                                  Page  3

            project costs.  

          In the early 1990s, public works agencies grew frustrated with 
          design-bid-build and began experimenting with more innovative 
          project delivery methods, namely design-build.  Design-build is 
          an alternate method for procuring design and construction 
          services that provides for the delivery of public works projects 
          from a single entity.  Design-build combines project design, 
          permit, and construction schedules in order to streamline the 
          traditional design-bid-build environment.  

          Design-build differs from design-bid-build in some key areas, 
          including:

          1)Shorter overall elapsed project delivery time because 
            construction can begin before final design is complete.  

          2)Project costs and schedule risks are more heavily borne by the 
            design-build contractor.  

          3)Construction claims and change orders are minimized.  

          4)Designs can be developed to take advantage of particular 
            contractor's strengths and abilities, thereby reducing the 
            need to "over-design" for generic use as in design-bid-build.  


          5)Project specifications are typically based on definitive 
            performance criteria (which may or may not be well established 
            by the project owner) rather than established specifications.  


          6)Contracts are awarded based on best-value analyses rather than 
            low-bid.  

          Design-build contracts are not without their drawbacks as well.  
          For example, with a design-build project, the project owner must 
          give up a good deal of control over the details of the project 
          design.  Additionally, design-build contractors are typically 
          selected using qualifications-based selection criteria or best 
          value analysis.  These approaches are more subjective than a 
          low-bid approach, potentially subjecting the public works owner 
          to greater contract challenges and higher costs.  

          This bill authorizes Caltrans to use CM/GC, an emerging project 








                                                                  AB 2498
                                                                  Page  4

          delivery method that potentially combines the best of both 
          design-bid-build and design-build, for up to four projects.  
          Using CM/GC, Caltrans will be able to engage a design and 
          construction management consultant (construction manager) to act 
          as the department's consultant during the pre-construction phase 
          and as the general contractor during construction.  During the 
          design phase, the construction manager acts in an advisory role, 
          providing constructability reviews, value engineering 
          suggestions, construction estimates, and other 
          construction-related recommendations.  Later, Caltrans and the 
          construction manager can agree that the project design has 
          progressed to a sufficient enough point that construction may 
          begin.  The two parties then work out mutually agreeable terms 
          and conditions for the construction contract, and, if all goes 
          well, the construction manager becomes the general contractor 
          and construction on the project commences, well before design is 
          entirely complete.  

          The CM/CG process is meant to provide continuity and 
          collaboration between the design and construction phases of the 
          project.  Construction managers have an incentive to provide 
          input during the design phase that will enhance constructability 
          of the project later because they know that they will have the 
          opportunity to become the general contractor for the project.  
          Furthermore, CM/CG promises to save project delivery time, 
          provide earlier cost certainty, transfer risks from Caltrans to 
          the contractor, and ensure project constructability.  
          Additionally, CM/CG allows Caltrans to have greater control of 
          design decisions.  It also allows Caltrans to design the project 
          to compliment the CM/CG's strengths and capabilities, thereby 
          avoiding the need to over-design the project to provide maximum 
          competitiveness in a low-bid procurement.  

          The American Council of Engineering Companies (ACEC) is 
          concerned about amendments to the bill that would require 
          construction inspection services to be performed by Caltrans 
          employees or Caltrans consultants.  ACEC argues that this 
          requirement violates provisions of Proposition 35 (Article XXII 
          of the State Constitution) that requires that state and local 
          agencies must be allowed to contract with qualified private 
          entities for architectural and engineering services for all 
          public works of improvement.  ACEC argues that this bill 
          essentially removes a local agency's ability to procure 
          construction inspection services by requiring, instead, that 
          these services be performed by Caltrans.   








                                                                  AB 2498
                                                                  Page  5

           

          Analysis Prepared by  :  Janet Dawson / TRANS. / (916) 319-2093 


                                                               FN: 0005904