BILL ANALYSIS Ó ----------------------------------------------------------------- |SENATE RULES COMMITTEE | AB 797| |Office of Senate Floor Analyses | | |1020 N Street, Suite 524 | | |(916) 651-1520 Fax: (916) | | |327-4478 | | ----------------------------------------------------------------- THIRD READING Bill No: AB 797 Author: Gordon (D) Amended: 4/15/13 in Assembly Vote: 21 SENATE TRANSPORTATION & HOUSING COMMITTEE : 11-0, 6/11/13 AYES: DeSaulnier, Gaines, Beall, Cannella, Galgiani, Hueso, Lara, Liu, Pavley, Roth, Wyland SENATE APPROPRIATIONS COMMITTEE : 7-0, 6/24/13 AYES: De León, Walters, Gaines, Hill, Lara, Padilla, Steinberg ASSEMBLY FLOOR : 53-22, 5/13/13 - See last page for vote SUBJECT : Alternative project delivery methods SOURCE : Santa Clara Valley Transportation Authority DIGEST : This bill authorizes the Santa Clara County Valley Transportation Authority (VTA) and the San Mateo Transit District (SamTrans) to utilize the construction manager/general contractor (CM/GC) project delivery method for transit projects within their respective jurisdictions. ANALYSIS : Traditionally, state and local entities develop and construct transportation projects with a process known as the design-bid-build delivery method. This method requires the public agency to fully design a project and then ask general contractors to bid on the construction contract based on the agency's design. Design-bid-build procurement results in CONTINUED AB 797 Page 2 project risks being largely borne by the agency that designs the project, because the agency bears the financial burden if the plans are inadequate or there are unanticipated construction issues. The Legislature passed and the Governor signed SB 1549 (Vargas, Chapter 767, Statutes of 2012) which authorized the San Diego Association of Governments (SANDAG) to utilize other alternative project delivery methods for transit projects within its jurisdiction, including the CM/GC method. Unlike traditional design-bid-build procurement, the CM/GC project delivery method allows an agency to engage a construction manager during the design process to provide assistance to the design team, which ultimately leads to a more constructible project. When design is nearly complete, the agency and the construction manager negotiate a guaranteed maximum price for the construction of the project based on the defined scope and schedule. If this price is acceptable to both parties, they execute a contract for construction services, and the construction manager becomes the general contractor. Studies suggest the CM/GC method often leads to less costly or more expediently delivered projects because of the construction manager's involvement in the design process. Before electing to use the CM/GC method, SB 1549 required that SANDAG make a written finding declaring that the CM/GC project delivery method will either reduce costs, expedite completion, or provide features not achievable through the design-bid-build method. In addition, to determine the benefits of CM/GC, SB 1549 required SANDAG staff to present a report to the agency's governing body on its experience upon completion of a CM/GC project and to post the report on its Internet Web site. Existing law creates the VTA as the congestion management agency in Santa Clara County and vests it with the responsibility for countywide transportation planning, congestion management, and design and construction of specific highway, pedestrian, and bicycle improvement projects. In addition, VTA operates bus, light rail, and paratransit services throughout Santa Clara County. Existing law also creates the SamTrans, which is responsible for providing public transit and transportation programs in San Mateo County. This bill: CONTINUED AB 797 Page 3 1. Defines CM/GC and CM by reference to existing law to mean, the following: A. CM/GC to mean a project delivery method using a best value procurement process in which a construction manager is procured to provide preconstruction services during the design phase of the project and construction services during the construction phase of the project. B. CM to mean a partnership, corporation, or other legal entity that is able to provide appropriately licensed contracting and engineering services as needed pursuant to a CM/GC contract. 2. Specifically authorizes VTA to use the CM/GC project delivery method for public transit projects within its jurisdictions, under the condition that after evaluating the traditional design-bid-build process as well as the CM/GC process in a public meeting, VTA makes a written finding that use of the CM/GC process on a particular project will result in one or more of the following objectives: A. Reduce project costs; B. Expedite the project's completion; or, C. Provide features not achievable through a design-bid-build process. 3. Requires VTA to comply with prevailing wages laws on projects for which CM/GC is used or, alternatively, to enter into a collective bargaining contract that will bind all contractors on a project and that includes provisions governing the resolution of disputes about wage payments. 4. Requires, if VTA enters into a CM/GC contract that includes preconstruction services by the construction manager, VTA to pay a fee for preconstruction services for a mutually agreed to price. VTA may not request or obtain from the construction manager a fixed price or a guaranteed maximum price for a construction contract nor enter into a construction contract with the construction manager until after it has entered into a preconstruction services CONTINUED AB 797 Page 4 contract. The preconstruction services contract is to provide for subsequent negotiation for the construction phase of the project. 5. Authorizes VTA to enter into a contract for construction services after a project has been sufficiently developed and either a fixed price or guaranteed maximum price has been successfully negotiated. Should VTA not be able to come to terms for the construction services phases, then it may award the contract using any other procurement method authorized by law. 6. Requires the construction manager to perform at least 30% of the work covered by the construction services contract. 7. Requires any work not performed by the construction manager to be bid to subcontractors pursuant to the Subletting and Subcontracting Fair Practices Act. 8. Requires VTA to prepare a progress report to its governing body, with specified elements, and to make the report available on its Internet Web site. 9. Provides that the provisions of this bill are severable and that contracts awarded pursuant to the provisions of this bill are valid until the project is completed. 10.Duplicates all of these provisions to apply to San Mateo County Transit District as well. Background For decades, state and local agencies have relied on the design-bid-build procurement method for transportation projects. Design-bid-build reduces the risk for the construction contractor because the owner has a completed design, procured right-of-way, and achieved environmental clearance before letting the contract. Agencies using this traditional method generally receive the lowest initial cost construction contracts for a given project, because contractors are competitively bidding on a relatively risk-free project. Drawbacks to design-bid-build can include longer completion times, constructability challenges unforeseen by the designers, and increasing costs over time due to change orders and claims. CONTINUED AB 797 Page 5 The CM/GC process is meant to provide continuity and collaboration between the design and construction phases of the project. CMs have an incentive to provide input during the design phase that will enhance constructability of the project later because they know that they will have the opportunity to become the general contractor for the project. Furthermore, CM/GC promises to save project delivery time, provide earlier cost certainty, transfer risks from the public agency to the contractor, and ensure project constructability. Finally, it allows each agency to design the project to complement the general contractor's strengths and capabilities, thereby providing maximum competitiveness in a low-bid procurement. FISCAL EFFECT : Appropriation: No Fiscal Com.: Yes Local: No According to the Senate Appropriations Committee: Unknown transit project costs or savings (State Transit Assistance funds, local funds, federal funds). Before using the CM/GC method, the transit district must make a finding that the alternative method would provide a benefit that may be deemed to have a greater value than project cost alone, such as expedited project delivery or other features not achievable through design-bid-build. The overall value of a project may be measured by criteria other than cost. This could result in a higher overall project costs than design-bid build, but use of CM/GC must be justified by providing other benefits, as specified. Likely minor costs to DIR to perform prevailing wage monitoring and enforcement, reimbursed by VTA and SamTrans (State Public Works Enforcement Fund). SUPPORT : (Verified 6/26/13) Santa Clara Valley Transportation Authority (source) California Transit Association Peninsula Corridor Joint Powers Board San Mateo County Transit District San Mateo County Transportation Authority CONTINUED AB 797 Page 6 OPPOSITION : (Verified 6/26/13) Air Conditioning Trade Association Plumbing-Heating-Cooling Contractors Association of California Western Electrical Contractors Association ARGUMENTS IN SUPPORT : According to the author, "VTA and SamTrans seek the additional contract flexibility of the CM/GC project delivery method so that they can deliver ambitious new transit projects in a manner that makes the most efficient use of limited transit funding. The CM/GC method maintains full public agency control over the design of the project, but by allowing for contractor input during the design phase, it allows for the development of reliable cost estimates of different design alternatives." The author contends that "this can reduce design costs and accelerate construction timelines, leading to overall cost savings." ARGUMENTS IN OPPOSITION : While not opposing the authorization of alternative construction contracting methods, opponents object to this bill because it potentially exempts some projects from reimbursing the Department of Industrial Relations (DIR) for its costs of performing prevailing wage monitoring and enforcement. As an alternative to reimbursing DIR for prevailing wage work, this bill permits the agencies to adopt a collective bargaining agreement that includes a mechanism for resolving disputes about the payment of wages. Opponents contend that this alternative is not a suitable replacement for the enforcement of the entirety of the Labor Code by DIR. ASSEMBLY FLOOR : 53-22, 5/13/13 AYES: Achadjian, Alejo, Atkins, Bloom, Blumenfield, Bocanegra, Bonilla, Bonta, Bradford, Brown, Buchanan, Ian Calderon, Campos, Chau, Chesbro, Cooley, Daly, Dickinson, Eggman, Fong, Fox, Frazier, Garcia, Gatto, Gomez, Gordon, Gray, Hall, Roger Hernández, Jones-Sawyer, Levine, Medina, Mitchell, Mullin, Muratsuchi, Nazarian, Pan, Perea, V. Manuel Pérez, Quirk, Quirk-Silva, Rendon, Salas, Skinner, Stone, Ting, Torres, Weber, Wieckowski, Wilk, Williams, Yamada, John A. Pérez NOES: Bigelow, Chávez, Conway, Dahle, Donnelly, Beth Gaines, Gorell, Grove, Hagman, Harkey, Jones, Linder, Logue, Maienschein, Mansoor, Melendez, Morrell, Nestande, Olsen, Patterson, Wagner, Waldron CONTINUED AB 797 Page 7 NO VOTE RECORDED: Allen, Ammiano, Holden, Lowenthal, Vacancy JJA:d 6/26/13 Senate Floor Analyses SUPPORT/OPPOSITION: SEE ABOVE **** END **** CONTINUED