BILL ANALYSIS Ó 1 SENATE ENERGY, UTILITIES AND COMMUNICATIONS COMMITTEE ALEX PADILLA, CHAIR AB 2584 - Nestande Hearing Date: June 23, 2014 A As Amended: June 16, 2014 FISCAL B 2 5 8 4 DESCRIPTION Current law requires the state's investor-owned utilities (IOUs), publicly-owned utilities (POUs) (except the Los Angeles Department of Water and Power), and other entities offering retail electric service, to credit all electricity generated by a customer-owned renewable electric generation facility against the customer's usage of electricity sold by the utility, on a kilowatt hour basis (kWh), a procedure known as "net energy metering" (NEM). Participation by all utilities is capped at five percent of each utility's aggregate peak electricity demand and the size of individual renewable electric generation facilities is limited to those that will offset all or part of the customer's own electrical requirements to a maximum of 1 megawatt (MW). This program also exempts the customer from paying transmission and distribution costs and requires the utility to expedite interconnection at no less than 30 days. This is commonly referred to as full retail NEM. (Public Utilities Code § 2827) Current law defines "wind energy co-metering" as any wind energy project greater than 50 kWh, but not exceeding one MW, where electricity generated by the eligible customer-generator and fed back to the grid is credited, over a 12-month period, against the electricity supplied to the eligible customer-generator by the grid. (Public Utilities Code §§ 2827, 2827.8) Current decisions of the California Public Utilities Commission (CPUC) establish parameters for any IOU customer to interconnect generation to an IOU's distribution system, renewable or fossil-fueled, to offset their electrical load if they do not export power to the grid. (Rule 21) This bill requires Southern California Edison (Edison) to interconnect a 1.5 MW wind turbine located at the United States Marine Corp Logistics Base, Barstow. BACKGROUND Marine Corp Logistics Base, Barstow (MCLBB, the Base) - The base is a United States Marine Corp supply and maintenance installation located four miles east of the City of Barstow in San Bernardino County. Its mission is to enable operational readiness through infrastructure, logistics, and services to support the Marine Corps, the Army, and other government components. Congressional legislation, Presidential directives, and military policies require all military bases to diversify supply, update energy infrastructure, and reduce energy costs. The military's overall goal is procuring or producing 25% renewable energy by 2025. Peak demand at the base is about 7.2 MW and average demand is about 3.2 MW. Although Edison was involved in the purchase and interconnection of the wind turbine (see below), the base is a direct access (DA) customer of the Western Area Power Administration (WAPA), which means that it has a bilateral contract for the purchase and sale of energy - the vast majority of which is greenhouse gas (GHG)-free hydroelectric power. A wind turbine was acquired through a federal Utility Energy Service Contract (UESC) whereby, Edison provided analysis, design, installation, and financing for the federal entity, MCLBB. Edison facilitated the purchase of a 1.5 MW wind turbine because not 1 MW turbine was available. The turbine became operational in March 2009 and was interconnected through the NEM tariff. Following a short trial period during which the turbine operated at 1.5 MW, Edison required MCLBB to de-rate the turbine to 1 MW to prevent export and to comply with a statutory cap on systems operating under the NEM tariff. De-rating the turbine resulted in technical operational challenges initially, but Edison and the base agree that these challenges largely have been resolved. Interconnection Challenges - Project developers and grid operators face challenges as increasing volumes of renewable distributed generation attempt to interconnect. Even small-scale renewable systems can trigger in-depth engineering studies and expensive grid upgrades if they occur in locations with limited capacity. COMMENTS 1. Author's Statement . "According to the USMC, de-rating of the turbine has forced them to under-utilize [their] renewable energy assets? [and] raising the NEM cap for MCLBB would allow its wind turbine to operate at full capacity. Edison has replied that state law prohibits the base from operating the wind turbine at full capacity." 2. This is Not a New Dispute . This bill would provide for wind energy co-metering for MCLBB, not to exceed 1.5 MW. The base has spent a great deal of time working with Edison on a remedy to this issue. Edison argues, and the California Independent System Operator (CAISO) has confirmed, that the area in which the base is located has congestion and there is not sufficient capacity on the distribution/transmission system to accommodate additional generation. The CAISO advises that a transmission upgrade is planned for the Coolwater/Lugo line and that there are 100 interconnection requests, between Edison and the CAISO, waiting for additional capacity in that vicinity. The additional capacity will be available in 2018. In the meantime Edison can and will interconnect the turbine under Rule 21 as non-exporting generator. This option would require the base to submit an application, pay associated application and study fees, install equipment to prevent export, and be subject to Edison's standby and departing load tariffs. The base currently opposes (non-legislative) approaches that would incur additional costs. Given that the base has an average baseload of 3.2 MW, it's not clear why the base cannot utilize all of the generation onsite without export. However, trying to stay within a NEM tariff does suggest that the base would be exempt from some customer charges if they could move the additional capacity into NEM and above the 1.0 MW program cap. 3. Related Legislation . AB 2649 (Mullin) would support the development of independent generation facilities on military bases and privatized military housing by exempting these facilities from interconnection agreements, associated interconnection fees, and departing load charges, as specified. Status: Pending consideration by the Senate Committee on Energy, Utilities, and Communications June 23. AB 2229 (Bradford) require the CPUC to establish an energy efficiency program specifically for military bases and facilities. Status: Pending consideration by the Senate Committee on Energy, Utilities, and Communications June 23. . ASSEMBLY VOTES Assembly Floor (77-0) Assembly Appropriations Committee (17-0) Assembly Utilities and Commerce Committee (12-0) POSITIONS Sponsor: United States Marine Corps Support: None on file Neutral: Southern California Public Power Authority Oppose: California State Association of Electrical Workers Coalition of California Utility Employees Southern California Edison Alexis Erwin AB 2584 Analysis Hearing Date: June 23, 2014