California Legislature—2013–14 Regular Session

Assembly BillNo. 536


Introduced by Assembly Member Wagner

February 20, 2013


An act to amend Section 7108.5 of the Business and Professions Code, to amend Sections 8800, 8802, 8812, 8814, and 8818 of the Civil Code, and to amend Sections 7107 and 10262.5 of the Public Contract Code, relating to contracts.

LEGISLATIVE COUNSEL’S DIGEST

AB 536, as introduced, Wagner. Contractors: payments.

Existing law allows specified persons to withhold for a contractor or subcontractor no more than 150% of the disputed amount if there is a good faith dispute over the amount due on a contract payment.

This bill would exclude specified amounts from being considered disputed amounts and would provide that the authorized withholding is not wrongfully withheld.

Vote: majority. Appropriation: no. Fiscal committee: no. State-mandated local program: no.

The people of the State of California do enact as follows:

P1    1

SECTION 1.  

Section 7108.5 of the Business and Professions
2Code
is amended to read:

3

7108.5.  

(a) A prime contractor or subcontractor shall pay to
4any subcontractor, not later than seven days after receipt of each
5progress payment, unless otherwise agreed to in writing, the
6respective amounts allowed the contractor on account of the work
7performed by the subcontractors, to the extent of each
P2    1subcontractor’s interest therein. In the event that there is a good
2faith dispute over all or any portion of the amount due on a progress
3payment from the prime contractor or subcontractor to a
4subcontractor, the prime contractor or subcontractor may withhold
5no more than 150 percent of the disputed amount.

6(b) Any violation of this section shall constitute a cause for
7disciplinary action and shall subject the licensee to a penalty,
8payable to the subcontractor, of 2 percent of the amount due per
9month for every month that payment is not made.begin insert The amount
10withheld pursuant to subdivision (a) is not a violation of this
11section and is not an amount due for purposes of this section.end insert

12(c) In any action for the collection of funds wrongfully withheld,
13the prevailing party shall be entitled to his or her attorney’s fees
14and costs.begin insert The amount withheld pursuant to subdivision (a) is not
15wrongfully withheld.end insert

16(d) The sanctions authorized under this section shall be separate
17from, and in addition to, all other remedies, either civil,
18administrative, or criminal.

19(e) This section applies to all private works of improvement
20and to all public works of improvement, except where Section
2110262 of the Public Contract Code applies.

begin insert

22(f) For purposes of this section, a “disputed amount” shall not
23include any of the following:

end insert
begin insert

24(1) Any amount in excess of liquidated damages owed by the
25subcontractor.

end insert
begin insert

26(2) Any amount in excess of what the prime contractor or
27subcontractor is allowed by law to withhold from the subcontractor
28on account of a mechanics lien being recorded or a stop payment
29notice being served for labor, services, equipment, or materials
30allegedly provided to the project.

end insert
begin insert

31(3) The amount of any claim for additional compensation arising
32out of alleged extra work performed by the subcontractor or an
33alleged breach of contract by the prime contractor or
34subcontractor.

end insert
35

SEC. 2.  

Section 8800 of the Civil Code is amended to read:

36

8800.  

(a) Except as otherwise agreed in writing by the owner
37and direct contractor, the owner shall pay the direct contractor,
38within 30 days after notice demanding payment pursuant to the
39contract is given, any progress payment due as to which there is
40no good faith dispute between them. The notice given shall comply
P3    1with the requirements of Chapter 2 (commencing with Section
28100) of Title 1.

3(b) If there is a good faith dispute between the owner and direct
4contractor as to a progress payment due, the owner may withhold
5from the progress payment an amount not in excess of 150 percent
6of the disputed amount.

7(c) An owner that violates this section is liable to the direct
8contractor for a penalty of 2 percent per month on the amount
9wrongfully withheld, in place of any interest otherwise due. In an
10action for collection of the amount wrongfully withheld, the
11prevailing party is entitled to costs and a reasonable attorney’s fee.
12begin insert The amount withheld pursuant to subdivision (b) is not a violation
13of this section and is not wrongfully withheld.end insert

14(d) This section does not supersede any requirement of Article
152 (commencing with Section 8810) relating to the withholding of
16a retention.

begin insert

17(e) For purposes of this section, a “disputed amount” shall not
18include any of the following:

end insert
begin insert

19(1) Any amount in excess of liquidated damages owed by the
20direct contractor.

end insert
begin insert

21(2) Any amount in excess of what the owner is allowed by law
22to withhold from the direct contractor on account of a mechanics
23lien being recorded or a stop payment notice being served for
24labor, services, equipment, or materials allegedly provided to the
25project.

end insert
begin insert

26(3) The amount of any claim for additional compensation arising
27out of alleged extra work performed by the direct contractor or
28an alleged breach of contract by the owner.

end insert
29

SEC. 3.  

Section 8802 of the Civil Code is amended to read:

30

8802.  

(a) This section applies to a contract between a public
31utility and a direct contractor for all or part of a work of
32improvement.

33(b) Unless the direct contractor and a subcontractor otherwise
34agree in writing, within 21 days after receipt of a progress payment
35from the public utility the direct contractor shall pay the
36subcontractor the amount allowed the direct contractor on account
37of the work performed by the subcontractor to the extent of the
38subcontractor’s interest in the work. If there is a good faith dispute
39over all or part of the amount due on a progress payment from the
40direct contractor to a subcontractor, the direct contractor may
P4    1withhold an amount not in excess of 150 percent of the disputed
2amount.

3(c) A direct contractor that violates this section is liable to the
4subcontractor for a penalty of 2 percent of the disputed amount
5due per month for every month that payment is not made. In an
6action for collection of the amount wrongfully withheld, the
7prevailing party is entitled to costs and a reasonable attorney’s fee.
8begin insert The amount withheld pursuant to subdivision (b) is not a violation
9of this section and is not wrongfully withheld.end insert

10(d) This section does not limit or impair a contractual,
11administrative, or judicial remedy otherwise available to a
12contractor or subcontractor in a dispute involving late payment or
13nonpayment by the contractor or deficient performance or
14nonperformance by the subcontractor.

begin insert

15(e) For purposes of this section, a “disputed amount” shall not
16include any of the following:

end insert
begin insert

17(1) Any amount in excess of liquidated damages owed by the
18subcontractor.

end insert
begin insert

19(2) Any amount in excess of what the direct contractor is allowed
20by law to withhold from the subcontractor on account of a
21mechanics lien being recorded or a stop payment notice being
22served for labor, services, equipment, or materials allegedly
23provided to the project.

end insert
begin insert

24(3) The amount of any claim for additional compensation arising
25out of alleged extra work performed by the subcontractor or an
26alleged breach of contract by the direct contractor.

end insert
27

SEC. 4.  

Section 8812 of the Civil Code is amended to read:

28

8812.  

(a) If an owner withholds a retention from a direct
29contractor, the owner shall, within 45 days after completion of the
30work of improvement, pay the retention to the contractor.

31(b) If part of a work of improvement ultimately will become
32the property of a public entity, the owner may condition payment
33of a retention allocable to that part on acceptance of the part by
34the public entity.

35(c) If there is a good faith dispute between the owner and direct
36contractor as to a retention payment due, the owner may withhold
37from final payment an amount not in excess of 150 percent of the
38disputed amount.begin insert This withheld amount shall not be considered
39wrongfully withheld.end insert

begin insert

P5    1(d) For purposes of this section, a “disputed amount” shall not
2include any of the following:

end insert
begin insert

3(1) Any amount in excess of liquidated damages owed by the
4direct contractor.

end insert
begin insert

5(2) Any amount in excess of what the owner is allowed by law
6to withhold from the direct contractor on account of a mechanics
7lien being recorded or a stop payment notice being served for
8labor, services, equipment, or materials allegedly provided to the
9project.

end insert
begin insert

10(3) The amount of any claim for additional compensation arising
11out of alleged extra work performed by the direct contractor or
12an alleged breach of contract by the owner.

end insert
13

SEC. 5.  

Section 8814 of the Civil Code is amended to read:

14

8814.  

(a) If a direct contractor has withheld a retention from
15one or more subcontractors, the direct contractor shall, within 10
16days after receiving all or part of a retention payment, pay to each
17subcontractor from whom retention has been withheld that
18subcontractor’s share of the payment.

19(b) If a retention received by the direct contractor is specifically
20designated for a particular subcontractor, the direct contractor shall
21pay the retention payment to the designated subcontractor, if
22consistent with the terms of the subcontract.

23(c) If a good faith dispute exists between the direct contractor
24and a subcontractor, the direct contractor may withhold from the
25retention to the subcontractor an amount not in excess of 150
26percent of the estimated value of the disputed amount.begin insert This
27withheld amount shall not be considered wrongfully withheld.end insert

begin insert

28(d) For purposes of this section, a “disputed amount” shall not
29include any of the following:

end insert
begin insert

30(1) Any amount in excess of liquidated damages owed by the
31subcontractor.

end insert
begin insert

32(2) Any amount in excess of what the direct contractor is allowed
33by law to withhold from the subcontractor on account of a
34mechanics lien being recorded or a stop payment notice being
35served for labor, services, equipment, or materials allegedly
36provided to the project.

end insert
begin insert

37(3) The amount of any claim for additional compensation arising
38out of alleged extra work performed by the subcontractor or an
39alleged breach of the subcontract by the direct contractor.

end insert
40

SEC. 6.  

Section 8818 of the Civil Code is amended to read:

P6    1

8818.  

If an owner or direct contractor does not make a retention
2payment within the time required by this article:

3(a) The owner or direct contractor is liable to the person to which
4payment is owed for a penalty of 2 percent per month on the
5amount wrongfully withheld, in place of any interest otherwise
6due.

7(b) In an action for collection of the amount wrongfully
8withheld, the prevailing party is entitled to costs and reasonable
9attorney’s fees.

begin insert

10(c) Amounts authorized to be withheld pursuant to this article
11are not a payment required to be made and are not wrongfully
12withheld.

end insert
13

SEC. 7.  

Section 7107 of the Public Contract Code is amended
14to read:

15

7107.  

(a) This section is applicable with respect to all contracts
16entered into on or after January 1, 1993, relating to the construction
17of any public work of improvement.

18(b) The retention proceeds withheld from any payment by the
19public entity from the original contractor, or by the original
20contractor from any subcontractor, shall be subject to this section.

21(c) Within 60 days after the date of completion of the work of
22improvement, the retention withheld by the public entity shall be
23released. In the event of a dispute between the public entity and
24the original contractor, the public entity may withhold from the
25final payment an amount not to exceed 150 percent of the disputed
26amount. For purposes of this subdivision, “completion” means any
27of the following:

28(1) The occupation, beneficial use, and enjoyment of a work of
29improvement, excluding any operation only for testing, startup, or
30commissioning, by the public agency, or its agent, accompanied
31by cessation of labor on the work of improvement.

32(2) The acceptance by the public agency, or its agent, of the
33work of improvement.

34(3) After the commencement of a work of improvement, a
35cessation of labor on the work of improvement for a continuous
36period of 100 days or more, due to factors beyond the control of
37the contractor.

38(4) After the commencement of a work of improvement, a
39cessation of labor on the work of improvement for a continuous
P7    1period of 30 days or more, if the public agency files for record a
2notice of cessation or a notice of completion.

3(d) Subject to subdivision (e), within seven days from the time
4that all or any portion of the retention proceeds are received by
5the original contractor, the original contractor shall pay each of its
6subcontractors from whom retention has been withheld, each
7subcontractor’s share of the retention received. However, if a
8retention payment received by the original contractor is specifically
9designated for a particular subcontractor, payment of the retention
10shall be made to the designated subcontractor, if the payment is
11consistent with the terms of the subcontract.

12(e) The original contractor may withhold from a subcontractor
13its portion of the retention proceeds if a bona fide dispute exists
14between the subcontractor and the original contractor. The amount
15withheld from the retention payment shall not exceed 150 percent
16of the estimated value of the disputed amount.

17(f) In the event that retention payments are not made within the
18time periods required by this section, the public entity or original
19contractor withholding the unpaid amounts shall be subject to a
20charge of 2 percent per month on the improperly withheld amount,
21in lieu of any interest otherwise due. Additionally, in any action
22for the collection of funds wrongfully withheld, the prevailing
23party shall be entitled to attorney’s fees and costs.begin insert Amounts
24authorized to be withheld pursuant to this section are not a
25payment required to be made and are not wrongfully withheld.end insert

26(g) If a state agency retains an amount greater than 125 percent
27of the estimated value of the work yet to be completed pursuant
28to Section 10261, the state agency shall distribute undisputed
29retention proceeds in accordance with subdivision (c). However,
30notwithstanding subdivision (c), if a state agency retains an amount
31equal to or less than 125 percent of the estimated value of the work
32yet to be completed, the state agency shall have 90 days in which
33to release undisputed retentions.

34(h) Any attempted waiver of the provisions of this section shall
35be void as against the public policy of this state.

begin insert

36(i) For purposes of this section, a “disputed amount” shall not
37include any of the following:

end insert
begin insert

38(1) Any amount in excess of liquidated damages owed by the
39original contractor.

end insert
begin insert

P8    1(2) Any amount in excess of what the public entity is allowed
2by law to withhold from the original contractor on account of a
3stop payment notice being served for labor, services, equipment,
4or materials allegedly provided to the project.

end insert
begin insert

5(3) The amount of any claim for additional compensation arising
6out of alleged extra work performed by the original contractor or
7an alleged breach of contract by the public entity.

end insert
8

SEC. 8.  

Section 10262.5 of the Public Contract Code is
9amended to read:

10

10262.5.  

(a) begin insert(1)end insertbegin insertend insert Notwithstanding any other law, a prime
11contractor or subcontractor shall pay to any subcontractor, not later
12than seven days after receipt of each progress payment, the
13respective amounts allowed the contractor on account of the work
14performed by the subcontractors, to the extent of each
15subcontractor’s interest therein. In the event that there is a good
16faith dispute over all or any portion of the amount due on a progress
17payment from the prime contractor or subcontractor to a
18subcontractor, then the prime contractor or subcontractor may
19withhold no more than 150 percent of the disputed amount.

begin delete

20Any

end delete

21begin insert(2)end insertbegin insertend insertbegin insertAnyend insert contractor who violates this section shall pay to the
22subcontractor a penalty of 2 percent of the amount due per month
23for every month that payment is not made. In any action for the
24collection of funds wrongfully withheld, the prevailing party shall
25be entitled to his or her attorney’s fees and costs.begin insert The amount
26withheld pursuant to paragraph (1) is not a violation of this section
27 and is not wrongfully withheld.end insert

28(b) This section shall not be construed to limit or impair any
29contractual, administrative, or judicial remedies otherwise available
30to a contractor or a subcontractor in the event of a dispute involving
31late payment or nonpayment by a contractor or deficient
32subcontract performance or nonperformance by a subcontractor.

33(c) On or before September 1 of each year, the head of each
34state agency shall submit to the Legislature a report on the number
35and dollar volume of written complaints received from
36subcontractors and prime contractors on contracts in excess of
37three hundred thousand dollars ($300,000), relating to violations
38of this section.

begin insert

39(d) For purposes of this section, a “disputed amount” shall not
40include any of the following:

end insert
begin insert

P9    1(1) Any amount in excess of liquidated damages owed by the
2subcontractor.

end insert
begin insert

3(2) Any amount in excess of what the prime contractor or
4subcontractor is allowed by law to withhold from the subcontractor
5on account of a stop payment notice being served for labor,
6services, equipment, or materials allegedly provided to the project.

end insert
begin insert

7(3) The amount of any claim for additional compensation arising
8out of alleged extra work performed by the subcontractor or an
9alleged breach of the subcontract by the prime contractor or
10subcontractor.

end insert


O

    99