BILL ANALYSIS                                                                                                                                                                                                    Ó



                                                                  SB 293
                                                                  Page  1

          Date of Hearing:   August 17, 2011

                        ASSEMBLY COMMITTEE ON APPROPRIATIONS
                                Felipe Fuentes, Chair

                   SB 293 (Padilla) - As Amended:  August 15, 2011 

          Policy Committee:                              Business and 
          Professions  Vote:                            8-0
                        Judiciary                             9-0

          Urgency:     No                   State Mandated Local Program: 
          No     Reimbursable:               

           SUMMARY  

          This bill establishes a four-year limit on retention in public 
          works projects, with specified exceptions, and modifies 
          provisions regarding payments to subcontractors and provisions 
          regarding subcontractor claims for nonpayment. Specifically, 
          this bill:

          1)Limits retention-the amount withheld from public works 
            contract progress payments by any state or local public entity 
            to a contractor, by the contractor to a subcontractor, or by a 
            subcontractor to a subordinate subcontractor-to no more than 
            five percent of the payment for all contracts entered into 
            after January 1, 2012.

          2)Stipulates that the above does not apply if a subcontractor, 
            following written notice by contractor, is unable or refuses 
            to furnish a payment or performance bond.

          3)Authorizes retention exceeding five percent, between awarding 
            entities, contractors, and subcontractors, under the following 
            circumstances:

             a)   The director of a state department awarding the contract 
               makes a finding prior to the bid that the project is 
               substantially complex and therefore requires a higher 
               retention, and this finding and the actual retention is 
               included in the bid documents, which shall also be the 
               maximum retention on payments to subcontractors.

             b)   The governing body of a local government entity awarding 








                                                                  SB 293
                                                                  Page  2

               the contract adopts the same procedures as in (a).

          4)Sunsets the above retention provisions on January 1, 2016.

          5)Reduces, from 10 to seven, the number of days after receiving 
            a progress payment that a contractor or subcontractor must pay 
            a subcontractor, unless otherwise agreed to in writing.

          6)Establishes that a subordinate contractor, who has not 
            provided a contractor with a 20-day preliminary bond notice, 
            may not enforce a claim against the contractor-by giving 
            written notice to the surety and bond principal within 15 days 
            of the notice of completion, or if no notice of completion has 
            been recorded, within 75 days after completion of the work-if 
            all payments, except those disputed in good faith, have been 
            made by the contractor to the subcontractor with whom the 
            subordinate subcontractor has a contractual relationship.

          7)Clarifies the 20-day preliminary bond notice requirement does 
            not apply to laborers.

           FISCAL EFFECT  

          In general, reducing the amount of retention that can be 
          withheld would to some extent increase the likelihood that a 
          contractor or subcontractor would fail to fully perform their 
          work, and thus could lead to higher costs to the contracting 
          entity related to the administrative burden, project delays, and 
          potential litigation associated with finding alternative means 
          to complete the work.

          1)In most cases, the fiscal impact to the  state  would likely be 
            minor. According to the Department of General Services, the 
            use of a retention amount exceeding 5% is an exception on 
            state projects, and is used generally only on smaller 
            projects. 

          2)The University of California has a 5% retention practice. 
            Caltrans contracts funded at least in part with federal monies 
            (85% of all Caltrans capital outlay) have no retention 
            provisions, as required by federal law.

          3)The exception at the state level is the California State 
            University (CSU), which is opposed to this bill and argues 
            that limiting retention will remove a tool available to 








                                                                  SB 293
                                                                  Page  3

            protect against contractor non-performance. CSU cites the 
            example of an $18 million project that, based on the current 
            schedule is projected to finish two years behind schedule. 
            Were this bill in effect, about $900,000 in retention would be 
            withheld, but the university would be entitled to almost $2 
            million in liquidated damages for late completion. This would 
            leave CSU $1.1 million short, which might have to be recovered 
            from the contractor through legal means, thus entailing even 
            more costs. CSU argues that in these situations, it is 
            preferable to ratchet up the retention level above 5% rather 
            than attempt to seek reimbursement on the back end of a 
            project.

          4)The fiscal impact on  local governments  could be more 
            significant as they are generally more likely to use a 
            retention amount exceeding 5%, and thus would be restricted by 
            this bill. Any additional costs associated with this 
            limitation would not be reimbursable, however. In addition, 
            unlike previous legislation proposed to limit retention, this 
            bill allows local governments, as well as state agencies, to 
            establish higher retention on projects they deem to be 
            complex.



           COMMENTS  

          1)Purpose  . According to the author, "With California's economy 
            and cash flow continuing to tighten, it is important for 
            contractors to keep close controls on payments, moneys owed, 
            as well as potential disputes. The construction industry has 
            come together to resolve payment related issues that 
            predominately occur in the public works context. The solution 
            presented is a multi-prong approach that will reduce retention 
            on public works payments to no more than 5%, unless a surety 
            bond is requested and the subcontractor is unable to provide a 
            bond?In addition, the prompt payment statutes for public and 
            private works are often difficult to find for the small and 
            emerging contractor, so in an attempt to ease clarity in the 
            code it has been drafted to consolidate the statutes on prompt 
            payment.

            "Lastly, in private works, any person who provides 
            construction services or materials to a construction project 
            has the right to file a mechanic lien on the property if they 








                                                                  SB 293
                                                                  Page  4

            are not paid; however, prior to filing the lien, a 20 day 
            preliminary lien notice must be filed with the owner 
            identifying the subcontractor or material supplier and 
            notifying the owner of the potential mechanic lien in the 
            event payments are not forthcoming for work performed or 
            materials provided. In public works, instead of a mechanic 
            lien against the property title, there are "claims" that can 
            be made against the surety bond, which such bonds are required 
            for all public works projects meeting a minimum dollar 
            threshold. The 20-day notice applies in public works, but 
            provides that if the notice is not filed, the contractor is 
            not penalized and can make a claim up to 75 days after the 
            notice of completion. This area of the law has been revised to 
            ? avoid general contractors from being hit by "surprise" 
            claims from second and third tier subcontractors."

           2)Retention  proceeds represent a percentage of the amount of a 
            contract that is withheld from a progress payment by the 
            public entity to the general contractor, or the general 
            contractor from one its subcontractors. The withholding of 
            these amounts allows the public entity or general contractor 
            to maintain a degree of financial control over a project. 
            Current law requires the state and public agencies to withhold 
            at least 5% of the contract price until final completion and 
            acceptance of the project, except as follows:

             a)   For state projects, after 95% of the work has been 
               completed, the total funds withheld may be reduced to an 
               amount of at least 125% of the value of the work yet to be 
               completed.

             b)   For local agency projects, at any time after 50% of a 
               project is complete and the legislative body finds that 
               satisfactory progress is being made, it may reduce or 
               eliminate further withholding.

           3)Opposition  . In addition to several individual local government 
            entities, numerous organizations representing various sectors 
            of local government plus the CSU have jointly registered their 
            opposition to imposing a statutory retention limitation. These 
            organizations note that, unlike the private sector, they must 
            accept the lowest responsible bidder, which creates risk, and 
            they argue that limiting retention could, in some cases, 
            reduce a contractor's incentive to complete a job, thus 
            increasing costs to the public entity.








                                                                  SB 293
                                                                  Page  5

           
          4)Prior Legislation  . In 2010, AB 2216 (Fuentes), which contained 
            similar provisions, failed passage in the Senate. In 2009, SB 
            802 (Leno), which limited retention for five percent, was 
            vetoed by Governor Schwarzenegger, who expressed concern that 
            such a limit would harm public agencies' ability to complete 
            project on time and within budget. In 2008, an identical bill 
            (SB 619, Migden) passed the Assembly but was held and not sent 
            to the governor.  Several bills with similar retention 
            limitations have been vetoed: AB 806 (Keeley) of 1999; AB 940 
            (Miller) of 1997; and AB 1949 (Conroy) of 1996. 

           Analysis Prepared by  :    Chuck Nicol / APPR. / (916) 319-2081