AB 1407, as introduced, Committee on Utilities and Commerce. Public utilities: resource adequacy requirement.
Under existing law, the Public Utilities Commission has regulatory authority over public utilities, including electrical corporations. Existing law requires the commission, in consultation with the Independent System Operator to establish resource adequacy requirements for all load-serving entities to achieve specified objectives.
This bill would make technical, nonsubstantive changes to that provision.
Vote: majority. Appropriation: no. Fiscal committee: no. State-mandated local program: no.
The people of the State of California do enact as follows:
Section 380 of the Public Utilities Code is
2amended to read:
(a) The commission, in consultation with the Independent
4System Operator, shall establish resource adequacy requirements
5for all load-serving entities.
P2 1(b) In establishing resource adequacy requirements, the
2commission shall achieve all of the following objectives:
3(1) Facilitate development of new generating capacity and
4retention of existing generating capacity that is economic and
5needed.
6(2) begin deleteEquitably allocate end deletebegin insertAllocate equitably end insertthe cost of
generating
7capacity and preventbegin insert theend insert shifting of costs between customer classes.
8(3) Minimize enforcement requirements and costs.
9(4) Maximize the ability of community choice aggregators to
10determine the generation resources used to serve their customers.
11(c) Each load-serving entity shall maintain physical generating
12capacity adequate to meet its load requirements, including, but not
13limited to, peak demand and planning and operating reserves. The
14generating capacity shall be deliverable to locations and at times
15as may be necessary to provide reliable electric service.
16(d) Each load-serving entity shall, at a minimum, meet the most
17recent minimum
planning reserve and reliability criteria approved
18by the Board of Trustees of the Western Systems Coordinating
19Council or the Western Electricity Coordinating Council.
20(e) The commission shall implement and enforce the resource
21adequacy requirements established in accordance with this section
22in a nondiscriminatory manner. Each load-serving entity shall be
23subject to the same requirements for resource adequacy and the
24renewables portfolio standard program that are applicable to
25electrical corporations pursuant to this section, or otherwise
26required by law, or by order or decision of the commission. The
27commission shall exercise its enforcement powers to ensure
28compliance by all load-serving entities.
29(f) The commission shall require sufficient information,
30including, but not limited to, anticipated load, actual load, and
31measures undertaken by a load-serving entity to ensure
resource
32adequacy, to be reported to enable the commission to determine
33compliance with the resource adequacy requirements established
34by the commission.
35(g) An electrical corporation’s costs of meeting resource
36adequacy requirements, including, but not limited to, the costs
37associated with system reliability and local area reliability, that
38are determined to be reasonable by the commission, or are
39otherwise recoverable under a procurement plan approved by the
40commission pursuant to Section 454.5, shall be fully recoverable
P3 1from those customers on whose behalf the costs are incurred, as
2determined by the commission, at the time the commitment to
3incur the cost is made, on a fully nonbypassable basis, as
4determined by the commission. The commission shall exclude any
5amounts authorized to be recovered pursuant to Section 366.2
6when authorizing the amount of costs to be recovered from
7customers of a community choice aggregator or from customers
8
that purchase electricity through a direct transaction pursuant to
9this subdivision.
10(h) The commission shall determine and authorize the most
11efficient and equitable means for achieving all of the following:
12(1) Meeting the objectives of this section.
13(2) Ensuring that investment is made in new generating capacity.
14(3) Ensuring that existing generating capacity that is economic
15is retained.
16(4) Ensuring that the cost of generating capacity is allocated
17equitably.
18(5) Ensuring that community choice aggregators can determine
19the generation resources used to serve their customers.
20(i) In making the determination pursuant to subdivision (h), the
21commission may consider a centralized resource adequacy
22mechanism among other options.
23(j) For purposes of this section, “load-serving entity” means an
24electrical corporation, electric service provider, or community
25choice aggregator. “Load-serving entity” does not include any of
26the following:
27(1) A local publicly owned electric utility.
28(2) The State Water Resources Development System commonly
29known as the State Water Project.
30(3) Customer generation located on the customer’s site or
31providing electric service through arrangements authorized by
32Section 218, if the customer generation, or the load it serves, meets
33one of the
following criteria:
34(A) It takes standby service from the electrical corporation on
35a commission-approved rate schedule that provides for adequate
36backup planning and operating reserves for the standby customer
37class.
38(B) It is not physically interconnected to the electric transmission
39or distribution grid, so that, if the customer generation fails, backup
40electricity is not supplied from the electricity grid.
P4 1(C) There is physical assurance that the load served by the
2customer generation will be curtailed concurrently and
3commensurately with an outage of the customer generation.
O
99