BILL ANALYSIS                                                                                                                                                                                                    Ó



                                                                  AB 1228
                                                                  Page  1

          Date of Hearing:   April 29, 2013

                    ASSEMBLY COMMITTEE ON UTILITIES AND COMMERCE
                               Steven Bradford, Chair
                  AB 1228 (V.M. Perez) - As Amended:  April 24, 2013
          
          SUBJECT  :   Electricity: eligible fuel cell customer-generators

           SUMMARY  :   This bill would increase the capacity of a fuel cell  
          electrical generating facility, operating under a Net Energy  
          Metering (NEM) tariff, from 1 megawatt to not more than 3  
          megawatts and makes other changes. Specifically,  this bill  :  

          a)Increases the maximum allowable capacity of a fuel facility  
            eligible for the NEM tariff from 1 megawatt to 3 megawatts.

          b)Provides that eligible fuel cell projects shall not be exempt  
            from reasonable interconnection charges.

          c)Establishes that interconnection charges are to take into  
            account the ratepayer and system benefits of larger baseload  
            fuel cell projects.

          d)Sets a maximum rate at which electricity is fed back to the  
            grid at no more than one megawatt-hour.

           EXISTING LAW  

          1)Limits the maximum capacity of a qualified fuel cell project  
            to no larger than 1 megawatt. (Public Utilities Code 2827.10  
            (a)(3)(A)(i))

          2)Requires every electrical corporation to make available to an  
            eligible fuel cell customer-generator a standard tariff for  
            NEM on a first-come-first-served basis, until the total  
            cumulative rated generating capacity of the eligible fuel cell  
            electrical generating facilities receiving service reaches a  
            level equal to its proportionate share of a statewide limit of  
            500 megawatts cumulative rated generation. The proportionate  
            share shall be calculated based on the ratio of the electrical  
            corporation's peak demand compared to the total statewide peak  
            demand. (Public Utilities Code 2827.10 (b)(1))

          3)Allows the California Public Utilities Commission (PUC) to  
            incrementally raise the statewide limit of 500 megawatts  








                                                                  AB 1228
                                                                  Page  2

            following a review. (Public Utilities Code 2827.10 (b)(1))

          4)Requires that each NEM tariff be identical, with respect to  
            rate structure, all retail rate components, and any monthly  
            charges, to customer's otherwise applicable tariff if the  
            customer were not a fuel cell generator. (Public Utilities  
            Code 2827.10 (d)(1))

          5)Restricts any new or additional demand charge, standby charge,  
            customer charge, minimum monthly charge, interconnection  
            charge, or other charge that would increase an eligible fuel  
            cell customer-generator's costs beyond those of other  
            customers in the rate class to which the eligible fuel cell  
            customer-generator would otherwise be assigned. (Public  
            Utilities Code 2827.10 (d)(1))

          6)Authorizes a fee for interconnection inspection services for  
            fuel cell customer-generators. (Public Utilities Code 2827.10  
            (d)(1))

          7)Establishes that the value of electricity generated by the  
            fuel cell facility be the same price as the electrical  
            corporation would charge for retail sales of electricity,  
            exclusive of surcharges and, to the extent that transmission  
            and distribution services are recovered through demand  
            charges, no standby charges are to be applied. (Public  
            Utilities Code 2827.10 (e)(2)(A))

          8)Establishes that any excess kilowatt-hour generation that  
            might occur during the 12-month NEM period are to be retained  
            by the electrical corporation and no compensation is to be  
            paid to the customer. (Public Utilities Code 2827.10  
            (e)(2)(B)(3))

          9)Sunsets the fuel cell NEM on January 1, 2015. (Public  
            Utilities Code 2827.10 (f))

          10)Requires the PUC, in consultation with the California Energy  
            Commission (CEC) and the California Independent System  
            Operator (CAISO), to report on or before January 1, 2010, on  
            the impacts of distributed energy generation on the state's  
            distribution and transmission grid. The study is to include  
            the following:

               a)     Reliability and transmission issues related to  








                                                                  AB 1228
                                                                  Page  3

                 connecting distributed energy generation to the local  
                 distribution networks and regional grid.
               b)     Issues related to grid reliability and operation,  
                 including interconnection, and the position of federal  
                 and state regulators toward distributed energy  
                 accessibility.
               c)     The effect on overall grid operation of various  
                 distributed energy generation sources.
               d)     Barriers affecting the connection of distributed  
                 energy to the state's grid.
               e)     Emerging technologies related to distributed energy  
                 generation interconnection.
               f)     Interconnection issues that may arise for CAISO and  
                 local distribution companies.
               g)     The effect on peak demand for electricity.
               h)     The impacts of the California Solar Initiative (CSI)  
                 program, the self-generation incentive program (SGIP),  
                 and the net energy metering pilot program. 

               (Public Utilities Code 321.7)

           FISCAL EFFECT  :   Unknown

           COMMENTS  :   

           1)Author's Statement.  "This measure will amend the code to allow  
            fuel cell generating facilities up to 3 MW to qualify for the  
            NEM program. Increasing the fuel cell electrical generating  
            facility capacity will enhance competition among California's  
            fuel cell developers and will engender high-value,  
            multi-megawatt projects.  

            "These projects will allow corporate campuses, agricultural  
            facilities, colleges and universities and similar facilities  
            with fluctuating load to participate in this program.

            "In so doing, sites with more variable onsite load -like  
            campuses or agricultural facilities that fluctuate  
            seasonally-- will be able to send clean, reliable excess  
            energy back to the electric grid when onsite load is low.  

            "Thus, more facilities and employment centers can make the  
            switch to clean DG.  This is an important step toward growing  
            the market for zero-emission, baseload generation in  
            California."








                                                                  AB 1228
                                                                  Page  4


           2)Two-types of NEM tariffs.  There are currently two different  
            types of NEM tariffs in place: one tariff offers bill credits  
            at the full retail rate for RPS-eligible technologies,  
            including fuel cells that use renewable fuel ("full-retail  
            NEM"). A separate tariff, the subject of this bill, offers a  
            significantly lower bill credit that pays for the  
            generation-only component of the rate, available to fuel cells  
            that use renewable or non-renewable fuel and which meet  
            specified reductions in GHG emissions ("Fuel Cell NEM, FC-  
            NEM"). 

            According to the PUC, "Because renewable fuel cell projects  
            will likely take advantage of the higher bill credit rate  
            under the full-retail NEM program, the PUC assumes that the  
            majority of current fuel cell projects using the FC- NEM  
            tariff will be non-renewable fuel cells."

            Although all renewable resources sized up to 1 MW which offset  
            a customer's load are eligible for full retail NEM, most of  
            the facilities are solar photovoltaic (PV).  

           3)Baseload Generation.  Although fuel cells are not intermittent  
            and provide baseload generation, theses generators are  
            generally not dispatchable and lack ramping capability.   
            Consequently, the fuel cell generator can be run full-time  
            regardless of the load of the facility. If the load drops,  
            such as in the night or on weekends, the surplus electricity  
            goes back to the grid.  The FC-NEM program allows that  
            generation to accumulate to the customer's credit so that the  
            customer can utilize that credit during business hours when  
            the fuel cell is offsetting some or all load but the customer  
            could also be using generation from the grid.

           4)Electrical Corporations Only.  The mandates of this program  
            apply only to the electrical corporations regulated by the  
            PUC. There are no comparable requirements on Publicly Owned  
            Utilities (POU), which may create barriers to growth of the  
            industry and use of the technologies in very significant  
            portions of the state since the POUs serve as much as 23% of  
            the electric load in California. On the other hand, by  
            limiting the FC-NEM to the electrical corporations the  
            potential cost shift to non-participating ratepayers will not  
            effect on POU customers.









                                                                  AB 1228
                                                                  Page  5

           5)It's a Grid Problem  .  The 1 MW capacity cap for fuel is  
            consistent across all NEM programs for all technologies for  
            all customers.  There reasons for the 1 MW cap is related to  
            the reliability of the electric grid.  

            The California Independent System Operator (CAISO) requires  
            that generators exporting to the grid schedule deliveries. NEM  
            customers have no obligation to schedule deliveries because  
            they are located on the customer's side of the meter. If they  
            produce more than they consume on-site, the excess generation  
            is pushed back onto the grid, whether or not it is needed.  
            This is unscheduled excess generation. The excess generation  
            can create grid stability problems leading to poor power  
            quality which could damage equipment or appliances, blackouts,  
            or flickering.


            Larger NEM facilities, such as those envisioned by this bill,  
            could cause grid reliability problems, particularly depending  
            on the daily load profile of the FC-NEM customer. For example,  
            the FC-NEM customer could be 'closed on weekends and holidays"  
            yet still operate their fuel cell during those time periods.  
            This could put substantial amounts of unscheduled electricity  
            onto the grid at a time when demand for electricity is  
            typically low and there are substantial amounts of excess  
            generation from other resources (including renewable  
            supplies).

            Grid integration issues are among those being studied by the  
            PUC in the DG impacts study.

            AB 1228 was amended to add a provision that would limit the  
            net rate at which electricity is fed back to the electric  
            grid. The limit established in this provision is one  
            megawatt-hour. The author's intent is to ensure that  
            regardless of the increase in the FC-NEM cap the fuel cell  
            customer will be limited in the amount of electricity fed back  
            to the grid. This approach effectively increases the amount of  
            electricity that can be fed back to the grid because the  
            current cap of 1megawatt limits the amount fed back to the  
            grid at no more than 1 megawatt less the amount of electricity  
            consumed on-site.

             If this bill is passed out of this committee the author should  
            amend this provision to refer to the limit as one megawatt  








                                                                 AB 1228
                                                                  Page  6

            rather than one megawatt-hour.
           
           6)Interconnection Issues  . Interconnection describes the  
            electrical transfer point between a generating facility and  
            the distribution system. "Rule 21" is the name of the tariff  
            that sets metering and operating standards for self-generation  
            facilities interconnected to the utility distribution system.

            In a two-part proceeding the PUC approved, in September 2012,  
            a settlement to reform the interconnection tariff to craft  
            transparent rules that provide a clear, predictable path to  
            interconnection for distributed generation while maintain the  
            safety and reliability of the electric grid. 

            In December 2012, the PUC initiated Phase 2 in this proceeding  
            to further address issues related to streamlining  
            interconnection rules.

            This bill provides that eligible FC-NEM facilities with a  
            capacity of less than one megawatt would pay reasonable  
            interconnection charges. Interconnection charges are generally  
            inspection charges, which are current law.

            In addition, this bill would require the PUC, when it revises  
            Rule 21, to consider ratepayer and system benefits of larger  
            baseload fuel cell projects. The way this language was drafted  
            implies an assumption that there are no costs to adding larger  
            baseload fuel cell projects.

           7)Ratepayer funded incentives  . The Self Generation Incentive  
            Program (SGIP) also provides incentives to encourage the  
            deployment of clean distributed generation technologies that  
            have been determined to achieve reductions in greenhouse gas  
            emissions. Fuel cells that operate on renewable fuels and fuel  
            cells that operate on non-renewable fuels are eligible to  
            participate in SGIP. The SGIP offers incentives for the first  
            3 MW of fuel cell projects, which can be of any size (e.g. a  
            10MW fuel cell receives financial support for the first 3MW).

            Provided a system meets all requirements, both renewable and  
            non-renewable fuel cell systems could potentially participate  
            in the SGIP and the fuel cell NEM program.

           8)Unknown shift of costs to other ratepayers.  According to the  
            PUC, the FC-NEM customers are granted the same exemptions as  








                                                                  AB 1228
                                                                  Page  7

            full retail NEM customers. This includes an exemption from  
            standby and certain departing load charges, specifically, all  
            of the Cost Responsibility Surcharges - DWR Bond charge, DWR  
            Power charge, Regulatory Asset Charge, and Competition  
            Transition Charge).

            According to the PUC, the cost shift due to FC-NEM or whether  
            or not FC-NEM customers pay their share of public purpose  
            programs is not known at this time. The costs and benefits of  
            the FC-NEM are not part of the NEM study authorized by AB 2514  
            (Bradford)

           9)Related Legislation.
             
            AB 2514 (Bradford, Chapter 609, Statutes of 2012) requires the  
            PUC to study and report on the costs and benefits of NEM by  
            October 2013.

            AB 2075 (Fong, 2011-2012) would have increased the capacity of  
            a fuel cell electrical generating facility to not more than 3  
            megawatts. Failed passage in Senate EU&C Committee

           REGISTERED SUPPORT / OPPOSITION  :   

           Support 
           
          Clean Power Campaign
          Fuel Cell Energy (Sponsor)

           Opposition 
           
          San Diego Gas & Electric Company (SDG&E)
          Southern California Edison (SCE)
           
          Analysis Prepared by  :    Susan Kateley / U. & C. / (916)  
          319-2083