BILL ANALYSIS                                                                                                                                                                                                    Ó



                                                                     AB 552


                                                                    Page  1





          Date of Hearing:   April 21, 2015


                           ASSEMBLY COMMITTEE ON JUDICIARY


                                  Mark Stone, Chair


          AB 552  
          (O'Donnell) - As Amended March 26, 2015


                              As Proposed to be Amended


          SUBJECT:  Public works contracts: damages


          KEY ISSUE:  Should a public CONTRACT that requires a contractor  
          to pay consequential damages specify a fixed amount of damages,  
          instead of holding the contractor liable for open-ended  
          consequential damages?  


                                      SYNOPSIS


          When a breach of contract delays completion of a construction  
          project, the non-breaching party may recover consequential  
          damages (CDs) from the breaching party for any losses indirectly  
          caused by the breach and reasonably foreseeable at the time the  
          contract was made.  Because the indirect consequences of delay  
          are potentially unlimited and difficult to prove, construction  
          contracts often contain a liquidated damage (LD) provision to  
          limit liability for and make it easier for all parties, as well  
          as sureties, to assess risk.  Indeed, state law requires state  
          construction contracts to contain an LD provision that specifies  
          a fixed sum which the contractor must pay for each day beyond  








                                                                     AB 552


                                                                    Page  2





          the contracted completion date.  While LD provisions are common  
          in construction contracts, CD provisions are relatively rare.   
          Where CD clauses exist at all in construction contracts, it is  
          often to specify that there is "no liability" for CDs.  Indeed  
          LD clauses for delay are often intended as a substitute for  
          difficult to prove CDs resulting from delay.  Recently however,  
          the author and sponsor claim, some public agencies have included  
          CD clauses in contracts that make the contractor liable for  
          potentially unlimited consequential damages with no set amount  
          or even a range of amounts, even though these same contracts may  
          contain LD clauses that require the contractor to a pay a fixed  
          daily amount for delays.  While CD clauses in public contracts  
          are still not the norm, the author provided the Committee with  
          evidence that such clauses are common enough that surety bonders  
          have informed contractors and public agencies that they cannot  
          underwrite public contracts with open-ended CD clauses, or can  
          only provide bonds at higher prices.  In response to such  
          concerns, some public agencies, the Committee is informed, have  
          already removed open-ended CD clauses from all of their  
          contracts.  But apparently several have not.  This bill would  
          provide that if a public contract contains a clause making the  
          contractor liable for CDs, the amount cannot be open-ended.  In  
          other words, if there is a CD clause, the damages must be  
          liquidated to a set amount and identified in the contract.  This  
          bill is supported by several contractors' associations.  The  
          original version of the bill was opposed by the California State  
          Association of Counties (CSAC) and the League of California  
          Cities (League).   CSAC no longer opposes the bill as it is  
          proposed to be amended today.  The Committee is uncertain as to  
          whether today's amendments will remove the League's opposition.   
          The bill, as introduced, passed out of the Assembly  
          Accountability and Administrative Review Committee on a 9-0  
          vote. Author amendments to be taken in this Committee are  
          reflected in the analysis. 


          SUMMARY:  Provides that if a public contract contains a  
          consequential damages clause it must specify a set amount.   
          Specifically, this bill:  








                                                                     AB 552


                                                                    Page  3







          1)Provides that a public works contract entered into on or after  
            January 1, 2016, that contains a clause requiring a contractor  
            to be responsible for consequential damages, is not  
            enforceable unless the consequential damages have been  
            liquidated to a set amount and identified in the public works  
            contract. 


          2)Defines "public agency" for purposes of the above to include  
            the state, Regents of the University of California, a city,  
            charter city, county, charter county, district, public  
            authority, municipal utility, and any other political  
            subdivision or public corporation of the state.


          3)Makes findings and declarations relating to the need for clear  
            and uniform guidelines relating to liquidated damages in  
            public contracts. 


          EXISTING LAW:  


          1)Provides that for a breach of contract the proper measure of  
            damages, except where otherwise provided by statute, is the  
            amount which will compensate the party aggrieved for all the  
            detriment proximately caused by the breach, or which in the  
            ordinary course of things, would be likely to result from the  
            breach.  (Civil Code Section 3300.)


          2)Provides that a provision in a contract liquidating the  
            damages for the breach of the contract is valid unless the  
            party seeking to invalidate the provision establishes that the  
            provision was unreasonable under circumstances existing at the  
            time the contract was made.  (Civil Code Section 1671 (b).)









                                                                     AB 552


                                                                    Page  4






          3)Requires every state contract to contain a provision in regard  
            to the time when the whole or any specified portion of the  
            work contemplated shall be completed, and shall provide that  
            for each day completion is delayed beyond the specified time,  
            the contractor shall forfeit and pay to the state a specified  
            sum of money, to be deducted from any payments due or to  
            become due to the contractor. The sum so specified is valid as  
            liquidated damages unless manifestly unreasonable under the  
            circumstances existing at the time the contract was made.   
            (Public Contract Code Section 10226.)

          FISCAL EFFECT:  As currently in print this bill is keyed fiscal.  



          COMMENTS:  According to the sponsor, the California Construction  
          Employer Association, this bill responds to the practice of some  
          public agencies to use construction contracts that include both  
          liquidated and consequential damages.  Liquidated damages are  
          specific sums of money stipulated by the parties and written  
          into the contract as the amount of damages to be recovered by a  
          party in the event of a breach by the other party.   
          Consequential damages, which may or may not be referenced in the  
          contract, allow the non-breaching party to recover damages not  
          only for the value of the non-performed part of the contract,  
          but for any losses that flow from the consequences of breach, so  
          long as such consequences were reasonably foreseeable at the  
          time the contract was made.  


          This bill, as proposed to be amended, would simply provide that  
          if a public contract contains a clause making the contractor  
          liable for CDs, the amount cannot be open-ended.  The bill would  
          not prevent a public agency from seeking CDs, nor would it  
          require a public agency to include a CD clause in its contract.   
          Rather, the bill provides that if the public agency opts to  
          include a CD clause in the contract, then CDs must be liquidated  
          at a set amount and identified in the contract.








                                                                     AB 552


                                                                    Page  5







          The Legacy of Hadley's Mill:  The law governing a party's  
          ability to recover CDs still owes a great deal to the 19th  
          century English case of Hadley v. Baxendale 156 Eng. Rep. 145  
          (1854).  Hadley, the owner of a mill, needed to replace a worn  
          out crankshaft.  The manufacturer that Hadley hired to build a  
          new crankshaft asked Hadley to deliver the old crankshaft to its  
          facility, so that it could use the old crankshaft as a model for  
          constructing the new one.  Hadley hired Baxendale, a common  
          carrier, to deliver the crankshaft to the manufacturer.  Because  
          Baxendale was late in delivering the crankshaft to the  
          manufacturer's facility, the facility was late in getting the  
          new crankshaft to Hadley.  As a result Hadley had to close down  
          his mill for several days and failed to meet orders, all the  
          while continuing to pay his idle workers.  Hadley sued Baxendale  
          to recover his lost profits.  While the trial court ruled in  
          favor of Hadley and granted damages for the lost profits caused  
          by the delay, Hadley's damage award was overturned on appeal.   
          While the court conceded that the losses were caused by  
          Baxendale's breach, Hadley was not entitled to damages for lost  
          profits because they were not "reasonably foreseeable"  
          consequences of Baxendale's delay.  Because Baxendale did not  
          know that Hadley would need to suspend operations until the new  
          crankshaft arrived, it was reasonable for him to assume that an  
          experienced mill operator would have anticipated that  
          crankshafts wear out after a time and had a spare crankshaft  
          around, or had made some other arrangement to keep the mill  
          running.  Had Baxendale known that the mill would be closed  
          until the new crankshaft was delivered, he would have been  
          liable for the lost profits.  But Hadley never informed  
          Baxendale of any "special circumstances."  The still-accepted  
          rule of Hadley is that consequential damages are only available  
          where (1) the injury was a consequence of the breach and (2) the  
          result was reasonably foreseeable at the time when the contract  
          was made or the breaching party had knowledge of the "special  
          circumstances" that made the damages a natural consequence of  
          the breach.  









                                                                     AB 552


                                                                    Page  6






          For contractors and the bonding companies that underwrite them,  
          "consequential damages" (CDs) are especially troublesome because  
          they are unpredictable and potentially unlimited.  One of the  
          more common sources of CDs in construction contracts is the  
          failure of the contractor to complete the project on time.   
          Depending on the length of the delay and the nature of the  
          project, delays can result in lost profits and lost revenues  
          that may exceed the value of the contract.  When a breach of  
          contract delays completion of a construction project, the  
          non-breaching party may recover CDs from the breaching party for  
          any losses indirectly caused by the breach and reasonably  
          foreseeable at the time that the contract was made.  Because the  
          indirect consequences of delay are potentially unlimited and  
          difficult to prove, construction contracts often contain a  
          liquidated damage (LD) provision to limit liability for delay or  
          at least make it easier for the parties to assess risk.  Indeed,  
          state law requires state construction contracts to contain an LD  
          provision that specifies a fixed sum that the contractor must  
          pay for each day beyond the contracted completion date.  


          While LD provisions are common in construction contracts, CD  
          provisions are relatively rare.  When CD clauses are included in  
          construction contracts, it is often to specify that there is "no  
          liability" for CDs.  However in recent years, say the author and  
          sponsor, some public agencies have included CD clauses in their  
          contracts which make the contractor liable for potentially  
          unlimited consequential damages, even though these same  
          contracts may contain LD clauses that require the contractor to  
          a pay a fixed daily amount for a delay.  While CD clauses in  
          public contracts are still not the norm, the author provided the  
          Committee with evidence that such clauses are common enough that  
          surety bonders say they cannot underwrite public contracts with  
          open-ended CD clauses, or can only do so at higher prices.  In  
          response to such concerns, some public agencies, the Committee  
          is informed, have already removed open-ended CD clauses.  But,  
          apparently, several have not.









                                                                     AB 552


                                                                    Page  7






          Bill Does Not Prevent Public Agencies from Seeking Consequential  
          Damages:  Both proponents and opponents of this bill inform the  
          Committee that CDs in public construction contracts are  
          relatively rare, although some proponents claim that their use  
          is increasing.  (The Committee is not aware of anything other  
          than anecdotal evidence in support of this claim.)   In any  
          event, as noted above, CD provisions are common enough that  
          surety bond issuers have informed contractors and public  
          agencies that they cannot reasonably underwrite them, especially  
          when such contracts are open-ended without setting a fixed  
          amount.  According to the sponsor, the purpose of this bill is  
          not to prevent a public agency from seeking consequential  
          damages - which it can do with or without a CD clause - but only  
          to require that CDs effectively be capped if they are included  
          in the contract.  If a public agency can recover CDs whether or  
          not they are referenced in the contract, it raises questions  
          about why public agencies would insist on including them and why  
          contractors would object when they are included.  The answer to  
          these questions may have something to do with Hadley v.  
          Baxendale.  While an express CD clause in a contract might not  
          be dispositive, it would seem to help the agency meet its burden  
          of showing that the CDs were "reasonably foreseeable" and that  
          the contractor had knowledge of the agency's "special  
          circumstances."  This also explains why contractors would not  
          want a CD clause included in a contract unless the CDs were  
          liquidated at a set amount.  It is important to stress, however,  
          that this legislation is not intended to prevent public agencies  
          from recovering CDs.  Public agencies may opt to exclude CD  
          provisions from construction contracts and still be entitled to  
          CDs, which remain recoverable even if they are not expressly  
          provided for in the contract.  The agency would need to prove,  
          however, that the CDs were caused by the breach and were  
          reasonably foreseeable at the time when the contract was made. 


          ARGUMENTS IN SUPPORT:  According to author, "some public  
          agencies have adopted policies requiring both liquidated damages  
          and unlimited consequential damages as penalties for project  








                                                                     AB 552


                                                                    Page  8





          delays in their public works contracts.  . . .  While some of  
          these [public agencies] have reversed their decision on pursuing  
          these provisions due to difficulty finding contractors willing  
          to agree, others have not."   


          In addition to noting the "troubling trend" of public agencies  
          using LD provisions and unlimited CD provisions, the  
          Construction Employers Association (CEA), the bill's sponsor,  
          argues that CDs "are not a standard form of damages for  
          construction contracts because they are difficult to define,  
          quantify, or ascertain."  Like many of the proponents of the  
          bill, CEA stresses that CD provisions in recent public agency  
          contracts are "uninsurable because sureties will not issue  
          open-ended policies. Instead," CEA continues, "construction  
          contracts have historically addressed consequential damages for  
          delay using a stipulated Liquidated Damage . . . amount."   
          Finally CEA argues that the impact of CD provisions is not  
          "borne exclusively by general contractors;" in fact, CD  
          provisions "chill participation by subcontractors, especially  
          small contractors," in part due to rising costs and in part due  
          to the fact that most delays are caused by subcontractors and  
          damage provisions in the general contract are passed through  
          subcontractors.


          The California Concrete Contractors Association (CCA) argues  
          that, unlike liquidated damages, which are insurable, defined in  
          the contract and intended to cover actual projected damages,  
          consequential damages provisions are "uninsurable, open-ended  
          and speculative."  Their inclusion in public contracts, CCA  
          contends, "raises construction costs, chills participation by  
          mid and mall sized contractors and subcontractors, and increases  
          litigation costs."  CCA notes that "liquidated damages have been  
          the contractual standard for addressing delay damages for  
          decades and we do not believe there is a need for this practice  
          to be changed."  










                                                                     AB 552


                                                                    Page  9





          ARGUMENTS IN OPPOSITION (To Pre-Amended Version): The League of  
          California Cities (League) opposed the bill as introduced, and a  
          considerable portion of its letter addressed the provisions that  
          will no longer be included in the bill as proposed to be  
          amended.  However, the League would presumably object to the  
          remaining provision of the bill as well.  The League argues that  
          by "requiring that all consequential damages be liquidated, AB  
          552 would limit the ability of public agencies to ensure that  
          the costs associated with a contractor's non-performance or  
          under-performance could be collected.  . . AB 552 would remove  
          important tools public agencies use to ensure that public works  
          projects be completed on time, and to protect taxpayer dollars."  
           The City of Sacramento opposes the bill for substantially the  
          same reasons.


          [NOTE:  It is unclear at the time of this writing if the  
          proposed amendments remove the opposition of the League, or the  
          City of Sacramento.  The California Association of Counties  
          (CSAC) informed the Committee that they originally planned to  
          oppose the bill, but dropped their opposition in light of the  
          proposed amendments.  However, CSAC made it clear to the  
          Committee that it reserves its right to oppose the bill in the  
          future based on its ongoing analysis of the potential  
          consequences of the bill.]


          Proposed Author Amendments:   The author will take the  
          amendments listed below in this committee.  In addition to  
          deleting a subdivision that would have required all public works  
          contracts to contain liquidated damages in order to be  
          enforceable, the amendments also revise subdivision (b) to  
          better reflect to author's intent to only require CDs to be  
          fixed at a set amount if the public agency opts to include a CD  
          clause.  It was not the author's or sponsor's intent to say that  
          CDs could only be recovered if they were included in the  
          contract and liquidated.  In other words, if a public agency  
          opts not to include a CD clause, it can still recover if it can  
          show that the CDs were caused by the breach and were reasonably  








                                                                     AB 552


                                                                    Page  10





          foreseeable at the time the contract was entered into. 

             -    On page 2 delete lines 17 through 29 and insert:

          (a) Any public works contract entered into on or after January  
          1, 2016, that contains a clause requiring a contractor to be  
          responsible for consequential damages is not enforceable unless  
          the consequential damages have been liquidated to a set amount  
          and identified in the public works contract.   

             -    On page 2 line 30 change "(c)" to (b)

             -    On page 2 line 32 delete "public agency" 


          REGISTERED SUPPORT / OPPOSITION:

          Support

          Construction Employers' Association (sponsor)


          California Concrete Contractors Association


          California Surety Federation 

          Opposition

          California State Association of Counties (to pre-amended  
          version) 


          League of California Cities (to pre-amended version)



          Analysis Prepared by:Thomas Clark / JUD. / (916) 319-2334









                                                                     AB 552


                                                                    Page  11