BILL ANALYSIS Ó SENATE GOVERNANCE & FINANCE COMMITTEE Senator Lois Wolk, Chair BILL NO: AB 195 HEARING: 6/12/13 AUTHOR: Hall FISCAL: Yes VERSION: 5/20/13 TAX LEVY: No CONSULTANT: Weinberger DESIGN BUILD CONTRACTING Extends, from July 1, 2014 to July 1, 2016, the date on which the statutes authorizing counties to use the design-build contracting method expire. Background and Existing Law The Local Agency Public Construction Act requires local officials to invite bids for construction projects and then award contracts to the lowest responsible bid-der. This design-bid-build method is the traditional and most widely-used approach to public works construction. This approach splits construction projects into two distinct phases: design and construction. During the design phase, the local agency prepares detailed project plans and specifications using its own employees or by hiring outside architects and engineers. Once project designs are complete, local officials invite bids from the construction community and award the contract to the lowest responsible bidder. By contrast, state law also allows state and local officials to use the design-build method to procure both design and construction services from a single company before the development of complete plans and specifications. Under design-build, the owner contracts with a single entity - which can be a single firm, a consortium, or a joint venture - to design and construct a project. Before inviting bids, the owner prepares documents that describe the basic concept of the project, as opposed to a complete set of drawings and specifications of the final product. In the bidding phase, the owner typically evaluates bids on a best-value basis, incorporating technical factors, such as qualifications and design quality, in addition to price. AB 195 -- 5/20/13 -- Page 2 All counties can use the design-build method to construct buildings and related improvements and wastewater treatment facilities that cost more than $2.5 million (SB 416, Ashburn, 2007). State law requires each county that uses the design-build method on a public works project procured and completed between November 1, 2009 and August 1, 2013 to submit a report to the Legislative Analyst's Office (LAO) before September 1, 2013. On or before January 1, 2014, the LAO must submit a report to the Legislature on counties' use of the design-build method. The report must contain specified information, including: A fact-based analysis utilizing the information provided in the reports submitted by counties and any independent information provided by the public or interested parties. Conclusions describing the actual cost of projects procured pursuant to this section, whether the project schedule was met or altered, and whether projects needed or used project change orders. Under current law, the statutes authorizing counties to use the design-build method expire on July 1, 2014 (SB 879, Cox, 2010). County officials want to give the Legislature more time, after receiving the LAO report, to consider whether to extend or eliminate this statutory sunset date. Proposed Law Assembly Bill 195 extends, from July 1, 2014 to July 1, 2016, the date on which the statutes authorizing counties to use the design-build contracting method expire. State Revenue Impact No estimate. Comments 1. Purpose of the bill . In 2010, the Legislative Analyst's Office investigated five design-build projects and found that four of those projects were completed under budget. The LAO noted that counties that have used design-build generally expressed favorable opinions of the AB 195 -- 5/20/13 -- Page 3 process. Almost all reported that compared to the traditional design-bid-build process, it took less staff time to construct a project and resulted in fewer claims and less litigation. After considering the LAO's findings and holding a hearing on counties' use of design-build contracting, legislators passed a bill extending the county design-build statutes until mid-2014. That bill also required the LAO to provide the Legislature with updated information on county design-build projects by the end of 2013. With just six months between the date the LAO report is due and the date that the statutes expire, county officials worry that legislators won't have enough time to consider another extension next year. AB 195 ensures that counties won't lose their ability to use this successful, cost-effective project delivery system. 2. What's the rush ? The requirement for design-bid-build contracts was a reaction to the favoritism, corruption, and waste associated with major public works projects in the 19th Century. Ever since the reforms that separated the design and construction phases at the turn of the 20th Century, design-bid-build contracts became the norm. Responding to local officials' requests for more flexibility, legislators have loosened the statutes to allow experiments with design-build contracts. AB 195's opponents contend that design-build does not guarantee cost savings, reduces competitive bidding, and lacks impartial inspection procedures, which can put the public at risk for failed construction projects. In its last review, the LAO learned that five counties completed five design-build projects in recent years, with 10 more projects still underway. This small sample of county design-build projects may not be enough to justify a two-year extension before the LAO provides the updated report that is due by January 1, 2014. The Committee may wish to consider whether it is premature to extend counties' design-build statute before considering the pending report from the LAO. 3. Related legislation . At its May 1, 2013 hearing, by a vote of 7-0, the Senate Governance & Finance Committee approved SB 785 (Wolk), which enacts new, uniform statutes governing public agencies' design-build contracts. The bill is currently on the Senate Floor Inactive File. Assembly Actions AB 195 -- 5/20/13 -- Page 4 Assembly Local Government Committee: 7-1 Assembly Appropriations Committee:16-1 Assembly Floor: 59-9 Support and Opposition (6/6/13) Support : California State Association of Counties; Counties of Kern, Los Angeles, Merced, Napa, Orange, Sacramento, San Bernardino, San Diego, Santa Clara, Solano, Sonoma, and Stanislaus; Urban Counties Caucus; Associated General Contractors; California Chapter of the National electrical Contractors Association; California Legislative Conference of the Plumbing, Heating, and Piping Industry; California State Sheriffs' Association; CH2M Hill; Design-Build Institute of America; Rural County Representatives of California; San Francisco Unified School District. Opposition : Air Conditioning Trade Association; Plumbing-Heating-Cooling Contractors Association of California; Professional Engineers in California Government; Western Electrical Contractors Association.