BILL ANALYSIS                                                                                                                                                                                                    �          1





                SENATE ENERGY, UTILITIES AND COMMUNICATIONS COMMITTEE
                                 ALEX PADILLA, CHAIR
          

          SB 767 -  Lieu                     Hearing Date:  April 30, 2013  
                S
          As Amended:         April 4, 2013                 Non-FISCAL      
            B
                                                                        
                                                                        7
                                                                        6
                                                                        7

                                      DESCRIPTION
           
           Current law  requires investor-owned utilities, community choice  
          aggregators, and electric service providers (collectively  
          referred to as retail sellers) and local publicly-owned  
          utilities (POUs), to increase purchases of renewable energy such  
          that at least 33% of total retail sales are procured from  
          renewable energy resources by December 31, 2020. In the interim  
          each entity is required to procure an average of 20% of  
          renewable energy for the period of January 1, 2011 through  
          December 31, 2013 and 25% by December 31, 2016. This is known as  
          the Renewables Portfolio Standard (RPS).

           Current law  requires the California Energy Commission (CEC) to  
          certify generating facilities for purposes of establishing  
          eligibility under the RPS and to design and implement an  
          accounting system to verify compliance with the RPS by retail  
          sellers and POUs. 

           Current law  defines an eligible renewable electrical generation  
          facility and includes in that definition a facility that uses  
          landfill gas or digester gas (biomethane) delivered through a  
          common carrier pipeline if the source and delivery of the fuel  
          can be verified by the CEC.  For facilities that rely on  
          biomethane, eligibility is distinguished by the contract date  
          for the fuel.  If the contract was executed and reported to the  
          CEC before March 29, 2012, the biomethane must be flowing on or  
          before April 1, 2014.  This is commonly referred to as the flow  
          date.

           This bill  extends the flow date until April 1, 2015.  











                                      BACKGROUND
           
          Eligible Renewable Generation - Procurement from a renewable  
          facility cannot be counted for purposes of complying with the  
          RPS unless that facility has been certified as RPS-eligible by  
          the CEC. Facilities interested in obtaining a bilateral contract  
          or competing in a load-serving entity's RPS solicitation  
          generally pre-certify the facility with the CEC.

          There are two types of certification: (1) RPS Certification,  
          and, (2) RPS Pre-Certification. Renewable facilities that are  
          under development may seek "pre-certification," with the  
          understanding that the CEC will verify the information submitted  
          in the pre-certification application once the facility has been  
          completed and is delivering electricity. All certified and  
          pre-certified facilities are subject to audit. The Western  
          Renewable Energy Generation Information System (WREGIS) has been  
          developed to satisfy current RPS tracking requirements. All  
          RPS-certified facilities must register with WREGIS. 

          The fourth edition of the CEC's RPS eligibility guidebook,  
          released in January 2011, introduced a number of changes to the  
          treatment of biomethane injected into the natural gas pipeline  
          system. Some of the more noteworthy changes were the creation of  
          the biogas section as a stand-alone section, the introduction of  
          the term "pipeline biomethane," and clarifying the delivery  
          requirements for delivering biogas (now called pipeline  
          biomethane, or biomethane) for use in an RPS-eligible electric  
          generating facility.  

          Pipeline biomethane stands out in the portfolio of eligible RPS  
          resources because it is transported to a natural gas facility  
          and it is the natural gas facility that gets certified as  
          RPS-eligible because some portion of the generation from the  
          facility is considered renewable based on the fuel source.   
          Other RPS-eligible facilities have the fuel source and  
          generating facility at the same site.  Consequently, until the  
          adoption of AB 2196, in trying to define as RPS eligible,  
          pipeline biomethane, the CEC had to try and fit a square peg  
          into a round hole when it released its 2011 eligibility  
          guidebook.

          Pipeline Biomethane Suspension - After the release of the 2011  
          eligibility guidebook by the CEC, controversy ensued over the  
          new classification of "pipeline biomethane."  The adoption of SB  









          x1 2 with its product categories, delivery requirements, and  
          environmental objectives raised further question as to whether  
          pipeline biomethane as defined as eligible in the guidebook was  
          consistent with the RPS program.  The guidelines for pipeline  
          landfill and digester gas do not require displacement of fossil  
          fuel consumption, the reduction of air pollution, or other  
          environmental benefits to California.  Additionally, the  
          contracts being signed by some California retail sellers and  
          POUs were with landfills from as far away as Pennsylvania, Ohio  
          and Tennessee - locales which make it physically impossible to  
          verify delivery of the fuel to California particularly because  
          the flow of those pipelines passes through pipelines flowing in  
          the opposite direction of California.  The RPS also intends that  
          the program achieve "additionality" - that new development of  
          renewables occurs - but in the case of many of the contracts,  
          the biomethane had been flowing for quite some time so that  
          there appeared to be no new capture or incremental capture  
          occurring.  The 4th guidebook also lacked vigorous requirements  
          to verify that the claimed quantity of biomethane was actually  
          used by the designated power plant or that the necessary  
          biomethane attributes were transferred to the power plant  
          operator for purposes of the RPS and not double-counted for  
          other purposes. 

          The CEC recognized that its guidebook was inconsistent with the  
          requirements of SB x1 2 and on March 28, 2012, voted to suspend  
          the RPS eligibility guidelines relative to biomethane with  
          specified conditions.  

          AB 2196 (Chesbro, 2012) - The passage of this bill brought  
          clarity for biomethane eligibility and established standards for  
          the fuel source based on the contract execution date between the  
          biomethane supplier and the utility.  For contracts executed  
          before the CEC's suspension, the CEC is to certify those  
          supplies as eligible under the rules in place at that time.   
          Contracts executed or amended on or after March 29, 2012, are  
          subject to new conditions as specified in AB 2196 and subsequent  
          rules adopted by the CEC.  Those conditions include a "flow  
          date" requirement for the biomethane of April 1, 2014 meaning  
          that the biomethane source must be producing and capturing  
          biomethane and injecting it into a common carrier pipeline by  
          that date.

          The CEC certifies an "eligible renewable facility."  In the case  
          of pipeline biomethane, the CEC will certify a natural gas plant  









          that will receive pipeline biomethane.  Until the passage of AB  
          2196 (Chesbro) last year (Chapter 605, Statutes of 2012) the CEC  
          did not consider the execution date of a contract or the flow  
          date in its certification process.  

          RPS Eligibility Guidebook, Seventh Edition - Although AB 2196  
          grandfathered some biomethane purchases, some of those contracts  
          had been executed but the biomethane source had not been  
          developed and the fuel wasn't flowing.  Consequently, those  
          sources still need pre-certification and certification under the  
          rules to be adopted by the CEC according to the provisions of AB  
          2196.  To implement the bill, the CEC released a "Staff Concept  
          Paper" in January which was based on consultation with the  
          CalEPA, California Air Resources Board, CalRecycle, and  
          California Department of Food and Agriculture, and many  
          interested stakeholders.  Agency and stakeholder input received  
          in response to the paper from those same parties informed the  
          development of eligibility, reporting, and verification and  
          compliance requirements pertaining to electricity generation  
          facilities using biomethane and are now reflected the draft "RPS  
          Eligibility Guidebook, Seventh Edition" which was released for  
          public comment in March.  The guidebook not only concerns  
          biomethane but describes the eligibility requirements and  
          process for certifying all eligible renewable energy resources  
          for RPS and describes the CEC's accounting system to verify  
          compliance with the RPS.

          Adoption of the guidebook by the CEC is scheduled for its April  
          30th business meeting.  At that time the CEC will also lift the  
          suspension on biomethane as an eligible fuel source under the  
          RPS.  Any developer of biomethane that has not previously  
          certified the facility into which the fuel will flow, will then  
          file a new application if one was not filed before the  
          suspension, or a form supplementing the prior application, with  
          the CEC for pre-certification.  Once the biomethane is flowing,  
          a final request for certification is filed with the CEC.  The  
          process is awkward since, unlike other RPS eligible generation,  
          the both fuel source and the facility are reviewed by the CEC  
          (in contrast to a solar or wind facility for instance where the  
          fuel and the generator are at the same physical site).  Some  
          natural gas plants in California are already certified as RPS  
          eligible and also receive biomethane from multiple sources and  
          under multiple contracts.

                                       COMMENTS









           
              1.   Author's Purpose  .  The author opines that there have  
               been unanticipated delays in the implementation of AB 2196  
               related to the execution of biomethane contracts and as a  
               result, it appears as if the projects won't meet the flow  
               date set in AB 2196 and need additional time to complete  
               the projects.  SB 767 makes a minor change to existing law  
               governing procurements for biomethane executed and reported  
               to the CEC prior to 3/29/12. It extends by one year the  
               flow date for these projects due to unanticipated delays in  
               implementation of AB 2196 by the CEC. The change is meant  
               to allow adequate time for completion of biomethane  
               projects once the CEC certifies the procurements as  
               eligible for use in RPS compliance. 

              2.   Upends Delicate Negotiation  .  The path for AB 2196 was  
               bumpy and fraught with controversy. Every element of the  
               bill was carefully considered.  Nearing the end of the 2012  
               legislative session, the flow date in AB 2196 was January,  
               2014.  The flow date of April 1, 2014 required in current  
               law was the result of a very sensitive negotiation and  
               reflects the request of the landfill representatives which  
               provide the biogas.  They indicated that the April, 2014  
               date would give them a fair chance to complete projects  
               underway and the bill was amended accordingly.  

               This bill "undoes" a deal which neutralized the opposition  
               of many legislators and stakeholders.  The Utility Reform  
               Network (TURN) in its opposition to AB 2196 states that the  
               April 2014 flow "date was a compromise that gave certain  
               developers an opportunity to demonstrate the near-term  
               viability of their projects...To the extent that these  
               developers cannot successfully produce or inject biomethane  
               into a common carrier pipeline prior to April 1, 2014, the  
               projects would remain eligible to provide renewable fuel  
               under Public Utilities Code �399.12.6(b) so long as the  
               sellers can demonstrate physical delivery of the biomethane  
               to California and prove that legitimate environmental  
               benefits accrue to the residents of this state."  

               Supporters of this bill represent that the change in the  
               flow date does not increase the volume of biogas permitted  
               under the pre-March, 2012 contracts but merely ensures that  
               those contracts are allowed to be fulfilled as intended by  
               the Legislature.  The author opines that the CEC has not  









               responded to the requirements of AB 2196 causing a delay in  
               implementing the bill.  The committee staff has monitored  
               the progress of the CEC's work to implement AB 2196  
               including periodic briefings by CEC staff.  When the CEC  
               adopts the guidelines on April 30th, which also required  
               consultation with several agencies and public notice and  
               comment periods, it will have fully implemented the bill -  
               four months after the bill took effect.

              3.   Referral to Rules  .  Should this bill be approved by the  
               committee, it will be referred to the Senate Committee on  
               Rules for its consideration of the re-referral request from  
               the Senate Committee on Appropriations. 

                                       POSITIONS
           
           Sponsor:
           
          Author

           Support:
           
          Burbank Water and Power
          Element Markets Renewables LLC
          Imperial Irrigation District
          Southern California Public Power Authority
          The Coalition for Renewable Natural Gas

           Oppose:
           
          California Wind Energy Association
          Large-Scale Solar Association
          Solar Energy Industries Association
          The Utility Reform Network


          Kellie Smith 
          SB 767 Analysis
          Hearing Date:  April 30, 2013