BILL ANALYSIS                                                                                                                                                                                                    �



                                                                  AB 536
                                                                  Page  1

          Date of Hearing:   April 16, 2013

              ASSEMBLY COMMITTEE ON BUSINESS, PROFESSIONS AND CONSUMER  
                                     PROTECTION
                              Richard S. Gordon, Chair
                     AB 536 (Wagner) - As Amended:  April 8, 2013
           
          SUBJECT  :   Contractors: payments. 

           SUMMARY  :   Excludes certain types of claims from the calculation  
          of a 'disputed amount'  for purposes of an existing law that  
          authorizes the withholding of 150% of a disputed amount from  
          certain payments to contractors when good faith disputes arise  
          in public or private works contracts.   Specifically,  this bill  :  
           

          1)Prohibits a prime contractor or subcontractor from withholding  
            the following progress payments and retention proceeds from a  
            subcontractor, in both public and private works: 

             a)   Any amount exceeding the liquidated damages owed by a  
               subcontractor, for liquidated damages an owner or public  
               utility has assessed against the prime contractor; 

             b)   Any amount exceeding what the owner or public utility is  
               permitted by law to withhold from the prime contractor for  
               a mechanics lien or stop payment notice; and, 

             c)   A subcontractor's claim for additional compensation  
               against the prime contractor. 

          2)Prohibits, in a private work of improvement, the owner from  
            withholding the following progress payments or retention  
            proceeds from a direct contractor: 

             a)   Any amount exceeding the liquidated damages assessed  
               against the direct contractor; 

             b)   Any amount exceeding what the owner is permitted by law  
               to withhold from the direct contractor for a mechanics lien  
               or stop payment notice; and, 

             c)   A direct contractor's claim for additional compensation  
               against the owner. 









                                                                  AB 536
                                                                  Page  2

          3)Prohibits, in a public works project, a public entity from  
            withholding the following progress payments and retention  
            proceeds from a prime contractor: 

             a)   Any amount exceeding the liquidated damages assessed by  
               the public entity; 

             b)   Any amount exceeding what a public entity is permitted  
               by law to withhold from the prime contractor for a  
               mechanics lien or stop payment notice; and, 

             c)   An original subcontractor's or subcontractor's claim for  
               additional compensation against the public entity. 

           EXISTING LAW : 

          1)Contains various provisions relating to contracts for the  
            performance of private and public works of improvement,  
            including provisions for the withholding and disbursement of  
            retention proceeds, and provides that, with respect to those  
            contracts for works of improvement, the retention proceeds  
            withheld from any payment may not exceed 150% of the disputed  
            amount.  (Business and Professions Code [BPC] Section 7108.5,  
            Civil Code Sections 3260 and 3260.1, and Public Contract Code  
            [PCC] Sections 7107 and10262.5)

          2)Requires a prime contractor or subcontractor to pay a  
            subcontractor within seven days after receiving a progress  
            payment, unless otherwise agreed to in writing.  Provides that  
            in the event of a good faith dispute over the amount due on a  
            progress payment, that the prime contractor or subcontractor  
            may withhold no more than 150% of the disputed amount.   
            Requires the contractor who violates the appropriate  
            withholding provisions to pay a penalty to the subcontractor  
            equal to 2% of the amount due each month until the  
            subcontractor is fully paid, and allows for the prevailing  
            party to be entitled to attorney's fees and costs. (BPC  
            7108.5)

          3)Requires, for a public works contract, a public entity to  
            release the retention withheld within 60 days after the date  
            of completion.  Requires a prime contractor to pay  
            subcontractors within seven days after receiving retention  
            proceeds.  (PCC 7107) 









                                                                  AB 536
                                                                  Page  3

          4)Allows for the Contractors' State License Board (CSLB) to take  
            disciplinary action against a licensed contractor for  
            deliberating failing to pay for materials and services  
            rendered and for falsely denying liability. (BPC 7120)

          5)Provides that mechanics, persons furnishing materials,  
            artisans, and laborers of every class shall have a lien upon  
            the property upon which they bestowed labor or furnished  
            material for the value of such labor done and material  
            furnished.  Requires the Legislature to provide, by law, for  
            the speedy and efficient enforcement of such liens.  
            (California Constitution, Article 14, Section 3)

          6)Requires a contractor that fails to timely pay wages to  
            laborers employed by the contractor to provide notice of the  
            non-payment to the laborer, to the laborer's bargaining  
            representative, and to the construction lender on the project,  
            or face discipline. (Civil Code Section 3097)

           FISCAL EFFECT  :   None.  This bill is keyed non-fiscal by the  
          Legislative Counsel.  

           COMMENTS  :   

           1)Purpose of this bill  .  This bill excludes certain types of  
            claims from the calculation of a "disputed amount" for  
            purposes of an existing law that authorizes the withholding of  
            150% of a disputed amount from the progress payments due to a  
            contractor or subcontractor.  The excluded amounts proposed  
            under this bill are those in excess of liquidated damages  
            claims, those in excess of the withholding permitted for  
            mechanics lien or stop payment notices, and claims for  
            additional compensation.  While the sponsor argues that this  
            bill partially addresses the abusive contracting practice of  
            intentionally disputing payments to withhold and delay  
            payments to contractors and subcontractors, opponents contend  
            that weakening of retention and withholding provisions limit  
            the ability of public entities to drive the performance of  
            contractors. 

            This bill is sponsored by the Engineering Contractors'  
            Association, California Fence Contractors' Association,  
            California Chapter of the American Fence Association, Marin  
            Builders Association, and the Flasher Barricade Association.    
             








                                                                  AB 536
                                                                  Page  4


           2)Author's statement  .  According to the author, "The Prompt Pay  
            statutes are turning into a mess of loopholes that prevent  
            contractors from being paid what they are legitimately owed.   
            They provide no relief to contractors against a sophisticated  
            owner.  Worse, they provide those owners with excuses for  
            withholding more money due to a loophole within the existing  
            statute.  The intent of this measure states what cannot be  
            included in a disputed amount."

          3)Disputed amounts  .  Existing law requires that, in the event of  
            a good faith dispute over all or any portion of an amount due  
            on a contract progress payment or retention proceeds, the one  
            paying for construction services (a property owner, public  
            entity, or prime contractor) withhold no more than 150% of the  
            disputed amount from the one rendering services (a prime  
            contractor or subcontractor, labors, and material suppliers).   
            There is nothing in statute that defines a "disputed amount,"  
            although the dispute must be a bona fide dispute.    

           4)Bill responds to lawsuit regarding meaning of "disputed  
            amount"  .  The sponsors contend that the ambiguity of a  
            "disputed amount" has resulted in legal action over withheld  
            amounts.  For example, in the 2009 case of Martin Brothers  
            Construction, Inc. v. Thompson Pacific Construction, 2009 Cal  
            App. 3d,  a subcontractor, Martin Brothers, filed claims  
            directly with the general contractor, Thompson Pacific  
            Construction, for extra work and change orders valued at  
            roughly $400,000.  In December 2004, Martin Brothers filed an  
            initial complaint in the case, seeking over $900,000 in  
            damages, interests, penalties, and attorney fees.  Thompson  
            Pacific and Martin Brothers settled out of court for over  
            $600,000.  

            The Court sided with Thompson Pacific, reading the statute to  
            be clear on its face and inferring no restriction on the kinds  
            of disputes covered by the statute.  The Court affirmed that  
            it was legally entitled to withhold payment from Martin  
            Brothers for a good faith dispute pursuant to existing law.   
            The relevant holding found that withholding applies to "any  
            good faith dispute" - including change orders and claims for  
            additional or extra work. 

            In response to that finding, this bill would explicitly  
            exclude from the disputed amount those amounts in excess of  








                                                                  AB 536
                                                                  Page  5

            liquidated damages claims, amounts in excess of withholding  
            permitted for mechanics liens and stop payment notices, and  
            claims for additional compensation.

           5)Questions for the Committee  .  Existing law provides for  
            several ways for an unpaid worker to demand payment: an unpaid  
            worker can file a mechanics lien on a private property, file a  
            stop notice to require a public entity to withhold payment  
            from a prime contractor who has not paid subcontractors, file  
            a claim against a contractor's bond, file a complaint with the  
            CSLB, or sue for compensation.  The Committee may wish to  
            consider whether existing law provides sufficient payment  
            remedies for an individual who has rendered labor or services  
            in connection with a construction project but has not yet been  
            paid.

            In addition, this bill would prohibit a homeowner, public  
            entity, or prime contractor from withholding any claims for  
            "additional compensation" from a contractor or subcontractor,  
            even if there is a legitimate disagreement over the amount  
            due.  Because the bill does not specify what "additional  
            compensation" might entail, it is not clear if the effect of  
            this bill would be to exclude claims in situations where a  
            general contractor contends that a subcontractor never  
            performed or incorrectly performed certain work, whether or  
            not the subcontractor believed he or she had a bona fide claim  
            for payment.  The Committee may wish to consider whether or  
            not this bill would inadvertently restrict withholding over  
            legitimate disputes. 
            
            The Committee may also wish to enquire of the author for  
            specific examples of how the current operation of the  
            retention statute is prone to abuse, and how the changes  
            wrought by this bill would minimize that abuse without  
            impinging on amounts in a bona fide dispute.    

           6)Arguments in support  .  According to the sponsors, the  
            Engineering Contractors' Association, California Fence  
            Contractors' Association, California Chapter off the American  
            Fence Association, Marin Builders Association, and the Flasher  
            Barricade Association, "[The Prompt Pay statutes] provide  
            owners with excuses for withholding more money [from a  
            contractor].  Here's why: 'disputed amount' is not defined.   
            As a result, virtually every construction attorney is running  
            into these kinds of things: 








                                                                  AB 536
                                                                  Page  6


            "A)  The owner orders time and material extra work.  Daily  
            tickets are signed by the owner's job site representative,  
            confirming that the equipment and labor actually performed the  
            extra work.   When the extra work is completed, the contractor  
            submits an invoice for $10,000 for the extra work?  The owner  
            decides the total is too much, so he declares this to be a  
            disputed amount.  Not only does the owner not pay for the  
            extra work, but because it is a 'disputed amount,' the owner  
            withholds what the law provides, which is 150% of that amount,  
            or $15,000. 

            "B)  The job is delayed.  The causes of the delay are  
            disputed.  The owner assesses liquated damages of $10,000.   
            The contractor contests this assessment.  The owner, in-turn,  
            declares this to be a 'disputed amount' and withholds [150% of  
            that amount, or $15,000].

            "C)  A cost-plus job is performed.  Under the agreement, the  
            owner must pay all of the costs of the work.  A dispute  
            develops near the end of the job.  In response, the owner  
            stops paying and the contractor pulls off the job.  The owner  
            hires another contractor to finish the work at a cost of  
            $10,000? to justify withholding [150% of that amount, or]  
            $15,000 from what is still owed to the original contractor for  
            costs of the work performed by the original contractor."

           7)Arguments in opposition  .  According to the Construction  
            Employers' Association, "AB 536 would preclude general  
            contractors from withholding funds from subcontractors who  
            fail to pay their suppliers, fail to pay their insurance  
            premiums, fail to pay civil judgments, fail to rectify  
            defective work, etc.  By specifically defining what  
            constitutes a 'disputed amount,' AB 536 would preclude  
            contractors from withholding funds for any number of  
            contractual violations that don't fall within the definition  
            of 'disputed amount.'"

            According to the California Special Districts Association,  
            "Current law provides for the distribution of retained  
            proceeds on a public work of improvement to an original  
            contractor within 60 days, unless there is a dispute over  
            payment, in which case the public agency is allowed to  
            withhold 150% of the disputed amount until the dispute is  
            resolved.  This provision helps to ensure prompt and  








                                                                  AB 536
                                                                  Page  7

            satisfactory completion of public works projects.  Allowing a  
            public agency to withhold funds in the case of a dispute  
            provide [the agency] with a tool to correct defective or  
            incomplete work.  Moreover, it ensures that agencies have  
            sufficient funds to honor stop payment notices filed by  
            subcontractors and suppliers.  Ample remedies already exist  
            for contractors against owners who over-withhold, including  
            monthly interest on the improperly withheld amounts and  
            attorney's fees and costs if the withholding is not in good  
            faith? 

            "Additionally, not allowing the withholding of any amount in  
            excess of liquidated damages ignores other potential damages  
            to which the original contractor might be responsible, such as  
            attorney's fees or other liabilities.  Not to mention, it  
            would limit a public agency's ability to withhold actual  
            damages that are not included in the liquidated damages.  All  
            of these concerns raise the financial risk associated with  
            public works construction, ultimately leading to increased  
            utility bills, higher taxes, or fewer job-creating  
            infrastructure projects." 

           8)Previous Legislation  .  AB 2021 (Wagner) of 2012, was a similar  
            bill that would have revised the amount that an owner can  
            withhold from a contractor, and a contractor from a  
            subcontractor, for disputed private works of improvement.  The  
            difference is that AB 2021 limited the total amount of  
            withholding based on a withholding formula, whereas this bill  
            (AB 536) would exclude certain types of payments from the  
            withholding calculation.  AB 2021 was held on the Senate  
            Floor. 
             
             AB 2549 (Pacheco) of 2004, would have revised the law with  
            respect to retention proceeds for works of improvement.  AB  
            2549 would have increased the amount that may be withheld from  
            progress payments or final payments, depending on the  
            circumstances, to a sum of various amounts and percentages, as  
            specified.  The Governor vetoed AB 2549 with the following  
            message: 

               "Existing law, including lien protections and other  
               prompt pay requirements, afford most contractors with  
               sufficient protection to ensure payment on disputed  
               payments.   Additionally, I believe this bill will  
               only further complicate the various disparate statutes  








                                                                  AB 536
                                                                  Page  8

               regarding disputed payments between contractors and  
               owners.  This area of law that is very important to  
               both the consumer and contractor has been amended  
               piecemeal for far too long."

           9)Double-referred  .  This bill is double-referred, and if passed  
            by this committee will be referred to Assembly Judiciary  
            Committee. 

           REGISTERED SUPPORT / OPPOSITION  :   

           Support 
           
          Engineering Contractors' Association (sponsor) 
          California Fence Contractors' Association (sponsor) 
          California Chapter off the American Fence Association (sponsor)
          Marin Builders Association (sponsor) 
          Flasher Barricade Association (sponsor) 
          California Professional Association of Specialty Contractors
          Southern California Contractors Association

           Opposition 
           
          California Special Districts Association 
          Construction Employers' Association 
           
          Analysis Prepared by  :    Joanna Gin / B.,P. & C.P. / (916)  
          319-3301