BILL ANALYSIS                                                                                                                                                                                                    Ó          1





                SENATE ENERGY, UTILITIES AND COMMUNICATIONS COMMITTEE
                                 ALEX PADILLA, CHAIR
          

          AB 2584 -  Nestande                               Hearing Date:   
          June 23, 2014              A
          As Amended:         June 16, 2014            FISCAL       B

                                                                        2
                                                                        5
                                                                        8
                                                                        4

                                      DESCRIPTION
          
          Current law  requires the state's investor-owned utilities  
          (IOUs), publicly-owned utilities (POUs) (except the Los Angeles  
          Department of Water and Power), and other entities offering  
          retail electric service, to credit all electricity generated by  
          a customer-owned renewable electric generation facility against  
          the customer's usage of electricity sold by the utility, on a  
          kilowatt hour basis (kWh), a procedure known as "net energy  
          metering" (NEM).  Participation by all utilities is capped at  
          five percent of each utility's aggregate peak electricity demand  
          and the size of individual renewable electric generation  
          facilities is limited to those that will offset all or part of  
          the customer's own electrical requirements to a maximum of 1  
          megawatt (MW).  This program also exempts the customer from  
          paying transmission and distribution costs and requires the  
          utility to expedite interconnection at no less than 30 days.   
          This is commonly referred to as full retail NEM.  (Public  
          Utilities Code § 2827)
           
          Current law  defines "wind energy co-metering" as any wind energy  
          project greater than 50 kWh, but not exceeding one MW, where  
          electricity generated by the eligible customer-generator and fed  
          back to the grid is credited, over a 12-month period, against  
          the electricity supplied to the eligible customer-generator by  
          the grid. (Public Utilities Code §§ 2827, 2827.8)

           Current decisions of the California Public Utilities Commission   
          (CPUC) establish parameters for any IOU customer to interconnect  
          generation to an IOU's distribution system, renewable or  
          fossil-fueled, to offset their electrical load if they do not  











          export power to the grid.   (Rule 21) 

           This bill  requires Southern California Edison (Edison) to  
          interconnect a 1.5 MW wind turbine located at the United States  
          Marine Corp Logistics Base, Barstow.

                                      BACKGROUND
           
          Marine Corp Logistics Base, Barstow (MCLBB, the Base) - The base  
          is a United States Marine Corp supply and maintenance  
          installation located four miles east of the City of Barstow in  
          San Bernardino County. Its mission is to enable operational  
          readiness through infrastructure, logistics, and services to  
          support the Marine Corps, the Army, and other government  
          components. 

          Congressional legislation, Presidential directives, and military  
          policies require all military bases to diversify supply, update  
          energy infrastructure, and reduce energy costs. The military's  
          overall goal is procuring or producing 25% renewable energy by  
          2025.

          Peak demand at the base is about 7.2 MW and average demand is  
          about 3.2 MW. Although Edison was involved in the purchase and  
          interconnection of the wind turbine (see below), the base is a  
          direct access (DA) customer of the Western Area Power  
          Administration (WAPA), which means that it has a bilateral  
          contract for the purchase and sale of energy - the vast majority  
          of which is greenhouse gas (GHG)-free hydroelectric power. 
           
           A wind turbine was acquired through a federal Utility Energy  
          Service Contract (UESC) whereby, Edison provided analysis,  
          design, installation, and financing for the federal entity,  
          MCLBB. Edison facilitated the purchase of a 1.5 MW wind turbine  
          because not 1 MW turbine was available. The turbine became  
          operational in March 2009 and was interconnected through the NEM  
          tariff. Following a short trial period during which the turbine  
          operated at 1.5 MW, Edison required MCLBB to de-rate the turbine  
          to 1 MW to prevent export and to comply with a statutory cap on  
          systems operating under the NEM tariff.  De-rating the turbine  
          resulted in technical operational challenges initially, but  
          Edison and the base agree that these challenges largely have  
          been resolved. 











          Interconnection Challenges - Project developers and grid  
          operators face challenges as increasing volumes of renewable  
          distributed generation attempt to interconnect. Even small-scale  
          renewable systems can trigger in-depth engineering studies and  
          expensive grid upgrades if they occur in locations with limited  
          capacity. 

                                       COMMENTS
           
              1.   Author's Statement  . "According to the USMC, de-rating of  
               the turbine has forced them to under-utilize [their]  
               renewable energy assets? [and] raising the NEM cap for  
               MCLBB would allow its wind turbine to operate at full  
               capacity. Edison has replied that state law prohibits the  
               base from operating the wind turbine at full capacity."

              2.   This is Not a New Dispute  . This bill would provide for  
               wind energy co-metering for MCLBB, not to exceed 1.5 MW.  
               The base has spent a great deal of time working with Edison  
               on a remedy to this issue.  Edison argues, and the  
               California Independent System Operator (CAISO) has  
               confirmed, that the area in which the base is located has  
               congestion and there is not sufficient capacity on the  
               distribution/transmission system to accommodate additional  
               generation.  

               The CAISO advises that a transmission upgrade is planned  
               for the Coolwater/Lugo line and that there are 100  
               interconnection requests, between Edison and the CAISO,  
               waiting for additional capacity in that vicinity.  The  
               additional capacity will be available in 2018.  In the  
               meantime Edison can and will interconnect the turbine under  
               Rule 21 as non-exporting generator. This option would  
               require the base to submit an application, pay associated  
               application and study fees, install equipment to prevent  
               export, and be subject to Edison's standby and departing  
               load tariffs. The base currently opposes (non-legislative)  
               approaches that would incur additional costs.
               Given that the base has an average baseload of 3.2 MW, it's  
               not clear why the base cannot utilize all of the generation  
               onsite without export.  However, trying to stay within a  
               NEM tariff does suggest that the base would be exempt from  
               some customer charges if they could move the additional  
               capacity into NEM and above the 1.0 MW program cap.











              3.   Related Legislation  . 

               AB 2649 (Mullin) would support the development of  
               independent generation facilities on military bases and  
               privatized military housing by exempting these facilities  
               from interconnection agreements, associated interconnection  
               fees, and departing load charges, as specified. Status:  
               Pending consideration by the Senate Committee on Energy,  
               Utilities, and Communications June 23.

               AB 2229 (Bradford) require the CPUC to establish an energy  
               efficiency program specifically for military bases and  
               facilities.  Status: Pending consideration by the Senate  
               Committee on Energy, Utilities, and Communications June 23.
          .
                                    ASSEMBLY VOTES
                                           
          Assembly Floor                     (77-0)
          Assembly Appropriations Committee  (17-0)
          Assembly Utilities and Commerce Committee                       
          (12-0)

                                       POSITIONS
           
           Sponsor:
           
          United States Marine Corps

           Support:
           
          None on file

           Neutral:
           
          Southern California Public Power Authority

           Oppose:
           
          California State Association of Electrical Workers
          Coalition of California Utility Employees 
          Southern California Edison

          










          Alexis Erwin 
          AB 2584 Analysis
          Hearing Date:  June 23, 2014