Amended in Assembly April 8, 2013

California Legislature—2013–14 Regular Session

Assembly BillNo. 536


Introduced by Assembly Member Wagner

February 20, 2013


An act to amend Section 7108.5 of the Business and Professions Code, to amend Sections 8800, 8802, 8812,begin insert andend insert 8814begin delete, and 8818end delete of the Civil Code, and to amend Sections 7107 and 10262.5 of the Public Contract Code, relating to contracts.

LEGISLATIVE COUNSEL’S DIGEST

AB 536, as amended, Wagner. Contractors: payments.

Existing law allows specified persons to withholdbegin delete forend deletebegin insert fromend insert a contractor or subcontractor no more than 150% of the disputed amount if there is a good faith dispute over the amount due on a contract payment.

This bill would exclude specified amounts from being considered disputed amountsbegin delete and would provide that the authorized withholding is not wrongfully withheldend delete.

Vote: majority. Appropriation: no. Fiscal committee: no. State-mandated local program: no.

The people of the State of California do enact as follows:

P1    1

SECTION 1.  

Section 7108.5 of the Business and Professions
2Code
is amended to read:

3

7108.5.  

(a) A prime contractor or subcontractor shall pay to
4any subcontractor, not later than seven days after receipt of each
5progress payment, unless otherwise agreed to in writing, the
6respective amounts allowed the contractor on account of the work
P2    1performed by the subcontractors, to the extent of each
2subcontractor’s interest therein. In the event that there is a good
3faith dispute over all or any portion of the amount due on a progress
4payment from the prime contractor or subcontractor to a
5subcontractor, the prime contractor or subcontractor may withhold
6no more than 150 percent of the disputed amount.

7(b) Any violation of this section shall constitute a cause for
8disciplinary action and shall subject the licensee to a penalty,
9payable to the subcontractor, of 2 percent of the amount due per
10month for every month that payment is not made.begin delete The amount
11withheld pursuant to subdivision (a) is not a violation of this section
12and is not an amount due for purposes of this section.end delete

13(c) In any action for the collection of funds wrongfully withheld,
14the prevailing party shall be entitled to his or herbegin delete attorney’send delete
15begin insert attorneys’end insert fees and costs.begin delete The amount withheld pursuant to
16subdivision (a) is not wrongfully withheld.end delete

17(d) The sanctions authorized under this section shall be separate
18from, and in addition to, all other remedies, either civil,
19administrative, or criminal.

20(e) This section applies to all private works of improvement
21and to all public works of improvement, except where Section
2210262 of the Public Contract Code applies.

23(f) For purposes of this section, a “disputed amount” shall not
24include any of the following:

begin delete

25(1) Any amount in excess of liquidated damages owed by the
26subcontractor.

end delete
begin delete

27(2) Any amount in excess of what the prime contractor or
28subcontractor is allowed by law to withhold from the subcontractor
29on account of a mechanics lien being recorded or a stop payment
30notice being served for labor, services, equipment, or materials
31allegedly provided to the project.

end delete
begin insert

32(1) With respect to liquidated damages assessed by the owner
33against the prime contractor, any amount in excess of the
34liquidated damages that are owed by the subcontractor.

end insert
begin insert

35(2) With respect to mechanics liens and stop payment notices
36for which the subcontractor is responsible, any amount in excess
37of what the owner is permitted by law to withhold from the prime
38contractor on account of the mechanics lien or stop payment notice.

end insert

39(3) The amount of any claim for additional compensation begin delete arising
40out of alleged extra work performed by the subcontractor or an
P3    1alleged breach of contractend delete
by the begin deleteprime contractor or end deletesubcontractor
2begin insert against the prime contractorend insert.

3

SEC. 2.  

Section 8800 of the Civil Code is amended to read:

4

8800.  

(a) Except as otherwise agreed in writing by the owner
5and direct contractor, the owner shall pay the direct contractor,
6within 30 days after notice demanding payment pursuant to the
7contract is given, any progress payment due as to which there is
8no good faith dispute between them. The notice given shall comply
9with the requirements of Chapter 2 (commencing with Section
108100) of Title 1.

11(b) If there is a good faith dispute between the owner and direct
12contractor as to a progress payment due, the owner may withhold
13from the progress payment an amount not in excess of 150 percent
14of the disputed amount.

15(c) An owner that violates this section is liable to the direct
16contractor for a penalty of 2 percent per month on the amount
17wrongfully withheld, in place of any interest otherwise due. In an
18action for collection of the amount wrongfully withheld, the
19prevailing party is entitled to costs andbegin delete aend delete reasonablebegin delete attorney’s feeend delete
20begin insert attorneys’ feesend insert.begin delete The amount withheld pursuant to subdivision (b)
21is not a violation of this section and is not wrongfully withheld.end delete

22(d) This section does not supersede any requirement of Article
232 (commencing with Section 8810) relating to the withholding of
24a retention.

25(e) For purposes of this section, a “disputed amount” shall not
26include any of the following:

begin delete

27(1) Any amount in excess of liquidated damages owed by the
28direct contractor.

29(2) Any amount in excess of what the owner is allowed by law
30to withhold from the direct contractor on account of a mechanics
31lien being recorded or a stop payment notice being served for labor,
32services, equipment, or materials allegedly provided to the project.

end delete
begin insert

33(1) With respect to liquidated damages assessed by the owner,
34any amount in excess of the liquidated damages assessment.

end insert
begin insert

35(2) With respect to mechanics liens and stop payment notices,
36any amount in excess of what the owner is permitted by law to
37withhold from the direct contractor on account of the mechanics
38lien or stop payment notice.

end insert

P4    1(3) The amount of any claim for additional compensationbegin delete arising
2out of alleged extra work performedend delete
by the direct contractorbegin delete or an
3alleged breach of contract byend delete
begin insert againstend insert the owner.

4

SEC. 3.  

Section 8802 of the Civil Code is amended to read:

5

8802.  

(a) This section applies to a contract between a public
6utility and a direct contractor for all or part of a work of
7improvement.

8(b) Unless the direct contractor and a subcontractor otherwise
9agree in writing, within 21 days after receipt of a progress payment
10from the public utility the direct contractor shall pay the
11subcontractor the amount allowed the direct contractor on account
12of the work performed by the subcontractor to the extent of the
13subcontractor’s interest in the work. If there is a good faith dispute
14over all or part of the amount due on a progress payment from the
15direct contractor to a subcontractor, the direct contractor may
16withhold an amount not in excess of 150 percent of the disputed
17amount.

18(c) A direct contractor that violates this section is liable to the
19subcontractor for a penalty of 2 percent of the disputed amount
20due per month for every month that payment is not made. In an
21action for collection of the amount wrongfully withheld, the
22prevailing party is entitled to costs andbegin delete aend delete reasonablebegin delete attorney’s feeend delete
23begin insert attorneys’ feesend insert. begin deleteThe amount withheld pursuant to subdivision (b)
24is not a violation of this section and is not wrongfully withheld.end delete

25(d) This section does not limit or impair a contractual,
26administrative, or judicial remedy otherwise available to a
27contractor or subcontractor in a dispute involving late payment or
28nonpayment by the contractor or deficient performance or
29nonperformance by the subcontractor.

30(e) For purposes of this section, a “disputed amount” shall not
31include any of the following:

begin delete

32(1) Any amount in excess of liquidated damages owed by the
33subcontractor.

end delete
begin delete

34(2) Any amount in excess of what the direct contractor is
35allowed by law to withhold from the subcontractor on account of
36a mechanics lien being recorded or a stop payment notice being
37served for labor, services, equipment, or materials allegedly
38provided to the project.

end delete
begin insert

P5    1(1) With respect to liquidated damages assessed by the public
2utility against the direct contractor, any amount in excess of the
3liquidated damages that are owed by the subcontractor.

end insert
begin insert

4(2) With respect to mechanics liens and stop payment notices
5for which the subcontractor is responsible, any amount in excess
6of what the public utility is permitted by law to withhold from the
7direct contractor on account of the mechanics lien or stop payment
8notice.

end insert

9(3) The amount of any claim for additional compensationbegin delete arising
10out of alleged extra work performed by the subcontractor or an
11alleged breach of contract by the direct contractor.end delete
begin insert by the
12subcontractor against the direct contractor.end insert

13

SEC. 4.  

Section 8812 of the Civil Code is amended to read:

14

8812.  

(a) If an owner withholds a retention from a direct
15contractor, the owner shall, within 45 days after completion of the
16work of improvement, pay the retention to the contractor.

17(b) If part of a work of improvement ultimately will become
18the property of a public entity, the owner may condition payment
19of a retention allocable to that part on acceptance of the part by
20the public entity.

21(c) If there is a good faith dispute between the owner and direct
22contractor as to a retention payment due, the owner may withhold
23from final payment an amount not in excess of 150 percent of the
24disputed amount. This withheld amount shall not be considered
25wrongfully withheld.

26(d) For purposes of this section, a “disputed amount” shall not
27include any of the following:

begin delete

28(1) Any amount in excess of liquidated damages owed by the
29direct contractor.

end delete
begin delete

30(2) Any amount in excess of what the owner is allowed by law
31to withhold from the direct contractor on account of a mechanics
32lien being recorded or a stop payment notice being served for labor,
33services, equipment, or materials allegedly provided to the project.

end delete
begin insert

34(1) With respect to liquidated damages assessed by the owner,
35any amount in excess of the liquidated damages assessment.

end insert
begin insert

36(2) With respect to mechanics liens and stop payment notices,
37any amount in excess of what the owner is permitted by law to
38withhold from the direct contractor on account of the mechanics
39lien or stop payment notice.

end insert

P6    1(3) The amount of any claim for additional compensationbegin delete arising
2out of alleged extra work performedend delete
by the direct contractorbegin delete or an
3alleged breach of contract byend delete
begin insert againstend insert the owner.

4

SEC. 5.  

Section 8814 of the Civil Code is amended to read:

5

8814.  

(a) If a direct contractor has withheld a retention from
6one or more subcontractors, the direct contractor shall, within 10
7days after receiving all or part of a retention payment, pay to each
8subcontractor from whom retention has been withheld that
9subcontractor’s share of the payment.

10(b) If a retention received by the direct contractor is specifically
11designated for a particular subcontractor, the direct contractor shall
12pay the retention payment to the designated subcontractor, if
13consistent with the terms of the subcontract.

14(c) If a good faith dispute exists between the direct contractor
15and a subcontractor, the direct contractor may withhold from the
16retention to the subcontractor an amount not in excess of 150
17percent of the estimated value of the disputed amount.begin delete This
18withheld amount shall not be considered wrongfully withheld.end delete

19(d) For purposes of this section, a “disputed amount” shall not
20include any of the following:

begin delete

21(1) Any amount in excess of liquidated damages owed by the
22subcontractor.

end delete
begin delete

23(2) Any amount in excess of what the direct contractor is
24allowed by law to withhold from the subcontractor on account of
25a mechanics lien being recorded or a stop payment notice being
26served for labor, services, equipment, or materials allegedly
27provided to the project.

end delete
begin insert

28(1) With respect to liquidated damages assessed by the owner
29against the direct contractor, any amount in excess of the
30liquidated damages that are owed by the subcontractor.

end insert
begin insert

31(2) With respect to mechanics liens and stop payment notices
32for which the subcontractor is responsible, any amount in excess
33of what the owner is permitted by law to withhold from the direct
34contractor on account of the mechanics lien or stop payment notice.

end insert

35(3) The amount of any claim for additional compensationbegin delete arising
36out of alleged extra work performedend delete
by the subcontractorbegin delete or an
37alleged breach of the subcontract byend delete
begin insert againstend insert the direct contractor.

begin delete38

SEC. 6.  

Section 8818 of the Civil Code is amended to read:

39

8818.  

If an owner or direct contractor does not make a retention
40payment within the time required by this article:

P7    1(a) The owner or direct contractor is liable to the person to which
2payment is owed for a penalty of 2 percent per month on the
3amount wrongfully withheld, in place of any interest otherwise
4due.

5(b) In an action for collection of the amount wrongfully
6withheld, the prevailing party is entitled to costs and reasonable
7attorney’s fees.

8(c) Amounts authorized to be withheld pursuant to this article
9are not a payment required to be made and are not wrongfully
10withheld.

end delete
11

begin deleteSEC. 7.end delete
12begin insertSEC. 6.end insert  

Section 7107 of the Public Contract Code is amended
13to read:

14

7107.  

(a) This section is applicable with respect to all contracts
15entered into on or after January 1, 1993, relating to the construction
16of any public work of improvement.

17(b) The retention proceeds withheld from any payment by the
18public entity from the original contractor, or by the original
19contractor from any subcontractor, shall be subject to this section.

20(c) Within 60 days after the date of completion of the work of
21improvement, the retention withheld by the public entity shall be
22released. In the event of a dispute between the public entity and
23the original contractor, the public entity may withhold from the
24final payment an amount not to exceed 150 percent of the disputed
25amount. For purposes of this subdivision, “completion” means any
26of the following:

27(1) The occupation, beneficial use, and enjoyment of a work of
28improvement, excluding any operation only for testing, startup, or
29commissioning, by the public agency, or its agent, accompanied
30by cessation of labor on the work of improvement.

31(2) The acceptance by the public agency, or its agent, of the
32work of improvement.

33(3) After the commencement of a work of improvement, a
34cessation of labor on the work of improvement for a continuous
35period of 100 days or more, due to factors beyond the control of
36the contractor.

37(4) After the commencement of a work of improvement, a
38cessation of labor on the work of improvement for a continuous
39period of 30 days or more, if the public agency files for record a
40notice of cessation or a notice of completion.

P8    1(d) Subject to subdivision (e), within seven days from the time
2that all or any portion of the retention proceeds are received by
3the original contractor, the original contractor shall pay each of its
4subcontractors from whom retention has been withheld, each
5subcontractor’s share of the retention received. However, if a
6retention payment received by the original contractor is specifically
7designated for a particular subcontractor, payment of the retention
8shall be made to the designated subcontractor, if the payment is
9consistent with the terms of the subcontract.

10(e) The original contractor may withhold from a subcontractor
11its portion of the retention proceeds if a bona fide dispute exists
12between the subcontractor and the original contractor. The amount
13withheld from the retention payment shall not exceed 150 percent
14of the estimated value of the disputed amount.

15(f) In the event that retention payments are not made within the
16time periods required by this section, the public entity or original
17contractor withholding the unpaid amounts shall be subject to a
18charge of 2 percent per month on the improperly withheld amount,
19in lieu of any interest otherwise due. Additionally, in any action
20for the collection of funds wrongfully withheld, the prevailing
21party shall be entitled tobegin delete attorney’send deletebegin insert attorneys’end insert fees and costs. begin delete22 Amounts authorized to be withheld pursuant to this section are not
23a payment required to be made and are not wrongfully withheld.end delete

24(g) If a state agency retains an amount greater than 125 percent
25of the estimated value of the work yet to be completed pursuant
26to Section 10261, the state agency shall distribute undisputed
27retention proceeds in accordance with subdivision (c). However,
28notwithstanding subdivision (c), if a state agency retains an amount
29equal to or less than 125 percent of the estimated value of the work
30yet to be completed, the state agency shall have 90 days in which
31to release undisputed retentions.

32(h) Any attempted waiver of the provisions of this section shall
33be void as against the public policy of this state.

34(i) For purposes of this section, a “disputed amount”begin insert and “bona
35fide dispute”end insert
shall not include any of the following:

begin delete

36(1) Any amount in excess of liquidated damages owed by the
37original contractor.

end delete
begin delete

38(2) Any amount in excess of what the public entity is allowed
39by law to withhold from the original contractor on account of a
P9    1stop payment notice being served for labor, services, equipment,
2or materials allegedly provided to the project.

end delete
begin insert

3(1) With respect to liquidated damages assessed by the public
4entity, any amount in excess of the liquidated damages assessment.

end insert
begin insert

5(2) With respect to mechanics liens and stop payment notices
6for which the subcontractor is responsible, any amount in excess
7of what the owner is permitted by law to withhold from the prime
8contractor on account of the mechanics lien or stop payment notice.

end insert

9(3) The amount of any claim for additional compensationbegin delete arising
10out of alleged extra work performedend delete
by the original contractor or
11begin delete an alleged breach of contract by the public entity.end deletebegin insert subcontractor.end insert

12

begin deleteSEC. 8.end delete
13begin insertSEC. 7.end insert  

Section 10262.5 of the Public Contract Code is
14amended to read:

15

10262.5.  

(a) (1) Notwithstanding any other law, a prime
16contractor or subcontractor shall pay to any subcontractor, not later
17than seven days after receipt of each progress payment, the
18respective amounts allowed the contractor on account of the work
19performed by the subcontractors, to the extent of each
20subcontractor’s interest therein. In the event that there is a good
21faith dispute over all or any portion of the amount due on a progress
22payment from the prime contractor or subcontractor to a
23subcontractor, then the prime contractor or subcontractor may
24withhold no more than 150 percent of the disputed amount.

25(2) Any contractor who violates this section shall pay to the
26subcontractor a penalty of 2 percent of the amount due per month
27for every month that payment is not made. In any action for the
28collection of funds wrongfully withheld, the prevailing party shall
29be entitled to his or herbegin delete attorney’send deletebegin insert attorneys’end insert fees and costs. begin delete The
30amount withheld pursuant to paragraph (1) is not a violation of
31this section and is not wrongfully withheld.end delete

32(b) This section shall not be construed to limit or impair any
33contractual, administrative, or judicial remedies otherwise available
34to a contractor or a subcontractor in the event of a dispute involving
35late payment or nonpayment by a contractor or deficient
36subcontract performance or nonperformance by a subcontractor.

37(c) On or before September 1 of each year, the head of each
38state agency shall submit to the Legislature a report on the number
39and dollar volume of written complaints received from
40subcontractors and prime contractors on contracts in excess of
P10   1three hundred thousand dollars ($300,000), relating to violations
2of this section.

3(d) For purposes of this section, a “disputed amount” shall not
4include any of the following:

begin delete

5(1) Any amount in excess of liquidated damages owed by the
6subcontractor.

end delete
begin delete

7(2) Any amount in excess of what the prime contractor or
8subcontractor is allowed by law to withhold from the subcontractor
9on account of a stop payment notice being served for labor,
10services, equipment, or materials allegedly provided to the project.

end delete
begin insert

11(1) With respect to liquidated damages assessed by the public
12entity against the prime contractor, any amount in excess of the
13liquidated damages that are owed by the subcontractor.

end insert
begin insert

14(2) With respect to stop payment notices for which the
15subcontractor is responsible, any amount in excess of what the
16public entity is permitted by law to withhold from the prime
17contractor on account of the stop payment notice.

end insert

18(3) The amount of any claim for additional compensationbegin delete arising
19out of alleged extra work performed by the subcontractor or an
20alleged breach of the subcontract by the prime contractor or
21subcontractor.end delete
begin insert by the subcontractor against the prime contractor.end insert



O

    98