BILL ANALYSIS                                                                                                                                                                                                    Ó






                                                       Bill No:  AB  
          1705
          
                 SENATE COMMITTEE ON GOVERNMENTAL ORGANIZATION
                           Senator Lou Correa, Chair
                           2013-2014 Regular Session
                                 Staff Analysis



          AB 1705  Author:  Williams
          As Amended:  March 28, 2014
          Hearing Date:  June 10, 2014
          Consultant:  Paul Donahue


                                     SUBJECT  

                Public contracts: Retention of contract payments

                                   DESCRIPTION
           
          Limits the circumstances under which public agencies may  
          withhold more than 5% of total payment amounts for time and  
          materials on substantially complex public works projects.  
          Specifically, this bill:

          1)Requires a state agency that plans to withhold more than  
            5% of the contract price by making a finding, prior to  
            the bid, that a project is substantially complex, to  
            include in bid documents an explanation of the basis for  
            that finding, and the actual amount above 5% to be  
            retained by the agency during the project. 

          2)Specifies that if a local government agency intends to  
            require a retention amount higher than 5% on a specific  
            project, it must make the findings that the project is  
            substantially complex during a properly noticed and  
            scheduled public hearing prior to the bid. 

          3)Declares that public projects are not substantially  
            complex if they are maintenance projects, or are projects  
            that are regularly, customarily, or routinely performed  
            by the agency or by licensed contractors.

          4)Provides that in a contract between the original  





          AB 1705 (Williams) continued                              
          PageB


            contractor and a subcontractor, and in a contract between  
            a subcontractor and any subcontractor, the percentage of  
            the retention proceeds withheld shall not exceed the  
            percentage specified in the contract between the public  
            agency and the original contractor.

                                   EXISTING LAW
           
          1)Prohibits state and local public agencies from retaining  
            more than 5% of a contract price until final completion  
            of a project, unless the public agency finds that the  
            project is substantially complex pursuant to specified  
            circumstances. 

          2)Authorizes a public entity to withhold more than 5% of  
            the contract price if a project is deemed to be  
            substantially complex under specified circumstances. 

          3)Prohibits retention amounts between contractors and  
            subcontractors from exceeding the retention percentage  
            specified in the contract between the public agency and  
            the original contractor. 

          4)Repeals these provisions governing retention proceeds on  
            January 1, 2016.

                                    BACKGROUND
           
           1)Purpose  : The author states that AB 1705 will clarify what  
            a substantially complex project is as it relates to  
            retention proceeds in public works projects. In the event  
            that a project is deemed substantially complex, AB 1705  
            requires that details explaining the basis of the finding  
            be included in the bid documents.

            In 2011, SB 293 (Padilla) limited the amount of retention  
            proceeds to 5% of the costs of the contract, unless a  
            project was substantially complex. According to the  
            author and the sponsors of AB 1705, soon thereafter, many  
            public entities, particularly school districts, started  
            adopting resolutions setting forth the methodology by  
            which ALL construction future projects will be designated  
            as substantially complex. The author states that this  
            practice is inconsistent with the original intent of SB  
            293 (Padilla), and unfairly exploits what was meant to be  
            a reasonable exemption to the law.





          AB 1705 (Williams) continued                              
          PageC



           2)Retention proceeds  : In California and many other  
            states,<1>  a public entity is entitled to withhold from  
            payment a specified amount so that the public entity can  
            maintain financial control of the project. In 2011,  
            special retention procedures were enacted into law in  
            California, and public entities cannot now retain more  
            than 5% of the costs of a contract, subject to the  
            "substantially complex" exception.<2>

            Before this law passed limiting retention on public works  
            projects to 5%, the usual standard for public entities  
            was 10%, although this was not set by statute. The only  
            identified exception to the 5% retention limit is when a  
            public entity approves a finding that a project is  
            substantially complex during a properly noticed and  
            regularly scheduled public meeting prior to bidding the  
            project. In that case, retention proceeds may exceed 5%.  
            Whether a project is substantially complex for purposes  
            of requiring retention in excess of 5% must be analyzed  
            and approved on a project-by-project basis. The finding  
            and the designated retention amount must be included in  
            the project's bid documents. This law remains in effect  
            until January 1, 2016 and cannot be waived by agreement. 

            It should be noted that the 5% limit on retention  
            proceeds in Public Contract Code § 7201 does not limit a  
            public entity's ability to withhold funds for other  
            purposes, including withholding 150% of the value for  
            disputed work. 

           3)Overuse of the "substantially complex" exception  :  
            According to the author and the supporters of AB 1705,  
            many local public entities, particularly school  
            districts, have circumvented existing law by adopting  
            resolutions containing boilerplate language deeming  
            essentially every school district project as a  
            substantially complex one. 

          -------------------------
          <1> The following states have capped retention rates at 5%:  
           Arizona, Delaware, Hawaii, Idaho, Iowa, Maine,  
          Massachusetts, Minnesota, Mississippi, Missouri, Montana,  
          New York (for bonded contractors), Oregon, Rhode Island,  
          Utah, Virginia, and Washington.

          <2> Public Contract Code § 7201





          AB 1705 (Williams) continued                              
          PageD


            For example, supporters furnished a sample resolution for  
            use by school districts in which substantially complex  
            projects are those which are, among other things, subject  
            to design approval by the State Architect (which happens  
            to be every school construction or modification project),  
            subject to higher safety standards than other public  
            works projects (any maintenance, construction or  
            modification done at school district property), and the  
            like. 

            In a specific instance, Newport Mesa Unified adopted a  
            resolution designating all of its school construction  
            projects as substantially complex ones because they are,  
            among other things, "designed to higher safety standard,  
            including seismic, fire protection and ADA compliance."   
            These resolutions are then routinely cited by the school  
            board in advance of the bid in order to form a basis to  
            support a 10% retention amount included on all of its  
            school construction projects. 

           4)Support  : The sponsors of the bill complain that the  
            actions of public agencies have undermined the law, which  
            is intended to apply to all projects unless a project is  
            exceptionally unique, but the agencies and their  
            attorneys have instead turned this substantially complex  
            "exception" into the rule, and are routinely deeming  
            simple projects "substantially complex" in order to  
            withhold 10% instead of 5%. Supporters believe that AB  
            1705 will remedy this situation because it requires  
            public entities to explain the reasons why a project is  
            complex, as well as the project's retention rate. 

           5)Opposition  : The opponents say that the construction  
            contract companies should be focusing solely on school  
            projects, where the substantially complex exception rule  
            has apparently been troublesome for construction  
            companies. They would prefer this approach to one that  
            seeks to define "substantially complex" by what is isn't  
            - which is a counterintuitive approach that will only  
            lead to additional litigation and further hinder the  
            decisions that local agencies can make on behalf of their  
            taxpayers and ratepayers. 

           6)Suggested amendment  : In order to avoid another  
            contentious fight in a little more than a year from now  
            about retention proceeds, and the substantially complex  





          AB 1705 (Williams) continued                              
          PageE


            exception to the 5% retention rule, the Committee or the  
            author should amend AB 1705 to delete or extend the  
            January 1, 2016 sunset clause that now exists in Public  
            Contract Code § 7201.

                            PRIOR/RELATED LEGISLATION
           
          SB 293 (Padilla), Chapter 700, Statutes of 2011. Among  
          other things, prohibits a public entity from retaining more  
          than 5% of a contract price until final completion and  
          acceptance of a project, but allows retention of higher  
          amounts when a project is deemed "substantially complex."

          SB 802 (Leno), 2009-2010 Session. Would have prohibited the  
          Department of General Services (DGS) from withholding more  
          than 5% of a contract price until final completion and  
          acceptance of the project. Would also have prohibited  
          retention proceeds from exceeding 5% percent of a payment  
          for all contracts entered into between an original  
          contractor and a subcontractor, and between all  
          subcontractors. (Vetoed)

          SB 629 (Liu), 2009-2010 Session. Would have prohibited  
          withholding of retention proceeds in private works of  
          improvements from exceeding 5% of the amount otherwise due  
          under the contract. (Died on Senate Inactive File)

          AB 396 (Fuentes), 2009-2010 Session. Would have reduced the  
          allowable retention proceeds on public works contracts to  
          5%. (Held in Assembly Appropriations)

          SB 593 (Margett), Chapter 341, Statutes of 2008. Prohibits  
          the Department of Transportation from withholding retention  
          proceeds when making progress payments to a contractor for  
          works performed on a transportation project. Repealed  
          effective 1/1/2014.

          SB 619 (Migden), 2007-08 Session. Would have prohibited  
          retention proceeds from exceeding 5% of a payment for all  
          contracts between a public entity and an original  
          contractor and a subcontractor, and between all  
          subcontractors. The bill would also have prohibited DGS  
          from withholding more than five percent of a contract price  
          until final completion and acceptance of the project. (Died  
          on the Assembly Floor)






          AB 1705 (Williams) continued                              
          PageF


           SUPPORT:   


          Air Conditioning & Refrigeration Contractors Association
          Air Conditioning Sheet Metal Association
          Air Conditioning Trade Association
          American Subcontractors Association California 
          Associated Builders and Contractors - San Diego Chapter
          Building Industry Credit Association
          California Association of Sheet Metal & Air Conditioning  
          Contractors 
          California Chapter, American Fence Association
          California Chapters of the National Electrical Contractors  
          Association 
          California Concrete Contractors Association
          California Fence Contractors' Association
          California Landscape Contractors Association
          California Legislative Conference, Plumbing, Heating and  
          Piping Industry
          California State Association of Electrical Workers
          California State Council of Laborers
          California State Pipe Trades Council
          Flasher Barricade Association
          Marin Builders Association
          Plumbing-Heating-Cooling Contractors Association of  
          California
          Sheet Metal and Air Conditioning Contractors' National  
          Association
          State Building and Construction Trades Council
          United Contractors
          Western Electrical Contractors Association 
          Western State Council of Sheet Metal Workers

           OPPOSE:   

          Association of California Water Agencies
          El Dorado Irrigation District
          La Puente County Water District
          Newhall County water District
          Pico Water District
          Rowland Water District 

           FISCAL COMMITTEE:   None
                                        

                                   **********





          AB 1705 (Williams) continued                              
          PageG