BILL ANALYSIS                                                                                                                                                                                                    Ó



                                                                  SB 1549
                                                                  Page  1

          Date of Hearing:   July 2, 2012

                        ASSEMBLY COMMITTEE ON TRANSPORTATION
                               Bonnie Lowenthal, Chair
                     SB 1549 (Vargas) - As Amended:  July 5, 2012

           SENATE VOTE  :  38-0
           
          SUBJECT  :  Transportation projects:  alternative project delivery 
          methods

           SUMMARY  :  Authorizes San Diego Association of Governments 
          (SANDAG) to use specified alternative project delivery methods 
          for public transit projects within its jurisdiction.  
          Specifically,  this bill  :  

          1)Makes legislative findings and declarations regarding the 
            value of examining the potential benefits and challenges 
            associated with using alternative public works project 
            delivery methods.  

          2)Defines key terms, including:

             a)   "Alternative project delivery method" to mean either 
               construction manager/general contractor (CM/CG) method or 
               design-sequencing.  

             b)   "Construction manager/general contractor method" to mean 
               a project delivery method using a best value procurement 
               process in which a construction manager is procured to 
               provide preconstruction services during the design phase of 
               a project and construction services during the construction 
               phase of the project.  

             c)   "Construction manager" to mean an entity that is able to 
               provide licensed contracting and engineering services.  

             d)   "Design sequencing" to mean a method of project delivery 
               that enables the sequencing of design activities to permit 
               each construction phase to commence when the design for 
               that phase is complete, instead of requiring design for the 
               entire project to be completed before commencing 
               construction.  

          3)Authorizes SANDAG to use either the CM/CG or the 








                                                                  SB 1549
                                                                  Page  2

            design-sequencing alternative project delivery method for 
            public transit projects within its jurisdiction, under certain 
            conditions.  

          4)Prior to entering into a contract to use an alternative 
            project delivery method, SANDAG must evaluate the use of that 
            method, along with the traditional design-bid-build delivery 
            method, in a public meeting and make a written finding that 
            use of the alternative project delivery method will achieve 
            one or more of the following objectives:

             a)   Reduced project costs;

             b)   Expedited project completion; or,

             c)   Benefits not achievable through the traditional 
               design-bid-build approach.  

          5)Subjects all CM/GC contracts awarded under the authority 
            granted by this bill to existing statutes governing SANDAG's 
            procurement, including provisions related to design-build 
            contracting by transit agencies, procurement by competitive 
            negotiations, and contracts for architectural and engineering 
            services.  

          6)Subjects all design-sequencing contracts awarded under the 
            authority granted by this bill to existing statutes related to 
            procuring architectural and engineering contracts; these 
            provisions generally provide that contracts for architectural 
            and engineering services are to be awarded on a best-qualified 
            basis, with terms to be competitively negotiated.  

          7)If SANDAG enters into a CM/GC contract that includes 
            preconstruction services by the construction manager, requires 
            SANDAG to pay a fee for preconstruction services for a 
            mutually agreed to price.  SANDAG may not request or obtain 
            from the construction manager a fixed price or a guaranteed 
            maximum price for a construction contract nor enter into a 
            construction contract with the construction manager until 
            after it has entered into a preconstruction services contract. 
             The preconstruction services contract is to provide for 
            subsequent negotiation for the construction phase of the 
            project.  
             
          8)Authorizes SANDAG to enter into a contract for construction 








                                                                  SB 1549
                                                                  Page  3

            services after a project has been sufficiently developed and 
            either a fixed price or guaranteed maximum price has been 
            successfully negotiated.  Should SANDAG not be able to come to 
            terms for the construction services phases, then it may award 
            the contract using any other procurement method authorized by 
            law.  

          9)Requires the construction manager to perform at least 30% of 
            the work covered by the construction services contract.  

          10)Requires any work not performed by the construction manager 
            to be bid to subcontractors pursuant to the Subletting and 
            Subcontracting Fair Practices Act.  

          11)Provides, notwithstanding any other provision of this bill, 
            that for projects on state-owned right-of-way, the California 
            Department of Transportation (Caltrans) will be the 
            responsible agency for the performance of project development 
            services, including:

             a)   Performance specifications;

             b)   Preliminary engineering;

             c)   Pre-bid services;

             d)   Project reports;

             e)   Environmental documents; and,

             f)   Construction inspection services.  

          12)Further provides that, for these projects, Caltrans will be 
            the responsible agency for the preparation of documents 
            related to performance specifications, design characteristics, 
            material specifications, and other documents necessary to 
            describe adequately the needs of the project.  

          13)Specifically provides that Caltrans may use department 
            employees or consultants to perform the work required by this 
            bill and requires that Caltrans include the required personnel 
            resources in its annual capital outlay support budget.  

          14)Provides that nothing in this bill affects, expands, alters, 
            or limits any rights or remedies otherwise available.  








                                                                  SB 1549
                                                                  Page  4


          15)Requires SANDAG to prepare a progress report to its governing 
            body, with specified elements, and to make the report 
            available on its Internet web site.  

          16)Provides that the provisions of the bill are severable and 
            that contracts awarded pursuant to the provisions of the bill 
            are valid until the project is completed.  

          17)Justifies the need for a special law.  

           EXISTING LAW  : 

          1)Sets forth provisions governing public works contracting.  
            These provisions generally prohibit public agencies from 
            contracting with the same firm for both the design and the 
            construction phases of a project.  

          2)Provides for a limited number of design-build contracts for 
            transportation, not including public transit; sets forth 
            criteria and procedures governing their procurement.  

          3)Grants transit districts authority to enter into design-build 
            contracts for both the design and construction of public 
            transit projects using prescribed processes and procedures for 
            entering into the contracts.  

          4)Defines "design-build" to mean a procurement process in which 
            both the design and construction of a project are procured 
            from a single entity.  

          5)Does not authorize the use of design-sequencing contracts.  

          6)Requires, generally, public works construction contracts to be 
            awarded based on a process referred to as "design-bid-build."  
            This process requires the public entity, before entering into 
            any contract for construction of a project, to prepare or 
            cause to be prepared full, complete, and accurate plans, 
            specifications, and estimates of cost, "giving such directions 
            as will enable any competent mechanic or other builder to 
            carry them out."  

          7)Until January 1, 2010:  

             a)   Defined "design-sequencing" as a method of contracting 








                                                                  SB 1549
                                                                  Page  5

               that enabled the sequencing of design activities to permit 
               each construction phase to commence when design for that 
               phase is complete, instead of requiring the design for the 
               entire project to be completed before commencing 
               construction; and,

             b)   Authorized Caltrans to use the design-sequencing 
               contract method on a pilot basis-up to 12 projects in each 
               of Phase I and Phase II of the pilot program; and, required 
               Caltrans to prepare an annual status report on the progress 
               of design-sequencing contracts; also, required a final 
               report of the pilot program, detailing the positive and 
               negative aspects of design-sequencing.  

          8)Consolidates the roles and responsibilities of SANDAG with 
            many of the transit functions of the Metropolitan Transit 
            Development Board and the North San Diego County Transit 
            Development Board. (The consolidation allowed SANDAG to assume 
            transit planning, funding allocation, project development, and 
            eventually construction in the San Diego region, in addition 
            to its ongoing transportation responsibilities and other 
            regional roles.)  

          9)Prescribes SANDAG's membership and responsibilities and grants 
            SANDAG broad powers and authorities with regard to 
            transportation planning and construction.  

          10)          Generally requires that contracts for architectural 
            and engineering services must be awarded based on bidders' 
            qualifications (rather than price).  

          11)          The Subletting and Subcontracting Fair Practices 
            Act, sets forth provisions that must be followed in public 
            works contracting to thwart the occurrence of bid peddling in 
            connection with the construction, alteration, and repair of 
            public improvements "that may result in poor quality material 
            and workmanship to the detriment of the public, deprive the 
            public of the full benefits of fair competition among prime 
            contractors and subcontractors, and lead to insolvencies, loss 
            of wages to employees, and other evils."  
           
           FISCAL EFFECT  :  According to Senate Appropriations Committee, 
          potential for increased transit project costs to the extent that 
          the alternative project delivery method chosen by SANDAG results 
          in a higher overall project cost than the traditional 








                                                                  SB 1549
                                                                  Page  6

          design-bid-build method.  If an alternative delivery method is 
          chosen, SANDAG must make a written finding in a public meeting 
          that the alternative method would provide a benefit that may be 
          deemed to have a greater value than project cost alone, such as 
          expedited project delivery or other features not achievable 
          through design-bid-build.  The overall value of a project may be 
          measured by criteria other than cost.  

           COMMENTS  :  For decades, the traditional process for procuring 
          public works projects has been the design-bid-build process.  
          This process relies on: 1) a design entity preparing complete 
          project design specifications and estimates; 2) the project 
          owner putting the complete package out to bid for construction; 
          and, 3) awarding the construction contract to the lowest 
          responsible bidder.  The design-bid-build process was developed 
          to protect taxpayers from extravagance, corruption, and other 
          improper practices by public officials as well as to secure a 
          fair and reasonable price for public works construction by 
          injecting competition amongst bidders into the process.  

          Although design-bid-build generally results in the lowest cost 
          construction contract, it is not without its drawbacks, 
          including:  

          1)Projects generally take longer to complete because designs 
            must be entirely completed, permits obtained, and right-of-way 
            acquired before the construction contract can be bid and 
            awarded.  

          2)Designs prepared for a competitive low-bid procurement are 
            developed to allow for a broad range of construction 
            approaches.  As a result, low-bid designs do not always equate 
            to the most efficient design possible, depending on a 
            particular contractor's particular strengths or capabilities.  


          3)Because the project designer does not have the benefit of 
            consulting with the entity that will ultimately be responsible 
            for construction of the project, there may be significant 
            issues that the designer does not anticipate, particularly 
            constructability issues.  This can result in change orders 
            that ultimately drive up the price of the contract.  

          4)Low-bid is not always the least expensive option, once change 
            orders and contractor claims are factored into the overall 








                                                                  SB 1549
                                                                  Page  7

            project costs.  

           Design-build:

           In the early 1990s, public works agencies grew frustrated with 
          design-bid-build and began experimenting with more innovative 
          project delivery methods, namely design-build.  Design-build is 
          an alternate method for procuring design and construction 
          services that provides for the delivery of public works projects 
          from a single entity.  Design-build combines project design, 
          permit, and construction schedules in order to streamline the 
          traditional design-bid-build environment.  

          Design-build differs from design-bid-build in some key areas, 
          including:

          1)Shorter overall elapsed project delivery time because 
            construction can begin before final design is complete.  

          2)Project costs and schedule risks are more heavily borne by the 
            design-build contractor.  

          3)Construction claims and change orders are minimized.  

          4)Designs can be developed to take advantage of particular 
            contractor's strengths and abilities, thereby reducing the 
            need to "over-design" for generic use as in design-bid-build.  


          5)Project specifications are typically based on definitive 
            performance criteria (which may or may not be well established 
            by the project owner) rather than established specifications.  


          6)Contracts are awarded based on best-value analyses rather than 
            low-bid.  

          Design-build contracts are not without their drawbacks as well.  
          For example, with a design-build project, the project owner must 
          give up a good deal of control over the details of the project 
          design.  Additionally, design-build contractors are typically 
          selected using qualifications-based selection criteria or best 
          value analysis.  These approaches are more subjective than a 
          low-bid approach, potentially subjecting the public works owner 
          to greater contract challenges and higher costs.  








                                                                  SB 1549
                                                                  Page  8




           Design-sequencing:  

          Design-sequencing was first authorized in 1999 by AB 405 (Knox) 
          Chapter 378, Statutes of 1999, which established the original 
          design-sequencing pilot program within Caltrans for up to six 
          projects.  The intent of AB 405 (Knox) was to offer an 
          alternative means to accelerate project delivery over 
          traditional means of contracting for highway improvements.  
          Under the traditional means, construction of any portion of the 
          project cannot commence until Caltrans has developed complete 
          plans and specifications for the project, placed the contract 
          out for bid, and awarded the contract.  AB 405 (Knox) sought to 
          test a form of contracting referred to as "design-sequencing" 
          that would speed completion of a project by allowing 
          construction on one phase of the project to be started while 
          other phases of the project were still under design.  As part of 
          the pilot program, Caltrans was to report to the Legislature on 
          the effectiveness of the program.  

          Of the 12 design-sequencing projects authorized as Phase I of 
          the pilot program, Caltrans initiated 10 projects before the end 
          of that phase.  SB 1210 (Torlakson), Chapter 795, Statutes of 
          2004, created Phase II of the pilot program and authorized an 
          additional 12 design-sequencing projects between January 2005 
          and January 2010.  Of those, Caltrans initiated 11 projects.  

          In discussions with Caltrans, staff acknowledges that not all 
          design-sequencing projects have met with success.  In fact, 
          Caltrans suggests that lessons learned from some of the early 
          failures caused the department to take a more conservative 
          approach in its use of design-sequencing contracts.  This in 
          turn resulted in some of the authorized design-sequencing 
          projects going unused.  

          Caltrans asserts that design-sequencing has the potential to 
          accelerate project delivery (or avoid project delays) with 
          minimal risks.  Caltrans has argued that more needs to be 
          learned regarding design-sequence contracts to develop the 
          appropriate procedures, engineering mind set, and agency culture 
          needed to effectively implement this approach and to determine 
          the types of projects that would most benefit from use of this 
          approach.  








                                                                  SB 1549
                                                                  Page  9


          In interim reports of the design-sequencing pilot program, 
          Caltrans reports mixed results in the initial design-sequencing 
          projects when compared to projects in the control group.  
          However, according to Caltrans staff, findings from some of the 
          more recent projects are more positive, due largely to the 
          refined criteria Caltrans is using to select appropriate 
          design-sequencing projects.  In fact, in its 2010 status of the 
          previous design-sequencing program, Caltrans states, "The 
          Department envisions design-sequencing as a valuable project 
          delivery tool that can reduce project completion time when 
          properly used on appropriately selected projects."  

           Alternative Project Delivery Methods:

           This bill authorizes SANDAG to use CM/GC, an emerging project 
          delivery method that potentially combines the best of both 
          design-bid-build and design-build.  Using CM/GC, SANDAG will be 
          able to engage a design and construction management consultant 
          (construction manager) to act as its consultant during the 
          pre-construction phase and as the general contractor during 
          construction.  During the design phase, the construction manager 
          acts in an advisory role, providing constructability reviews, 
          value engineering suggestions, construction estimates, and other 
          construction-related recommendations.  Later, SANDAG and the 
          construction manager can agree that the project design has 
          progressed to a sufficient enough point that construction may 
          begin.  The two parties then work out mutually agreeable terms 
          and conditions for the construction contract, and, if all goes 
          well, the construction manager becomes the general contractor 
          and construction on the project commences, well before design is 
          entirely complete.  

          The CM/CG process is meant to provide continuity and 
          collaboration between the design and construction phases of the 
          project.  Construction managers have an incentive to provide 
          input during the design phase that will enhance constructability 
          of the project later because they know that they will have the 
          opportunity to become the general contractor for the project.  
          Furthermore, CM/CG promises to save project delivery time, 
          provide earlier cost certainty, transfer risks from SANDAG to 
          the contractor, and ensure project constructability.  
          Additionally, CM/CG will allow SANDAG to have greater control of 
          design decisions.  It also allows SANDAG to design the project 
          to compliment the CM/CG's strengths and capabilities, thereby 








                                                                  SB 1549
                                                                  Page  10

          avoiding the need to over-design the project to provide maximum 
          competitiveness in a low-bid procurement.  
          
           This bill also allows SANDAG to use design-sequencing.  
          Caltrans' efforts to date indicate that this project delivery 
          tool offers the potential to minimize risks, increase 
          efficiencies, reduce costs, and speed project delivery.  

          Writing in support of this bill, SANDAG explains that it has an 
          ambitious capital improvement program comprising more than $850 
          million in Fiscal Year 2012 alone.  It anticipates using the 
          alternative project delivery method authority provided for in SB 
          1549 to accelerate infrastructure projects during a 
          low-construction-cost environment.  

          Professional Engineers in California Government (PECG) opposes 
          SB 1549 because it believes that if design-sequencing 
          authorization is provided for the State Highway System it should 
          be done on a statewide basis and not limited to SANDAG.  PECG 
          also suggests that the use of CM/CG, an "untested procurement 
          methodology," should be limited to a trial of no more than four 
          projects.  

          Also in opposition, the American Council of Engineering 
          Companies (ACEC) objects to provisions that name Caltrans the 
          responsible agency for performing project development services 
          and construction inspection services for projects on the State 
          Highway System.   
           
          Related legislation: AB 294 (Portantino) authorizes Caltrans to 
          use the design-sequencing method procurement for up to five 
          transportation projects until January 1, 2015.  That bill is 
          currently on the inactive file in the Senate.  

          AB 2498 (Gordon) authorizes Caltrans to use CM/GC for up to four 
          projects, using a substantially similar process as prescribed in 
          SB 1549.  That bill is currently pending in Senate 
          Appropriations Committee.  

           Double referred  :  This bill was also heard in the Assembly 
          Committee on Local Government and passed out on June 27, 2012 
          with a vote of 9-0.  

           REGISTERED SUPPORT / OPPOSITION  :









                                                                  SB 1549
                                                                  Page  11

           Support 
           
          San Diego Association of Governments (sponsor)
          Automobile Club of Southern California 
          Metropolitan Transit System 
           
            Opposition 
           
          American Council of Engineering Companies 
          Professional Engineers in California Government
           

          Analysis Prepared by  :   Janet Dawson / TRANS. / (916) 319-2093