BILL ANALYSIS Ó AB 2498 Page 1 ( Without Reference to File ) CONCURRENCE IN SENATE AMENDMENTS AB 2498 (Gordon) As Amended August 31, 2012 Majority vote ----------------------------------------------------------------- |ASSEMBLY: |71-0 |(May 25, 2012) |SENATE: |21-13|(August 31, | | | | | | |2012) | ----------------------------------------------------------------- Original Committee Reference: TRANS . SUMMARY : Authorizes the California Department of Transportation (Caltrans) to use an alternative procurement method referred to as Construction Manager/General Contractor (CM/GC) for up to four projects. The Senate amendments: 1)Add legislative findings and declarations citing the benefits of Caltrans' use of CM/GC. 2)Require Caltrans to advertise, award, and administer CM/GC contracts and prohibits Caltrans from delegating the CM/GC contracting authority. 3)Increase from four to six the number of projects for which Caltrans can use the CM/GC method. 4)Require that, of the six projects for which Caltrans may use CM/GC, at least five of the projects have to have construction costs greater than $10 million. 5)Require that, on at least four of the six projects, all of the design and engineering services have to be performed by Caltrans employees or Caltrans consultants. Similarly, on all six contracts, all construction inspection services have to be performed by Caltrans employees or Caltrans consultants. Require Caltrans' capital outlay support program budget to reflect the needed resources for these contracts. 6)Prescribe elements of the report required to be submitted by Caltrans at the completion of the CM/GC contracts. AB 2498 Page 2 FISCAL EFFECT : According to the Senate Appropriations Committee, pursuant to Senate Rule 28.8, negligible state costs. AS PASSED BY THE ASSEMBLY , this bill was substantially similar to the version passed by the Senate. COMMENTS : For decades, the traditional process for procuring public works projects has been the design-bid-build process. This process relies on: 1) a design entity preparing complete project design specifications and estimates; 2) the project owner putting the complete package out to bid for construction; and, 3) awarding the construction contract to the lowest responsible bidder. The design-bid-build process was developed to protect taxpayers from extravagance, corruption, and other improper practices by public officials as well as to secure a fair and reasonable price for public works construction by injecting competition amongst bidders into the process. Although design-bid-build generally results in the lowest cost construction contract, it is not without its drawbacks, including: 1)Projects generally take longer to complete because designs must be entirely completed, permits obtained, and right-of-way acquired before the construction contract can be bid and awarded. 2)Designs prepared for a competitive low-bid procurement are developed to allow for a broad range of construction approaches. As a result, low-bid designs do not always equate to the most efficient design possible, depending on a particular contractor's particular strengths or capabilities. 3)Because the project designer does not have the benefit of consulting with the entity that will ultimately be responsible for construction of the project, there may be significant issues that the designer does not anticipate, particularly constructability issues. This can result in change orders that ultimately drive up the price of the contract. 4)Low-bid is not always the least expensive option, once change orders and contractor claims are factored into the overall AB 2498 Page 3 project costs. In the early 1990s, public works agencies grew frustrated with design-bid-build and began experimenting with more innovative project delivery methods, namely design-build. Design-build is an alternate method for procuring design and construction services that provides for the delivery of public works projects from a single entity. Design-build combines project design, permit, and construction schedules in order to streamline the traditional design-bid-build environment. Design-build differs from design-bid-build in some key areas, including: 1)Shorter overall elapsed project delivery time because construction can begin before final design is complete. 2)Project costs and schedule risks are more heavily borne by the design-build contractor. 3)Construction claims and change orders are minimized. 4)Designs can be developed to take advantage of particular contractor's strengths and abilities, thereby reducing the need to "over-design" for generic use as in design-bid-build. 5)Project specifications are typically based on definitive performance criteria (which may or may not be well established by the project owner) rather than established specifications. 6)Contracts are awarded based on best-value analyses rather than low-bid. Design-build contracts are not without their drawbacks as well. For example, with a design-build project, the project owner must give up a good deal of control over the details of the project design. Additionally, design-build contractors are typically selected using qualifications-based selection criteria or best value analysis. These approaches are more subjective than a low-bid approach, potentially subjecting the public works owner to greater contract challenges and higher costs. This bill authorizes Caltrans to use CM/GC, an emerging project AB 2498 Page 4 delivery method that potentially combines the best of both design-bid-build and design-build, for up to four projects. Using CM/GC, Caltrans will be able to engage a design and construction management consultant (construction manager) to act as the department's consultant during the pre-construction phase and as the general contractor during construction. During the design phase, the construction manager acts in an advisory role, providing constructability reviews, value engineering suggestions, construction estimates, and other construction-related recommendations. Later, Caltrans and the construction manager can agree that the project design has progressed to a sufficient enough point that construction may begin. The two parties then work out mutually agreeable terms and conditions for the construction contract, and, if all goes well, the construction manager becomes the general contractor and construction on the project commences, well before design is entirely complete. The CM/CG process is meant to provide continuity and collaboration between the design and construction phases of the project. Construction managers have an incentive to provide input during the design phase that will enhance constructability of the project later because they know that they will have the opportunity to become the general contractor for the project. Furthermore, CM/CG promises to save project delivery time, provide earlier cost certainty, transfer risks from Caltrans to the contractor, and ensure project constructability. Additionally, CM/CG allows Caltrans to have greater control of design decisions. It also allows Caltrans to design the project to compliment the CM/CG's strengths and capabilities, thereby avoiding the need to over-design the project to provide maximum competitiveness in a low-bid procurement. The American Council of Engineering Companies (ACEC) is concerned about amendments to the bill that would require construction inspection services to be performed by Caltrans employees or Caltrans consultants. ACEC argues that this requirement violates provisions of Proposition 35 (Article XXII of the State Constitution) that requires that state and local agencies must be allowed to contract with qualified private entities for architectural and engineering services for all public works of improvement. ACEC argues that this bill essentially removes a local agency's ability to procure construction inspection services by requiring, instead, that these services be performed by Caltrans. AB 2498 Page 5 Analysis Prepared by : Janet Dawson / TRANS. / (916) 319-2093 FN: 0005904