BILL ANALYSIS Ó SENATE TRANSPORTATION & HOUSING COMMITTEE BILL NO: ab 797 SENATOR MARK DESAULNIER, CHAIRMAN AUTHOR: gordon VERSION: 4/15/13 Analysis by: Eric Thronson FISCAL: YES Hearing date: June 11, 2013 SUBJECT: Alternative project delivery methods DESCRIPTION: This bill authorizes the Santa Clara County Valley Transportation Authority and the San Mateo Transit District to utilize the construction manager/general contractor project delivery method for transit projects within their respective jurisdictions. ANALYSIS: Traditionally, state and local entities develop and construct transportation projects with a process known as the design-bid-build delivery method. This method requires the public agency to fully design a project and then ask general contractors to bid on the construction contract based on the agency's design. Design-bid-build procurement results in project risks being largely borne by the agency that designs the project, because the agency bears the financial burden if the plans are inadequate or there are unanticipated construction issues. In 2012, the Legislature passed and the governor signed SB 1549 (Vargas), Chapter 767, which authorized the San Diego Association of Governments (SANDAG) to utilize other alternative project delivery methods for transit projects within its jurisdiction, including the construction manager/general contractor (CM/GC) method. Unlike traditional design-bid-build procurement, the CM/GC project delivery method allows an agency to engage a construction manager during the design process to provide assistance to the design team, which ultimately leads to a more constructible project. When design is nearly complete, the agency and the construction manager negotiate a guaranteed maximum price for the construction of the project based on the defined scope and schedule. If this price is acceptable to both AB 797 (GORDON) Page 2 parties, they execute a contract for construction services, and the construction manager becomes the general contractor. Studies suggest the CM/GC method often leads to less costly or more expediently delivered projects because of the construction manager's involvement in the design process. Before electing to use the CM/GC method, SB 1549 requires that SANDAG make a written finding declaring that the CM/GC project delivery method will either reduce costs, expedite completion, or provide features not achievable through the design-bid-build method. In addition, to determine the benefits of CM/GC, SB 1549 requires SANDAG staff to present a report to the agency's governing body on its experience upon completion of a CM/GC project and to post the report on its internet web site. Existing law creates the Santa Clara County Valley Transportation Authority (VTA) as the congestion management agency in Santa Clara County and vests it with the responsibility for countywide transportation planning, congestion management, and design and construction of specific highway, pedestrian, and bicycle improvement projects. In addition, VTA operates bus, light rail, and paratransit services throughout Santa Clara County. Existing law also creates the San Mateo Transit District (SamTrans), which is responsible for providing public transit and transportation programs in San Mateo County. This bill authorizes VTA and SamTrans to utilize the CM/GC project delivery method for transit projects within their respective jurisdictions, similar to SANDAG's authority. COMMENTS: 1.Purpose . According to the author, VTA and SamTrans seek the additional contract flexibility of the CM/GC project delivery method so that they can deliver ambitious new transit projects in a manner that makes the most efficient use of limited transit funding. The CM/GC method maintains full public agency control over the design of the project, but by allowing for contractor input during the design phase, it allows for the development of reliable cost estimates of different design alternatives. The author contends that this can reduce design costs and accelerate construction timelines, leading to overall cost savings. 2.Why pursue alternative project delivery approaches ? For AB 797 (GORDON) Page 3 decades, state and local agencies have relied on the design-bid-build procurement method for transportation projects. Design-bid-build reduces the risk for the construction contractor because the owner has a completed design, procured right-of-way, and achieved environmental clearance before letting the contract. Agencies using this traditional method generally receive the lowest initial cost construction contracts for a given project, because contractors are competitively bidding on a relatively risk-free project. Drawbacks to design-bid-build can include longer completion times, constructability challenges unforeseen by the designers, and increasing costs over time due to change orders and claims. The CM/GC process is meant to provide continuity and collaboration between the design and construction phases of the project. Construction managers have an incentive to provide input during the design phase that will enhance constructability of the project later because they know that they will have the opportunity to become the general contractor for the project. Furthermore, CM/GC promises to save project delivery time, provide earlier cost certainty, transfer risks from the public agency to the contractor, and ensure project constructability. Finally, it allows each agency to design the project to complement the general contractor's strengths and capabilities, thereby providing maximum competitiveness in a low-bid procurement. 3.Opposition . While not opposing the authorization of alternative construction contracting methods, opponents object to this bill because it potentially exempts some projects from reimbursing the Department of Industrial Relations (DIR) for its costs of performing prevailing wage monitoring and enforcement. As an alternative to reimbursing DIR for prevailing wage work, this bill permits the agencies to adopt a collective bargaining agreement that includes a mechanism for resolving disputes about the payment of wages. Opponents contend that this alternative is not a suitable replacement for the enforcement of the entirety of the Labor Code by DIR. The language in this bill related to DIR's enforcement of prevailing wage law mirrors the language in SB 1549, the bill granting SANDAG authority to employ the CM/GC procurement method. On April 17, 2012, this committee unanimously passed SB 1549. AB 797 (GORDON) Page 4 Assembly Votes: Floor: 53-22 Appr: 12-5 Trans: 12-4 POSITIONS: (Communicated to the committee before noon on Wednesday, June 5, 2013.) SUPPORT: Santa Clara Valley Transportation Authority (sponsor) Peninsula Corridor Joint Powers Board (Caltrain) San Mateo County Transit District San Mateo County Transportation Authority OPPOSED: Air Conditioning Trade Association Plumbing-Heating-Cooling Contractors Association of California Western Electrical Contractors Association