AB 626, as amended, Chiu. Public contracts: claim resolution.
Existing law prescribes various requirements regarding the formation, content, and enforcement of state and local public contracts. Existing law applicable to state public contracts generally requires that the resolution of claims related to those contracts be subject to arbitration. Existing law applicable to local agency contracts prescribes a process for the resolution of claims related to those contracts of $375,000 or less.
This bill would establish, for contracts entered into on or after January 1, 2017, a claim resolution process applicable to any claim by a contractor in connection with a public works project. The bill would define a claim as a separate demand by the contractor for one or more of the following: a time extension for relief from damages or penalties for delay, payment of money or damages arising from work done pursuant to the contract for a public work, or payment of an amount disputed by the public entity, as specified.
This bill would require a public entity, defined to exclude certain state entities, upon receipt of a claim sent by registered or certified mail, to review it and, within 45 days, provide a written statement identifying the disputed and undisputed portions of the claim. The bill would authorize the 45-day period to be extended by mutual agreement. The bill would require any payment due on an undisputed portion of the claim to be processed within 60 days, as specified. The bill would require that the claim be deemed rejected in its entirety if the public entity fails to issue the written statement.
This bill would authorize, if the claimant disputes the public entity’s written response or if the public entity fails to respond to a claim within the time prescribed, the claimant to demand to meet and confer for settlement of the issues in dispute. The bill would require any disputed portion of the claim that remains in dispute after the meet and confer conference to be subject to nonbinding mediation, as specified. The bill would provide that unpaid claim amounts accrue interest at 7% per annum. The bill would prescribe a procedure by which a subcontractor or lower tier contractor may make a claim through the contractor.
This bill would require the text of these provisions, or a summary, to be set forth in the plans or specifications for any public work which may give rise to a claim. The bill would specify that a waiver of these rights is void and contrary to public policy, except as specified. The bill would also specify that it does not impose liability on a public entity that makes loans or grants available through a competitive application process, for the failure of an awardee to meet its contractual obligations.
By increasing the duties of local agencies and officials, this bill would impose a state-mandated local program.
This bill would, on January 1, 2020, repeal the provision establishing the claim resolution process.
This bill would specify that these provisions constitute a matter of statewide concern.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that, if the Commission on State Mandates determines that the bill contains costs mandated by the state, reimbursement for those costs shall be made pursuant to these statutory provisions.
Vote: majority. Appropriation: no. Fiscal committee: yes. State-mandated local program: yes.
The people of the State of California do enact as follows:
Section 9204 is added to the Public Contract
2Code, to read:
(a) The Legislature finds and declares that it is in the
4best interests of the state and its citizens to ensure that all
5construction business performed on a public works project in the
6state that is complete and not in dispute is paid in full and in a
7timely manner.
8(b) Notwithstanding any other law, including, but not limited
9to, Article 7.1 (commencing with Section 10240) of Chapter 1 of
10Part 2, Chapter 10 (commencing with Section 19100) of Part 2,
11and Article 1.5 (commencing with Section 20104) of Chapter 1 of
12Part 3, this section shall apply to any claim by a contractor in
13connection with a public works project.
14(c) For purposes of this section:
15(1) “Claim” means a separate demand by a contractor sent by
16registered mail or certified mail with return receipt requested, for
17one or more of the following:
18(A) A time extension, including, without limitation, for relief
19from damages or penalties for delay assessed by a public entity
20under a contract for a public works project.
21(B) Payment by the public entity of money or damages arising
22from work done by, or on behalf of, the contractor pursuant to the
23contract for a public works project and payment for which is not
24otherwise expressly provided or to which the claimant is not
25otherwise entitled.
26(C) Payment of an amount that is disputed by the public entity.
27(2) “Contractor” means any type of contractor within the
28meaning of Chapter 9 (commencing with Section 7000) of Division
293 of the Business and Professions Code who has entered into a
30direct contract with a public entity for a public works project.
P4 1(3) (A) “Public entity” means, without limitation, except as
2provided in subparagraph (B), a state agency, department, office,
3division, bureau, board, or commission, the California State
4University, the University of California, a city, including a charter
5city, county, including a charter county, city and county, including
6a charter city and county, district, special district, public authority,
7political
subdivision, public corporation, or nonprofit transit
8corporation wholly owned by a public agency and formed to carry
9out the purposes of the public agency.
10(B) “Public entity” shall not include the following:
11(i) The Department of Water Resources as to any project under
12the jurisdiction of that department.
13(ii) The Department of Transportation as to any project under
14the jurisdiction of that department.
15(iii) The Department of Parks and Recreation as to any project
16under the jurisdiction of that department.
17(iv) The Department of Corrections and Rehabilitation with
18respect to any project under its
jurisdiction pursuant to Chapter 11
19(commencing with Section 7000) of Title 7 of Part 3 of the Penal
20Code.
21(v) The Military Department as to any project under the
22jurisdiction of that department.
23(vi) The Department of General Services as to all other projects.
24(vii) The High-Speed Rail Authority.
25(4) “Public works project” means the erection, construction,
26alteration, repair, or improvement of any public structure, building,
27road, or other public improvement of any kind.
28(5) “Subcontractor” means any type of contractor within the
29meaning of Chapter 9 (commencing with Section 7000) of Division
303
of the Business and Professions Code who either is in direct
31contract with a contractor or is a lower tier subcontractor.
32(d) (1) (A) Upon receipt of a claim pursuant to this section,
33the public entity to which the claim applies shall conduct a
34reasonable review of the claim and, within a period not to exceed
3545 days, shall provide the claimant a written statement identifying
36what portion of the claim is disputed and what portion is
37undisputed. Upon receipt of a claim, a public entity and a contractor
38may, by mutual agreement, extend the time period provided in this
39subdivision.
P5 1(B) The claimant shall furnish reasonable documentation to
2support the claim.
3(C) If the public
entity needs approval from its governing body
4to provide the claimant a written statement identifying the disputed
5portion and the undisputed portion of the claim, and the governing
6body does not meet within the 45 days or within the mutually
7agreed to extension of time following receipt of a claim sent by
8registered mail or certified mail, return receipt requested, the public
9entity shall have up to three days following the next duly publicly
10noticed meeting of the governing body after the 45-day period, or
11extension, expires to provide the claimant a written statement
12identifying the disputed portion and the undisputed portion.
13(D) Any payment due on an undisputed portion of the claim
14shall be processed and made within 60 days after the public entity
15issues its written statement. If the public entity fails to issue a
16written
statement, paragraph (3) shall apply.
17(2) (A) If the claimant disputes the public entity’s written
18response, or if the public entity fails to respond to a claim issued
19pursuant to this section within the time prescribed, the claimant
20may demand in writing an informal conference to meet and confer
21for settlement of the issues in dispute. Upon receipt of a demand
22in writing sent by registered mail or certified mail, return receipt
23requested, the public entity shall schedule a meet and confer
24conference within 30 days for settlement of the dispute.
25(B) Within 10 business days following the conclusion of the
26meet and confer conference, if the claim or any portion of the claim
27remains in dispute, the public entity shall provide the claimant a
28written statement
identifying the portion of the claim that remains
29in dispute and the portion that is undisputed. Any payment due on
30an undisputed portion of the claim shall be processed and made
31within 60 days after the public entity issues its written statement.
32Any disputed portion of the claim, as identified by the contractor
33in writing, shall be submitted to nonbinding mediation, with the
34public entity and the claimant sharing the associated costs equally.
35The public entity and claimant shall mutually agree to a mediator
36within 10 business days after the disputed portion of the claim has
37been identified in writing. If the parties cannot agree upon a
38mediator, each party shall select a mediator and those mediators
39shall select a qualified neutral third party to mediate with regard
40to the disputed portion of the claim. Each party shall bear the fees
P6 1and costs charged by its respective mediator in connection with
2the
selection of the neutral mediator. If mediation is unsuccessful,
3the parts of the claim remaining in dispute shall be subject to
4applicable procedures outside this section.
5(C) For purposes of this section, mediation includes any
6nonbinding process, including, but not limited to, neutral evaluation
7or a dispute review board, in which an independent third party or
8board assists the parties in dispute resolution through negotiation
9or by issuance of an evaluation. Any mediation utilized shall
10conform to the timeframes in this section.
11(D) Unless otherwise agreed to by the public entity and the
12contractor in writing, the mediation conducted pursuant to this
13section shall excuse any further obligation under Section 20104.4
14to mediate after litigation has been commenced.
15(E) This section does not preclude a public entity from requiring
16arbitration of disputes under private arbitration or the Public Works
17Contract Arbitration Program, if mediation under this section does
18not resolve the parties’ dispute.
19(3) Failure by the public entity to respond to a claim from a
20contractor within the time periods described in this subdivision or
21to otherwise meet the time requirements of this section shall result
22in the claim being deemed rejected in its entirety. A claim that is
23denied by reason of the public entity’s failure to have responded
24to a claim, or its failure to otherwise meet the time requirements
25of this section, shall not constitute an adverse finding with regard
26to the merits of the claim or the responsibility or qualifications of
27the claimant.
28(4) Amounts not paid in a timely manner as required by this
29section shall bear interest at 7 percent per annum.
30(5) If a subcontractor or a lower tier subcontractor lacks legal
31standing to assert a claim against a public entity because privity
32of contract does not exist, the contractor may present to the public
33entity a claim on behalf of a subcontractor or lower tier
34subcontractor. A subcontractor may request in writing, either on
35his or her own behalf or on behalf of a lower tier subcontractor,
36that the contractor present a claim for work which was performed
37by the subcontractor or by a lower tier subcontractor on behalf of
38the subcontractor. The subcontractor requesting that the claim be
39presented to the public entity shall furnish reasonable
40documentation to support the claim.
Within 45 days of receipt of
P7 1this written request, the contractor shall notify the subcontractor
2in writing as to whether the contractor presented the claim to the
3public entity and, if the original contractor did not present the
4claim, provide the subcontractor with a statement of the reasons
5for not having done so.
6(e) The text of this section or a summary of it shall be set forth
7in the plans or specifications for any public works project that may
8give rise to a claim under this section.
9(f) A waiver of the rights granted by this section is void and
10contrary to public policy, provided, however, that (1) upon receipt
11of a claim, the parties may mutually agree to waive, in writing,
12mediation and proceed directly to the commencement of a civil
13action or binding arbitration, as
applicable; and (2) a public entity
14
begin delete in its public works contracts may include dispute resolution begin insert may prescribe reasonable change order, claim, and dispute
15provisions that comply with this section, including the timeframes
16set forth herein, and that prescribe additional reasonable and
17equitable terms regarding actions or procedures to be taken by the
18parties.end delete
19resolution procedures and requirements in addition to the
20provisions of this section, so long as the contractual provisions
21do not conflict with or otherwise impair the timeframes and
22procedures set forth in this section.end insert
23(g) This section applies to contracts entered into on or after
24January 1, 2017.
25(h) Nothing in this section shall impose liability upon a public
26entity that makes loans or grants available through a competitive
27application process, for the failure of an awardee to meet its
28contractual obligations.
29(i) This section shall remain in effect only until January 1, 2020,
30and as of that date is repealed, unless a later enacted statute, that
31is enacted before January 1, 2020, deletes or extends that date.
The Legislature finds and declares that it is of statewide
33concern to require a charter city, charter county, or charter city
34and county to follow a prescribed claims resolution process to
35ensure there are uniform and equitable procurement practices.
If the Commission on State Mandates determines that
37this act contains costs mandated by the state, reimbursement to
38local agencies and school districts for those costs shall be made
P8 1pursuant to Part 7 (commencing with Section 17500) of Division
24 of Title 2 of the Government Code.
O
94