BILL ANALYSIS Ó SB 1549 Page 1 Date of Hearing: July 2, 2012 ASSEMBLY COMMITTEE ON TRANSPORTATION Bonnie Lowenthal, Chair SB 1549 (Vargas) - As Amended: July 5, 2012 SENATE VOTE : 38-0 SUBJECT : Transportation projects: alternative project delivery methods SUMMARY : Authorizes San Diego Association of Governments (SANDAG) to use specified alternative project delivery methods for public transit projects within its jurisdiction. Specifically, this bill : 1)Makes legislative findings and declarations regarding the value of examining the potential benefits and challenges associated with using alternative public works project delivery methods. 2)Defines key terms, including: a) "Alternative project delivery method" to mean either construction manager/general contractor (CM/CG) method or design-sequencing. b) "Construction manager/general contractor method" to mean a project delivery method using a best value procurement process in which a construction manager is procured to provide preconstruction services during the design phase of a project and construction services during the construction phase of the project. c) "Construction manager" to mean an entity that is able to provide licensed contracting and engineering services. d) "Design sequencing" to mean a method of project delivery that enables the sequencing of design activities to permit each construction phase to commence when the design for that phase is complete, instead of requiring design for the entire project to be completed before commencing construction. 3)Authorizes SANDAG to use either the CM/CG or the SB 1549 Page 2 design-sequencing alternative project delivery method for public transit projects within its jurisdiction, under certain conditions. 4)Prior to entering into a contract to use an alternative project delivery method, SANDAG must evaluate the use of that method, along with the traditional design-bid-build delivery method, in a public meeting and make a written finding that use of the alternative project delivery method will achieve one or more of the following objectives: a) Reduced project costs; b) Expedited project completion; or, c) Benefits not achievable through the traditional design-bid-build approach. 5)Subjects all CM/GC contracts awarded under the authority granted by this bill to existing statutes governing SANDAG's procurement, including provisions related to design-build contracting by transit agencies, procurement by competitive negotiations, and contracts for architectural and engineering services. 6)Subjects all design-sequencing contracts awarded under the authority granted by this bill to existing statutes related to procuring architectural and engineering contracts; these provisions generally provide that contracts for architectural and engineering services are to be awarded on a best-qualified basis, with terms to be competitively negotiated. 7)If SANDAG enters into a CM/GC contract that includes preconstruction services by the construction manager, requires SANDAG to pay a fee for preconstruction services for a mutually agreed to price. SANDAG may not request or obtain from the construction manager a fixed price or a guaranteed maximum price for a construction contract nor enter into a construction contract with the construction manager until after it has entered into a preconstruction services contract. The preconstruction services contract is to provide for subsequent negotiation for the construction phase of the project. 8)Authorizes SANDAG to enter into a contract for construction SB 1549 Page 3 services after a project has been sufficiently developed and either a fixed price or guaranteed maximum price has been successfully negotiated. Should SANDAG not be able to come to terms for the construction services phases, then it may award the contract using any other procurement method authorized by law. 9)Requires the construction manager to perform at least 30% of the work covered by the construction services contract. 10)Requires any work not performed by the construction manager to be bid to subcontractors pursuant to the Subletting and Subcontracting Fair Practices Act. 11)Provides, notwithstanding any other provision of this bill, that for projects on state-owned right-of-way, the California Department of Transportation (Caltrans) will be the responsible agency for the performance of project development services, including: a) Performance specifications; b) Preliminary engineering; c) Pre-bid services; d) Project reports; e) Environmental documents; and, f) Construction inspection services. 12)Further provides that, for these projects, Caltrans will be the responsible agency for the preparation of documents related to performance specifications, design characteristics, material specifications, and other documents necessary to describe adequately the needs of the project. 13)Specifically provides that Caltrans may use department employees or consultants to perform the work required by this bill and requires that Caltrans include the required personnel resources in its annual capital outlay support budget. 14)Provides that nothing in this bill affects, expands, alters, or limits any rights or remedies otherwise available. SB 1549 Page 4 15)Requires SANDAG to prepare a progress report to its governing body, with specified elements, and to make the report available on its Internet web site. 16)Provides that the provisions of the bill are severable and that contracts awarded pursuant to the provisions of the bill are valid until the project is completed. 17)Justifies the need for a special law. EXISTING LAW : 1)Sets forth provisions governing public works contracting. These provisions generally prohibit public agencies from contracting with the same firm for both the design and the construction phases of a project. 2)Provides for a limited number of design-build contracts for transportation, not including public transit; sets forth criteria and procedures governing their procurement. 3)Grants transit districts authority to enter into design-build contracts for both the design and construction of public transit projects using prescribed processes and procedures for entering into the contracts. 4)Defines "design-build" to mean a procurement process in which both the design and construction of a project are procured from a single entity. 5)Does not authorize the use of design-sequencing contracts. 6)Requires, generally, public works construction contracts to be awarded based on a process referred to as "design-bid-build." This process requires the public entity, before entering into any contract for construction of a project, to prepare or cause to be prepared full, complete, and accurate plans, specifications, and estimates of cost, "giving such directions as will enable any competent mechanic or other builder to carry them out." 7)Until January 1, 2010: a) Defined "design-sequencing" as a method of contracting SB 1549 Page 5 that enabled the sequencing of design activities to permit each construction phase to commence when design for that phase is complete, instead of requiring the design for the entire project to be completed before commencing construction; and, b) Authorized Caltrans to use the design-sequencing contract method on a pilot basis-up to 12 projects in each of Phase I and Phase II of the pilot program; and, required Caltrans to prepare an annual status report on the progress of design-sequencing contracts; also, required a final report of the pilot program, detailing the positive and negative aspects of design-sequencing. 8)Consolidates the roles and responsibilities of SANDAG with many of the transit functions of the Metropolitan Transit Development Board and the North San Diego County Transit Development Board. (The consolidation allowed SANDAG to assume transit planning, funding allocation, project development, and eventually construction in the San Diego region, in addition to its ongoing transportation responsibilities and other regional roles.) 9)Prescribes SANDAG's membership and responsibilities and grants SANDAG broad powers and authorities with regard to transportation planning and construction. 10) Generally requires that contracts for architectural and engineering services must be awarded based on bidders' qualifications (rather than price). 11) The Subletting and Subcontracting Fair Practices Act, sets forth provisions that must be followed in public works contracting to thwart the occurrence of bid peddling in connection with the construction, alteration, and repair of public improvements "that may result in poor quality material and workmanship to the detriment of the public, deprive the public of the full benefits of fair competition among prime contractors and subcontractors, and lead to insolvencies, loss of wages to employees, and other evils." FISCAL EFFECT : According to Senate Appropriations Committee, potential for increased transit project costs to the extent that the alternative project delivery method chosen by SANDAG results in a higher overall project cost than the traditional SB 1549 Page 6 design-bid-build method. If an alternative delivery method is chosen, SANDAG must make a written finding in a public meeting that the alternative method would provide a benefit that may be deemed to have a greater value than project cost alone, such as expedited project delivery or other features not achievable through design-bid-build. The overall value of a project may be measured by criteria other than cost. COMMENTS : For decades, the traditional process for procuring public works projects has been the design-bid-build process. This process relies on: 1) a design entity preparing complete project design specifications and estimates; 2) the project owner putting the complete package out to bid for construction; and, 3) awarding the construction contract to the lowest responsible bidder. The design-bid-build process was developed to protect taxpayers from extravagance, corruption, and other improper practices by public officials as well as to secure a fair and reasonable price for public works construction by injecting competition amongst bidders into the process. Although design-bid-build generally results in the lowest cost construction contract, it is not without its drawbacks, including: 1)Projects generally take longer to complete because designs must be entirely completed, permits obtained, and right-of-way acquired before the construction contract can be bid and awarded. 2)Designs prepared for a competitive low-bid procurement are developed to allow for a broad range of construction approaches. As a result, low-bid designs do not always equate to the most efficient design possible, depending on a particular contractor's particular strengths or capabilities. 3)Because the project designer does not have the benefit of consulting with the entity that will ultimately be responsible for construction of the project, there may be significant issues that the designer does not anticipate, particularly constructability issues. This can result in change orders that ultimately drive up the price of the contract. 4)Low-bid is not always the least expensive option, once change orders and contractor claims are factored into the overall SB 1549 Page 7 project costs. Design-build: In the early 1990s, public works agencies grew frustrated with design-bid-build and began experimenting with more innovative project delivery methods, namely design-build. Design-build is an alternate method for procuring design and construction services that provides for the delivery of public works projects from a single entity. Design-build combines project design, permit, and construction schedules in order to streamline the traditional design-bid-build environment. Design-build differs from design-bid-build in some key areas, including: 1)Shorter overall elapsed project delivery time because construction can begin before final design is complete. 2)Project costs and schedule risks are more heavily borne by the design-build contractor. 3)Construction claims and change orders are minimized. 4)Designs can be developed to take advantage of particular contractor's strengths and abilities, thereby reducing the need to "over-design" for generic use as in design-bid-build. 5)Project specifications are typically based on definitive performance criteria (which may or may not be well established by the project owner) rather than established specifications. 6)Contracts are awarded based on best-value analyses rather than low-bid. Design-build contracts are not without their drawbacks as well. For example, with a design-build project, the project owner must give up a good deal of control over the details of the project design. Additionally, design-build contractors are typically selected using qualifications-based selection criteria or best value analysis. These approaches are more subjective than a low-bid approach, potentially subjecting the public works owner to greater contract challenges and higher costs. SB 1549 Page 8 Design-sequencing: Design-sequencing was first authorized in 1999 by AB 405 (Knox) Chapter 378, Statutes of 1999, which established the original design-sequencing pilot program within Caltrans for up to six projects. The intent of AB 405 (Knox) was to offer an alternative means to accelerate project delivery over traditional means of contracting for highway improvements. Under the traditional means, construction of any portion of the project cannot commence until Caltrans has developed complete plans and specifications for the project, placed the contract out for bid, and awarded the contract. AB 405 (Knox) sought to test a form of contracting referred to as "design-sequencing" that would speed completion of a project by allowing construction on one phase of the project to be started while other phases of the project were still under design. As part of the pilot program, Caltrans was to report to the Legislature on the effectiveness of the program. Of the 12 design-sequencing projects authorized as Phase I of the pilot program, Caltrans initiated 10 projects before the end of that phase. SB 1210 (Torlakson), Chapter 795, Statutes of 2004, created Phase II of the pilot program and authorized an additional 12 design-sequencing projects between January 2005 and January 2010. Of those, Caltrans initiated 11 projects. In discussions with Caltrans, staff acknowledges that not all design-sequencing projects have met with success. In fact, Caltrans suggests that lessons learned from some of the early failures caused the department to take a more conservative approach in its use of design-sequencing contracts. This in turn resulted in some of the authorized design-sequencing projects going unused. Caltrans asserts that design-sequencing has the potential to accelerate project delivery (or avoid project delays) with minimal risks. Caltrans has argued that more needs to be learned regarding design-sequence contracts to develop the appropriate procedures, engineering mind set, and agency culture needed to effectively implement this approach and to determine the types of projects that would most benefit from use of this approach. SB 1549 Page 9 In interim reports of the design-sequencing pilot program, Caltrans reports mixed results in the initial design-sequencing projects when compared to projects in the control group. However, according to Caltrans staff, findings from some of the more recent projects are more positive, due largely to the refined criteria Caltrans is using to select appropriate design-sequencing projects. In fact, in its 2010 status of the previous design-sequencing program, Caltrans states, "The Department envisions design-sequencing as a valuable project delivery tool that can reduce project completion time when properly used on appropriately selected projects." Alternative Project Delivery Methods: This bill authorizes SANDAG to use CM/GC, an emerging project delivery method that potentially combines the best of both design-bid-build and design-build. Using CM/GC, SANDAG will be able to engage a design and construction management consultant (construction manager) to act as its consultant during the pre-construction phase and as the general contractor during construction. During the design phase, the construction manager acts in an advisory role, providing constructability reviews, value engineering suggestions, construction estimates, and other construction-related recommendations. Later, SANDAG and the construction manager can agree that the project design has progressed to a sufficient enough point that construction may begin. The two parties then work out mutually agreeable terms and conditions for the construction contract, and, if all goes well, the construction manager becomes the general contractor and construction on the project commences, well before design is entirely complete. The CM/CG process is meant to provide continuity and collaboration between the design and construction phases of the project. Construction managers have an incentive to provide input during the design phase that will enhance constructability of the project later because they know that they will have the opportunity to become the general contractor for the project. Furthermore, CM/CG promises to save project delivery time, provide earlier cost certainty, transfer risks from SANDAG to the contractor, and ensure project constructability. Additionally, CM/CG will allow SANDAG to have greater control of design decisions. It also allows SANDAG to design the project to compliment the CM/CG's strengths and capabilities, thereby SB 1549 Page 10 avoiding the need to over-design the project to provide maximum competitiveness in a low-bid procurement. This bill also allows SANDAG to use design-sequencing. Caltrans' efforts to date indicate that this project delivery tool offers the potential to minimize risks, increase efficiencies, reduce costs, and speed project delivery. Writing in support of this bill, SANDAG explains that it has an ambitious capital improvement program comprising more than $850 million in Fiscal Year 2012 alone. It anticipates using the alternative project delivery method authority provided for in SB 1549 to accelerate infrastructure projects during a low-construction-cost environment. Professional Engineers in California Government (PECG) opposes SB 1549 because it believes that if design-sequencing authorization is provided for the State Highway System it should be done on a statewide basis and not limited to SANDAG. PECG also suggests that the use of CM/CG, an "untested procurement methodology," should be limited to a trial of no more than four projects. Also in opposition, the American Council of Engineering Companies (ACEC) objects to provisions that name Caltrans the responsible agency for performing project development services and construction inspection services for projects on the State Highway System. Related legislation: AB 294 (Portantino) authorizes Caltrans to use the design-sequencing method procurement for up to five transportation projects until January 1, 2015. That bill is currently on the inactive file in the Senate. AB 2498 (Gordon) authorizes Caltrans to use CM/GC for up to four projects, using a substantially similar process as prescribed in SB 1549. That bill is currently pending in Senate Appropriations Committee. Double referred : This bill was also heard in the Assembly Committee on Local Government and passed out on June 27, 2012 with a vote of 9-0. REGISTERED SUPPORT / OPPOSITION : SB 1549 Page 11 Support San Diego Association of Governments (sponsor) Automobile Club of Southern California Metropolitan Transit System Opposition American Council of Engineering Companies Professional Engineers in California Government Analysis Prepared by : Janet Dawson / TRANS. / (916) 319-2093