BILL ANALYSIS                                                                                                                                                                                                    Ó






                              SENATE JUDICIARY COMMITTEE
                         Senator Hannah-Beth Jackson, Chair
                              2013-2014 Regular Session


          AB 1939 (Daly)
          As Amended June 2, 2014
          Hearing Date: June 10, 2014
          Fiscal: No
          Urgency: No
          TMW


                                        SUBJECT
                                           
                Public Works:  Prevailing Wages:  Contractor's Costs

                                      DESCRIPTION  

          This bill would authorize a contractor on a private works  
          project to bring an action to recover from the hiring party that  
          the contractor directly contracts with the difference between  
          the wages actually paid to an employee and the increased wages  
          that were required to be paid to an employee, in addition to any  
          penalties or other sums required to be paid, and costs and  
          attorney's fees, because the project was subsequently deemed to  
          be a public work subject to prevailing wage requirements.

                                      BACKGROUND 

          Existing law generally requires a worker on a public works  
          project to be paid not less than the prevailing wage as  
          determined by the Director of Industrial Relations (DIR).   
          Typically, a contractor or subcontractor will be notified by the  
          DIR of the failure to comply with that requirement, and the  
          contractor or subcontractor is responsible for payment of the  
          difference between the wages paid to workers and the prevailing  
          wage rate.  SB 966 (Alarcon, Ch. 804, Stats. 2003) authorized a  
          contractor to bring an action to recover from the body awarding  
          the contract for a public work any increased costs incurred by  
          the contractor, including labor cost increases and penalties, if  
          the body awarding the contract knew the project was a public  
          work but failed to disclose that information to the contractor  
          or subcontractor.

          Similarly, this bill would authorize the contractor to bring an  
                                                                (more)



          AB 1939 (Daly)
          Page 2 of ?



          action to recover costs associated with a prevailing wage  
          violation from the hiring party that failed to disclose to the  
          contractor that the project was a public work.

                                CHANGES TO EXISTING LAW
           
           Existing law  requires, for public works projects of more than  
          $1,000, all workers employed on the project to be paid not less  
          than the general prevailing rate of per diem wages for work of a  
          similar character in the locality in which the public work is  
          performed, and not less than the general prevailing rate of per  
          diem wages for holiday and overtime work fixed.  (Lab. Code Sec.  
          1771.)
           
          Existing law  requires the Department of Industrial Relations  
          (DIR) to monitor and enforce compliance with applicable  
          prevailing wage requirements for any public works project.   
          (Lab. Code Sec. 1771.3(a)(1).)
           
          Existing law  requires a public works contractor to whom the  
          contract is awarded, and any subcontractor under him, to pay not  
          less than the specified prevailing rates of wages to all workmen  
          employed in the execution of the contract.  (Lab. Code Sec.  
          1774.)

           Existing law  requires the contractor and any subcontractor under  
          the contractor to, as a penalty to the state or political  
          subdivision on whose behalf the contract is made or awarded,  
          forfeit not more than $200 for each calendar day, or portion  
          thereof, for each worker paid less than the prevailing wage  
          rates as determined by the director for the work or craft in  
          which the worker is employed for any public work done under the  
          contract by the contractor or by any subcontractor under the  
          contractor.  (Lab. Code Sec. 1775(a)(1).)

           Existing law  requires the difference between the prevailing wage  
          rates and the amount paid to each worker for each calendar day  
          or portion thereof for which each worker was paid less than the  
          prevailing wage rate to be paid to each worker by the contractor  
          or subcontractor.  (Lab. Code Sec. 1775(a)(2)(E).)

           Existing law  provides that if a worker employed by a  
          subcontractor on a public works project is not paid the general  
          prevailing rate of per diem wages by the subcontractor, the  
          prime contractor of the project is not liable for any penalties  
          unless the prime contractor had knowledge of that failure of the  
                                                                      



          AB 1939 (Daly)
          Page 3 of ?



          subcontractor to pay the specified prevailing rate of wages to  
          those workers or unless the prime contractor fails to comply  
          specified requirements.  (Lab. Code Sec. 1775(b).)
           
          Existing law  authorizes a contractor to bring an action in a  
          court of competent jurisdiction to recover from the body  
          awarding a contract for a public work or otherwise undertaking  
          any public work any increased costs incurred by the contractor  
          as a result of any decision by the body, the DIR, or a court  
          that classifies, after the time at which the body accepts the  
          contractor's bid or awards the contractor a contract in  
          circumstances where no bid is solicited, the work covered by the  
          bid or contract as a public work, if that body, before the bid  
          opening or awarding of the contract, failed to identify as a  
          public work in the bid specification or in the contract  
          documents that portion of the work that the decision classifies  
          as a public work.  (Lab. Code Sec. 1781(a)(1).)

           Existing law  limits liability of the body awarding a contract  
          for a public work for recovery of increased costs if all of the  
          following conditions are met:
           the contractor did not directly submit a bid to, or directly  
            contract with, that body;
           the body stated in the contract, agreement, ordinance, or  
            other written arrangement by which it undertook the public  
            work that the work was a public work and obligated the party  
            with whom the body makes its written arrangement to cause the  
            work to be performed as a public work;
           the body fulfilled all of its duties, if any, under the Civil  
            Code or any other provision of law pertaining to the body  
            providing and maintaining bonds to secure the payment of  
            contractors, including the payment of wages to workers  
            performing the work; and
           if a contractor did not directly submit a bid to, or directly  
            contract with a body awarding a contract for, or otherwise  
            undertaking a public work, the liability of that body in an  
            action commenced by the contractor, who has made a good faith  
            attempt to collect that portion of the judgment against a  
            surety bond, guarantee, or some other form of assurance, is  
            limited to that portion of a judgment, obtained by that  
            contractor against the body that solicited the contractor's  
            bid or awarded the contract to the contractor, that the  
            contractor is unable to satisfy. (Lab. Code Sec. 1781(a)(2).)

           Existing law  provides that "awarding body" does not include the  
          Department of General Services, the Department of  
                                                                      



          AB 1939 (Daly)
          Page 4 of ?



          Transportation, or the Department of Water Resources, and  
          "increased costs" includes, but is not limited, to labor cost  
          increases required to be paid to workers who perform or  
          performed work on the public work and penalties for which the  
          contractor is liable.  (Lab. Code Sec. 1781(c).)
           
          Existing law  authorizes a contractor to bring an action in a  
          court of competent jurisdiction to recover from an awarding body  
          the difference between the wages actually paid to an employee  
          and the wages that were required to be paid to an employee, any  
          penalties required to be paid, and costs and attorney's fees  
          related to this action, if either of the following is true:
           the awarding body previously affirmatively represented to the  
            contractor in writing, in the call for bids, or otherwise,  
            that the work to be covered by the bid or contract was not a  
            public work; or
           the awarding body received actual written notice from the DIR  
            that the work to be covered by the bid or contract is a public  
            work, and failed to disclose that information to the  
            contractor before the bid opening or awarding of the contract.  
             (Lab. Code Sec. 1726(c).)

           Existing law  , before making payments to the contractor of money  
          due under a contract for public work, requires the awarding body  
          to withhold and retain therefrom all amounts required to satisfy  
          any civil wage and penalty assessment issued by the Labor  
          Commissioner, and amounts required to satisfy a civil wage and  
          penalty assessment shall not be disbursed by the awarding body  
          until receipt of a final order that is no longer subject to  
          judicial review.  (Lab. Code Sec. 1727(a).)
           
          Existing law  provides that, if the awarding body has not  
          retained sufficient money under the contract to satisfy a civil  
          wage and penalty assessment based on a subcontractor's  
          violations, the contractor shall, upon the request of the Labor  
          Commissioner, withhold sufficient money due the subcontractor  
          under the contract to satisfy the assessment and transfer the  
          money to the awarding body, and these amounts shall not be  
          disbursed by the awarding body until receipt of a final order  
          that is no longer subject to judicial review.  (Lab. Code Sec.  
          1727(b).)

           Existing law  authorizes any contractor to withhold from any  
          subcontractor under him sufficient sums to cover any penalties  
          withheld from him by the awarding body on account of the  
          subcontractor's failure to comply with the terms of this  
                                                                      



          AB 1939 (Daly)
          Page 5 of ?



          chapter, and if payment has already been made to the  
          subcontractor the contractor may recover from him the amount of  
          the penalty or forfeiture in a suit at law.  (Lab. Code Sec.  
          1729.)
           
          Existing law  provides that if the Labor Commissioner determines  
          after an investigation that there has been a violation of this  
          chapter, the Labor Commissioner shall with reasonable promptness  
          issue a civil wage and penalty assessment to the contractor or  
          subcontractor, or both, and interest will accrue on all due and  
          unpaid wages from the date the wages were due and payable until  
          the wages are paid.  (Lab. Code Sec. 1741.)  
           
          Existing law  provides that the contractor and subcontractor  
          shall be jointly and severally liable for all amounts due  
          pursuant to a final order or a judgment thereon, and the Labor  
          Commissioner shall first exhaust all reasonable remedies to  
          collect the amount due from the subcontractor before pursuing  
          the claim against the contractor.  (Lab. Code Sec. 1743(a).)

           Existing law  defines "awarding body" or "body awarding the  
          contract" to mean department, board, authority, officer or agent  
          awarding a contract for public work.  (Lab. Code Sec. 1722.)

           Existing law  defines "contractor" and "subcontractor" to include  
          a contractor, subcontractor, licensee, officer, agent, or  
          representative thereof, acting in that capacity, when working on  
          public works.  (Lab. Code Sec. 1722.1.)

           This bill  would authorize a contractor to bring an action in a  
          court of competent jurisdiction to recover from the hiring party  
          that the contractor directly contracts with any increased costs,  
          including, but not limited to, the difference between the wages  
          actually paid to an employee and the wages that were required to  
          be paid to an employee, any penalties or other sums required to  
          be paid, and costs and attorney's fees for the action incurred  
          by the contractor as a result of any decision by the DIR, the  
          Labor and Workforce Development Agency, or a court that  
          classifies, after the time at which the contracting party  
          accepts the contractor's bid, awards the contractor a contract  
          under circumstances when no bid is solicited, or otherwise  
          allows construction by the contractor to proceed, the work  
          covered by the project, or any portion thereof, as a public  
          work, unless either of the following is true:
           the owner or developer or its agent expressly advised the  
            contractor that the work to be covered by the contract would  
                                                                      



          AB 1939 (Daly)
          Page 6 of ?



            be a public work or is otherwise subject to the payment of  
            prevailing wages; or
           the hiring party expressly advised the contractor that the  
            work subject to the contract would be a public work or is  
            otherwise subject to the payment of prevailing wages.

           This bill  would require, in order to be entitled to recovery of  
          increased costs, the contractor to notify the hiring party and  
          the owner or developer within 30 days after receipt of the  
          notice of a decision by the DIR or the Labor and Workforce  
          Development Agency, or the initiation of any action in a court  
          alleging, that the work covered by the project, or any portion  
          thereof, is a public work.

           This bill  would provide that a contractor is not required to  
          list any prevailing wage or apprenticeship standard violations  
          on a prequalification questionnaire that are the direct result  
          of the failure of the owner or developer or its agent, or a  
          contractor, hiring party to notify the contractor that the  
          project, or any portion thereof, was a public work.

           This bill  would not apply to private residential projects built  
          on private property unless the project is built pursuant to an  
          agreement with a state agency, redevelopment agency, or local  
          public housing authority.

           This bill  would not apply if the conduct of the contractor  
          caused the project to be a public work or if the contractor has  
          actual knowledge that the work is a public work.

           This bill  would define "hiring party" to mean the party that has  
          a direct contract for services provided by the contractor who is  
          seeking recovery of a prevailing wage deficiency on a private  
          works project that was subsequently determined by the DIR or the  
          Labor and Workforce Development Agency, or the initiation of any  
          action in a court alleging, that the work covered by the  
          project, or any portion thereof, to be a public work.

           This bill  would allow a contractor to only seek recovery from  
          the hiring party with whom the contractor has a direct contract.

           This bill  would define "contractor" to mean a person or entity  
          licensed by the Contractors' State License Board that has a  
          direct contract with the hiring party to provide services on  
          private property or for the benefit of a private owner or  
          developer.
                                                                      



          AB 1939 (Daly)
          Page 7 of ?




                                        COMMENT
           
          1.  Stated need for the bill  
          
          The author writes:
            
            Current law is silent on whether private developers should  
            notify contractors of their intentions to use taxpayer dollars  
            on construction project[s].  Developers have no legal  
            obligation to inform contractors if they utilized tax  
            subsidies.  The lack of a notification requirement can leave  
            contractors unaware of whether a particular construction  
            project requires prevailing wages.  This can in turn put  
            workers at risk of being incorrectly compensated until some  
            sort of enforcement or legal action is taken.

            Under AB 1939, should a developer fail to inform a contractor  
            of a prevailing wage mandate, the developer will then be  
            required to reimburse the contractor for unpaid wages,  
            including legal fees and penalties levied by the Department of  
            Industrial Relations (DIR).  Contractors would in turn be  
            required to reimburse subcontractors.

            Additionally, contractors who fail to inform subcontractors  
            that a particular project is subject to prevailing wages will  
            be held liable for unpaid wages, along with legal fees and  
            associated penalties levied by the DIR.

          2.  Recovery of prevailing wage deficiencies from hiring party 

          This bill would authorize a contractor to recover the difference  
          between the wages actually paid to an employee and the wages  
          that were required to be paid to an employee, any penalties or  
          other sums required to be paid, and costs and attorney's fees  
          incurred by the contractor, because a private works project for  
          which the contractor was hired by the hiring party to provide  
          services was subsequently determined to be a public work.   
          California's prevailing wage law (PWL) requires the prevailing  
          wage (set by the DIR) to be paid to all workers employed on a  
          public work.  (Lab. Code Sec. 1771.)

          The author states that this bill was prompted by a recent  
          appellate court decision and subsequent prevailing wage  
          collection by the DIR from a prime contractor in connection with  
          a construction project that was deemed to be a public work.  In  
                                                                      



          AB 1939 (Daly)
          Page 8 of ?



          Hensel Phelps Construction Co. v. San Diego Unified Port Dist.  
          (2011) 197 Cal.App.4th 1020, 1034, the court determined that,  
          even though a lease between the San Diego Unified Port District  
          (Port District) and One Park Boulevard, LLC (OPB) was merely a  
          ground lease and not a construction project contract, the OPB's  
          hotel construction project was a public work subject to the  
          payment of prevailing wages because a rent credit provided in  
          OPB's lease with the Port District was intended to subsidize  
          construction of the hotel project.  Accordingly, the court held  
          that the rent credit in the lease qualified as a reduction and  
          waiver of rent within the meaning of the definition of "public  
          work" in the PWL.  (Id. at pp. 1040-41.)  After the court's  
          decision, the prime contractor on the hotel project, Hensel  
          Phelps Construction Company, negotiated with the DIR the amount  
          of wages due to the 2,051 workers on that project, amounting to  
          more than $8 million, and Hensel Phelps was also required to pay  
          an additional $400,000 to the Labor Commissioner as  
          reimbursement for investigative costs.  (Cal. Dept. of  
          Industrial Relations, News Release No. 13-30, Labor Commissioner  
          Collects Over $8 Million in Wages for Public Works Job at Hilton  
          Hotel in San Diego (June 17, 2013).)

          The sponsors of this bill argue that existing law provides for  
          public agency liability if it fails to include in a request for  
          proposal that a construction project is subject to prevailing  
          wages, yet existing law requires no such notice by private  
          owners or developers when public subsidies trigger a prevailing  
          wage requirement.  This bill would require the owner or  
          developer to reimburse the contractor for unpaid wages, sums  
          incurred pursuant to the Labor Code and attorney's fees  
          associated with the owner's or developer's failure to provide  
          direction to the contractor.  In this way, the sponsors assert  
          that this bill would ensure timely payment of prevailing wages  
          and reduce DIR enforcement actions.  As already provided under  
          existing law, the party responsible for providing notice of a  
          public work and attendant prevailing wage requirements is liable  
          for prevailing wage deficiencies if the contractor does not pay  
          the prevailing wage required.  This bill would further that  
          policy by requiring the owner or developer of the project to be  
          liable for the prevailing wage deficiencies if the owner or  
          developer does not notify the contractor of the prevailing wage  
          requirement.

          Staff notes that this bill was recently amended to clarify that  
          the contractor may bring an action to recover the prevailing  
          wage deficiencies only against the hiring party with whom the  
                                                                      



          AB 1939 (Daly)
          Page 9 of ?



          contractor has a direct contract to provide services on a  
          private works project that is subsequently deemed to be a public  
          work.  This clarification is necessary to authorize actions only  
          against the party that has the most information about the public  
          work determination (the party that hired the contractor) and to  
          avoid other contractor or subcontractors, who arguably would  
          have even less information because they do not have a direct  
          contract with the owner or developer, from being liable for the  
          prevailing wage deficiencies. 


           Support  :  Air Conditioning Trade Association; American Fence  
          Association - California Chapter; Associated Builders and  
          Contractors - San Diego Chapter; California Concrete Contractors  
          Association; California Fence Contractors' Association;  
          California Professional Association of Specialty Contractors;  
          Flasher Barricade Association; Marin Builders Association;  
          Plumbing-Heating-Cooling Contractors Association of California;  
          Western Electrical Contractors Association

           Opposition  :  None Known




                                        HISTORY
           
           Source  :  Associated General Contractors; Construction Employers'  
          Association

           Related Pending Legislation  :  None Known 

           Prior Legislation  :  SB 966 (Alarcon, Ch. 804, Stats. 2003) See  
          Background.

           Prior Vote  :

          Assembly Floor (Ayes 75, Noes 0) 
          Assembly Committee on Judiciary (Ayes 10, Noes 0)
          Assembly Committee on Labor and Employment (Ayes 6, Noes 0)

                                   **************
                                          



                                                                      



          AB 1939 (Daly)
          Page 10 of ?