BILL ANALYSIS                                                                                                                                                                                                    Ó



                             SENATE JUDICIARY COMMITTEE
                         Senator Hannah-Beth Jackson, Chair
                             2015-2016  Regular  Session


          AB 626 (Chiu)
          Version: June 8, 2016
          Hearing Date:  June 28, 2016
          Fiscal: Yes
          Urgency: No
          me   


                                        SUBJECT
                                           
                         Public contracts:  claim resolution

                                      DESCRIPTION  

          This bill, until January 1, 2020, would establish, for public  
          works contracts entered into on or after January 1, 2017, a  
          claim resolution procedure by which a general contractor can  
          seek public agency review of the claim.  This bill would also  
          prescribe a procedure by which a subcontractor or lower tier  
          contractor may make a claim against the public agency through  
          the general contractor.

                                      BACKGROUND  


          In general, public works refers to construction, alteration,  
          demolition, installation, or repair work (including maintenance)  
          of any public structure, building, road, or other improvement  
          done under contract and paid by public funds, or if private  
          funds are used, more than 50 percent of the square footage is  
          leased to a public entity.  Because of this, there are laws  
          regarding many aspects of the construction projects to protect  
          the public's interest.  Public works projects do not include  
          those done by a public agency with its own employees.



          On public works projects, a public agency contracts with a  
          general contractor, who has submitted a bid or estimated cost to  
          provide the materials and services for the construction,  
          alteration, demolition, installation, or repair work.  At times,  
          the cost of the materials and services is more than the general  
          contractor's bid due to changes in the project, which may be  
          attributed to inaccurate or incomplete project plans and  







          AB 626 (Chiu)
          Page 2 of ? 


          specifications, the public agency orders extra work to be  
          performed, or unexpected difficulties arise.  These increases in  
          costs may be submitted to the public agency for payment.   
          Typically, unless a change order is issued by the public agency  
          or its legislative body or appropriate department approving the  
          increase in cost, the general contractor, who may not be  
          responsible for the underlying cause of the increase in costs  
          but has accrued the expense for the sake of completing the  
          project, will be unable to resolve a claim dispute outside of  
          arbitration or civil action.  Further, a subcontractor, who has  
          performed additional services or provided materials outside the  
          scope of the original contract with the general contractor but  
          necessary to the completion of the project, may be seeking  
          payment from the public agency.  Delays in payment for the extra  
          work provided by the contractor or subcontractor may place the  
          contractor or subcontractor at financial risk with their  
          employees or continued work on the public work.  Additionally,  
          the failure of the public agency to issue a change order or the  
          denial of claims has resulted in costly litigation for the  
          public agency, contractors, and subcontractors.  Multiple  
          legislative attempts to address pre-litigation claim disputes  
          have failed.



          Existing law authorizes state agencies to arbitrate claim  
          disputes, while local agencies are subject to a different claims  
          resolution process.  Subcontractors must rely on submitting  
          their claims for payment through the general contractor or other  
          subcontractor through which they have contracted for services or  
          materials to be provided on the public works project.  However,  
          depending upon the general contractor and its desire, on one  
          hand, to help the subcontractor get paid, or, on the other hand,  
          to maintain positive relations with the public agency, the  
          subcontractor may or may not receive an answer from the general  
          contractor as to whether the claim was submitted to the public  
          agency.



          This bill seeks to provide a simplified, cost-effective claims  
          resolution procedure to resolve contractor claims prior to  
          arbitration or civil action.  This bill would also provide a  
          clear process for a subcontractor to submit claims through a  








          AB 626 (Chiu)
          Page 3 of ? 


          general contractor in order to provide the subcontractor with  
          information as to whether the general contractor has rejected  
          the request to submit the subcontractor's claim to the public  
          agency.

                                CHANGES TO EXISTING LAW
           
           Existing law  prohibits a local public entity, charter city, or  
          charter county from requiring a bidder (i.e., general  
          contractor) to assume responsibility for the completeness and  
          accuracy of architectural or engineering plans and  
          specifications on public works projects, except on clearly  
          designated design build projects.  (Pub. Contract Code Sec.  
          1104.)  However, the local public entity, charter city, or  
          charter county may require a bidder to review architectural or  
          engineering plans and specifications prior to submission of a  
          bid, and report any errors and omissions noted by the contractor  
          to the architect or owner.  (Id.)  The review by the contractor  
          shall be confined to the contractor's capacity as a contractor,  
          and not as a licensed design professional.  (Id.)

           Existing law  , prior to the commencement of the public work  
          costing more than $15,000, other than maintenance work or work  
          occasioned by emergency, requires the engineer to prepare and  
          file in his office either full, complete and accurate plans and  
          specifications or a work authorization approved by the engineer  
          describing the work to be performed, and an estimate of the cost  
          thereof, except where other and adequate provision is made by  
          law requiring the preparation and filing of such plans,  
          specifications and estimates of cost by some other officer or in  
          some other office.  (Gov. Code Sec. 4004.)
          
           Existing law  requires any public works contract of a local  
          public entity which involves digging trenches or other  
          excavations that extend deeper than four feet below the surface  
          to contain a clause which provides the following:
           that the contractor shall promptly, and before the following  
            conditions are disturbed, notify the local public entity, in  
            writing, of any material that may be hazardous waste, as  
            specified, subsurface or latent physical conditions at the  
            site differing from those indicated by information about the  
            site made available to bidders prior to the deadline for  
            submitting bids, and unknown physical conditions at the site  
            of any unusual nature, different materially from those  








          AB 626 (Chiu)
          Page 4 of ? 


            ordinarily encountered and generally recognized as inherent in  
            work of the character provided for in the contract;
           that the local public entity shall promptly investigate the  
            conditions, and if it finds that the conditions do materially  
            so differ, or do involve hazardous waste, and cause a decrease  
            or increase in the contractor's cost of, or the time required  
            for, performance of any part of the work shall issue a change  
            order under the procedures described in the contract; and
           that, in the event that a dispute arises between the local  
            public entity and the contractor whether the conditions  
            materially differ, or involve hazardous waste, or cause a  
            decrease or increase in the contractor's cost of, or time  
            required for, performance of any part of the work, the  
            contractor shall not be excused from any scheduled completion  
            date provided for by the contract, but shall proceed with all  
            work to be performed under the contract.  (Pub. Contract Code  
            Sec. 7104.)

           Existing law  provides that the contractor retains any and all  
          rights provided either by contract or by law which pertain to  
          the resolution of disputes and protests between the contracting  
          parties.  (Pub. Contract Code Sec. 7104.)
          
           Existing law  prohibits a public agency, including the state, the  
          Regents of the University of California, a city, county,  
          district, public authority, public agency, municipal utility,  
          and any other political subdivision or public corporation of the  
          state, from requiring the contractor to be responsible for the  
          cost of repairing or restoring damage to the work, which damage  
          is determined to have been proximately caused by an act of God  
          (earthquakes in excess of a magnitude of 3.5 on the Richter  
          Scale and tidal waves) in excess of 5 percent of the contracted  
          amount, provided, that the work damaged is built in accordance  
          with accepted and applicable building standards and the plans  
          and specifications of the awarding authority.  (Pub. Contract  
          Code Sec. 7105(a).)
           
          Existing law  authorizes public agencies to make changes in  
          construction contracts for public improvements in the course of  
          construction to bring the completed improvements into compliance  
          with environmental requirements or standards established by  
          state and federal statutes and regulations enacted after the  
          contract has been awarded or entered into.  The contractor is  
          required to be paid for the changes in accordance with the  








          AB 626 (Chiu)
          Page 5 of ? 


          provisions of the contract governing payment for changes in the  
          work or, if no provisions are set forth in the contract, payment  
          shall be as agreed to by the parties.  (Pub. Contract Code Sec.  
          7105(c).)

           Existing law  provides that where authority to contract is vested  
          in any public agency, excluding the state, the authority  
          includes the power, by mutual consent of the contracting  
          parties, to terminate, amend, or modify any contract within the  
          scope of such authority.  (Pub. Contract Code Sec. 7105(d).)   
          However, this provision does not apply to contracts entered into  
          pursuant to any statute expressly requiring that contracts be  
          let or awarded on the basis of competitive bids.  (Id.)   
          Contracts of public agencies, excluding the state, required to  
          be let or awarded on the basis of competitive bids pursuant to  
          any statute may be terminated, amended, or modified only if the  
          termination, amendment, or modification is so provided in the  
          contract or is authorized under provision of law.  (Id.)

           Existing law  provides that the compensation payable, if any, for  
          amendments and modifications shall be determined as provided in  
          the contract, and the compensation payable, if any, in the event  
          the contract is so terminated shall be determined as provided in  
          the contract or applicable statutory provision providing for the  
          termination.  (Pub. Contract Code Sec. 7105(d).)

           Existing law , except as otherwise provided, prohibits a suit for  
          money or damages against a public entity on a cause of action  
          for which a claim is required to be presented until a written  
          claim therefor has been presented to the public entity and has  
          been acted upon by the board, or has been deemed to have been  
          rejected by the board.  (Gov. Code Sec. 945.4.)

           Existing law  prescribes a contract claims resolution process for  
          contracts entered into with a state agency.  (Pub. Contract Code  
          Sec. 10240 et seq.)

           Existing law  requires arbitration of a claim, defined to mean a  
          demand for monetary compensation or damages, arising under or  
          relating to the performance of contracts with a state agency.   
          (Pub. Contract Code Sec. 10240.)

          Existing law  authorizes a claimant to initiate arbitration no  
          later than 90 days after the date of personal or mail service on  








          AB 626 (Chiu)
          Page 6 of ? 


          the claimant of the final written decision by the appropriate  
          public agency department on the claim; however, this limitation  
          does not apply to any claim founded on any cost audit, latent  
          defect, warranty, or guarantee under the contract.  (Pub.  
          Contract Code Sec. 10240.1.)

           Existing law  prohibits arbitration until the claimant pursues  
          diligently and exhausts, as to the claim, the required  
          administrative procedures set forth in the contract under which  
          the claim arose, unless more than 240 days have elapsed since  
          acceptance of the work by the department.  (Pub. Contract Code  
          Sec. 10240.2.)
           Existing law  provides that unless otherwise agreed by the  
          parties, the arbitration shall be conducted by a single  
          arbitrator selected by the parties from the certified list  
          created by the Public Works Contract Arbitration Committee.  
          (Pub. Contract Code Sec. 10240.3.)  If the parties cannot agree  
          on the arbitrator, either party may petition the superior court  
          to appoint one from the panel of arbitrators certified by the  
          Public Works Contract Arbitration Committee.  (Id.)

           Existing law  specifies that no decision made by a department  
          shall be conclusive on any issue in the arbitration.  (Pub.  
          Contract Code Sec. 10240.4.)

           Existing law  requires the Departments of General Services,  
          Transportation, and Water Resources to jointly adopt and may,  
          from time to time, modify, revise, or repeal uniform regulations  
          to implement arbitration provisions and may include, but need  
          not be limited to:
           the method of initiating arbitration;
           the place of hearing based upon the convenience of the  
            parties;
           procedures for the selection of a neutral arbitrator;
           the form and content of any pleading;
           procedure for conducting hearings;
           the providing of experts to assist the arbitrator in the event  
            the assistance is needed;
           the content of the award; and
           simplified procedures for claims of fifty thousand dollars  
            ($50,000) or less.  (Pub. Contract Code Sec. 10240.5.)

           Existing law  authorizes a party to the contract to join in the  
          arbitration as a party, any supplier, subcontractor, design  








          AB 626 (Chiu)
          Page 7 of ? 


          professional, surety, or other person who has so agreed and if  
          the joinder is necessary to prevent a substantial risk of the  
          party otherwise being subjected to inconsistent obligations or  
          decisions.  (Pub. Contract Code Sec. 10240.9.)

           Existing law  does not prevent the parties to the contract, after  
          the claim has arisen, from mutually agreeing in writing to waive  
          the arbitration statutes and to have the claim litigated in a  
          court of competent jurisdiction.  (Pub. Contract Code Sec.  
          10240.10.)

           Existing law  , within the applicable time periods and upon  
          specified grounds, authorizes a party to petition the court to  
          confirm, correct, or vacate the award rendered by the  
          arbitrator; however, no department may petition to vacate an  
          award without the prior written authorization of its agency  
          secretary.  (Pub. Contract Code Sec. 10240.12.)  Except where  
          the parties agree not to have the arbitration decision rendered  
          as specified, a court shall vacate the award, or part thereof,  
          if it determines either that the award, or part thereof, is not  
          supported by substantial evidence or that it is not decided  
          under or in accordance with the laws of this state, in which  
          case, the court may order a rehearing before the original  
          arbitrator or remand to the original arbitrator that portion of  
          the dispute which the court concludes the arbitrator failed to  
          determine.  (Id.)

           Existing law  provides that the costs of conducting the  
          arbitration shall be borne equally by the parties, but the  
          arbitrator may allow the prevailing party to recover its costs  
          and necessary disbursements, with interest, other than  
          attorney's fees, on the same basis as is allowed in civil  
          actions.  (Pub. Contract Code Sec. 10240.13.)
           
          Existing law  provides a public entity with full authority to  
          compromise or otherwise settle any claim relating to a contract  
          at any time.  (Pub. Contract Code Sec. 9201(a).)  The public  
          entity is required to include provisions in a public works  
          contract for timely notification of the contractor of the  
          receipt of any third-party claim relating to the contract.   
          (Pub. Contract Code Sec. 9201(b).)
          
           This bill  would preclude, until January 1, 2020, any other claim  
          resolution provision and apply to all claims by contractors in  








          AB 626 (Chiu)
          Page 8 of ? 


          connection with public works.

           This bill  would provide the following definitions:
           "claim" means a separate demand by a contractor by registered  
            mail or certified mail with return receipt requested,  for one  
            or more of the following: (a) a time extension, including,  
            without limitation, for relief from damages or penalties for  
            delay assessed by a public entity under a contract for a  
            public works project; (b) payment by the public entity of  
            money or damages or penalties arising from work done by, or on  
            behalf of, the contractor pursuant to the contract for a  
            public works project and payment for which is not otherwise  
            expressly provided or to which the claimant is not otherwise  
            entitled; or (c) payment of an amount that is disputed by the  
            public entity;
           "contractor" means any type of contractor subject to the  
            Contractor's State License Law who has entered into a direct  
            contract with a public entity for a public works project;
           "public entity" means, without limitation, a state agency,  
            department, office, division, bureau, board, or commission,  
            the California State University, the University of California,  
            a city, including a charter city, county, including a charter  
            county, city and county, including a charter city and county,  
            district, special district, public authority, political  
            subdivision, public corporation, or nonprofit transit  
            corporation wholly owned by a public agency and formed to  
            carry out the purposes of the public agency;
           "public entity" shall not include the Department of Water  
            Resources as to any project under the jurisdiction of that  
            department, the Department of Transportation as to any project  
            under the jurisdiction of that department; the Department of  
            Parks and Recreation as to any project under the jurisdiction  
            of that department, the Department of Corrections and  
            Rehabilitation, as specified, the Military Department as to  
            any project under the jurisdiction of that department, the  
            Department of General Services as to all other projects, and  
            the High-Speed Rail Authority;
           "public works project" means the erection, construction,  
            alteration, repair, or improvement of any public structure,  
            building, road, or other public improvement of any kind; and
           "subcontractor" means any type of contractor subject to the  
            Contractor's State License Law who either is in direct  
            contract with a contractor or is a lower tier subcontractor.









          AB 626 (Chiu)
          Page 9 of ? 


           This bill  , upon receipt of a claim, would require the public  
          entity to which the claim applies to conduct a reasonable review  
          of the claim and, within a period not to exceed 45 days, provide  
          the claimant a written statement identifying what portion of the  
          claim is disputed and what portion is undisputed.  However, a  
          public entity and a contractor may, by mutual agreement, extend  
          the time period.

           This bill  would require the claimant to furnish reasonable  
          documentation to support the claim.

           This bill  , if the public entity needs approval from its  
          governing body to provide the claimant a written statement  
          identifying the disputed portion and the undisputed portion of  
          the claim, and the governing body does not meet within the 45  
          days following receipt of a claim sent by registered mail, would  
          provide the public entity up to three days following the next  
          duly publicly noticed meeting of the governing body after the 45  
          day period, or extension expires to provide the claimant a  
          written statement identifying the disputed portion and the  
          undisputed portion.

           This bill  would require any payment due on an undisputed portion  
          of the claim to be processed and made within 60 days after the  
          public entity issues its written statement; if the public entity  
          fails to issue a written statement, the claim would be deemed  
          rejected in its entirety.

           This bill  , if the claimant disputes the public entity's written  
          response, or if the public entity fails to respond to a claim  
          issued within the time prescribed, would authorize the claimant  
          to demand in writing an informal conference to meet and confer  
          for settlement of the issues in dispute, and, upon receipt of a  
          demand in writing sent by registered mail or certified mail,  
          return receipt requested, , the public entity would be required  
          to schedule a meet and confer conference within 30 days for  
          settlement of the dispute.

           This bill  , within 10 business days following the conclusion of  
          the meet and confer conference, if the claim or any portion of  
          the claim remains in dispute, would require the public entity to  
          provide the claimant a written statement identifying the portion  
          of the claim that remains in dispute and the portion that is  
          undisputed. 








          AB 626 (Chiu)
          Page 10 of ? 



          This bill  would require any payment due on an undisputed portion  
          of the claim to be processed and made within 60 days after the  
          public entity issues its written statement, and any disputed  
          portion of the claim, as identified by the contractor in  
          writing, would be required to be submitted to nonbinding  
          mediation, with the public entity and the claimant sharing the  
          associated costs equally. 

           This bill  would require the public entity and claimant to  
          mutually agree to a mediator within 10 business days after the  
          disputed portion of the claim has been identified in writing,  
          and, if the parties cannot agree upon a mediator, each party  
          would select a mediator and those mediators would select a  
          qualified neutral third party to mediate with regard to the  
          disputed portion of the claim. 

           This bill  would provide that if the parties cannot agree upon a  
          mediator, each party shall select a mediator and those mediators  
          shall select a qualified neutral third party to mediate with  
          regard to the disputed portion of the claim, and each party  
          shall bear the fees and costs charged by their respective  
          mediators in selecting the neutral mediator.

           This bill  would provide that if mediation is unsuccessful, the  
          parts of the claim remaining in dispute would be subject to  
          other applicable claim resolution procedures.

           This bill  would specify that mediation includes any nonbinding  
          process, including, but not limited to,  neutral evaluation or a  
          dispute review board, in which an independent third party or  
          board assists the parties in dispute resolution through  
          negotiation or by issuance of an evaluation, and any mediation  
          utilized must conform to the time frames provided in this bill.
                                                         
           This bill  would require the mediation conducted pursuant to this  
          bill to excuse any further obligation under Section 20104.4 to  
          mediate (meet and confer) after litigation has been commenced,  
          unless otherwise agreed to by the public entity and the  
          contractor in writing.

           This bill  would not preclude a public entity from requiring  
          arbitration of disputes under private arbitration or the Public  
          Works Contract Arbitration Program, if under this bill,  








          AB 626 (Chiu)
          Page 11 of ? 


          mediation does not resolve the parties' dispute.

           This bill  would specify that failure by the public entity to  
          respond to a claim from a contractor within the time periods  
          described in this bill or to otherwise meet the time  
          requirements of this bill would result in the claim being deemed  
          rejected in its entirety.

           This bill  would provide that a claim that is denied by reason of  
          the public entity's failure to have responded to a claim or its  
          failure to otherwise meet the time requirements of this section,  
          shall not constitute an adverse finding with regard to the   
          merits of the claim or the responsibility or qualifications of  
          the claims.

           This bill  would require amounts not paid in a timely manner to  
          bear interest at 7 percent per annum.

           This bill  , if a subcontractor or a lower tier subcontractor  
          lacks legal standing to assert a claim against a public entity  
          because privity of contract does not exist, would authorize the  
          contractor to present to the public entity a claim on behalf of  
          a subcontractor or lower tier subcontractor. 
           This bill  would authorize a subcontractor to request in writing,  
          either on his or her own behalf or on behalf of a lower tier  
          subcontractor, that the contractor present a claim for work  
          which was performed by the subcontractor or by a lower tier  
          subcontractor on behalf of the subcontractor. 

           This bill  would require the subcontractor requesting that the  
          claim be presented to the public entity to furnish reasonable  
          documentation to support the claim. 

           This bill  , within 45 days of receipt of that written request,  
          would require the contractor to notify the subcontractor in  
          writing as to whether the contractor presented the claim to the  
          public entity and, if the original contractor did not present  
          the claim, provide the subcontractor with a statement of the  
          reasons for not having done so. 

           This bill  would require the text of the provisions provided  
          under this bill or a summary of it to be set forth in the plans  
          or specifications for any public works project that may give  
          rise to a claim under this bill.








          AB 626 (Chiu)
          Page 12 of ? 



           This bill  would make a waiver of the rights granted by this bill  
          void and contrary to public policy, provided, however, that upon  
          receipt of a claim, the parties may mutually agree to waive, in  
          writing, mediation and proceed directly to the commencement of a  
          civil action or binding arbitration as applicable; and (2) a  
          public entity in its public works contracts may include dispute  
          resolution provisions that comply with this section, including  
          timeframes set forth herein, and that prescribe additional  
          reasonable and equitable terms regarding actions or procedures  
          to be taken by the parties.  . 

           This bill  would apply to contracts entered into on or after  
          January 1, 2017. 

           This bill  would find and declare that it is in the best  
          interests of the state and its citizens to ensure that all  
          construction business performed on a public works project  in  
          the state that is complete and not in dispute is paid in full  
          and in a timely manner, and that it is of statewide concern to  
          require a charter city, charter county, or charter city and  
          county to follow a prescribed claims resolution process to  
          ensure they are uniform and equitable procurement practices.

           This bill  would provide that nothing in this bill shall impose  
          liability upon a public entity that makes loans or grants  
          available through a competitive application process, for the  
          failure of an awardee to meet its contractual obligations.  

           This bill  provides that the provisions sunset on January 1,  
          2020.





                                        COMMENT
           

          1. Stated need for the bill  

          The author writes:

             This bill closes an unfair loophole in the law that allows  








          AB 626 (Chiu)
          Page 13 of ? 


             agencies to indefinitely delay payments to contractors for  
             money owed to them. This is a particular threat to small  
             businesses and minority owned businesses in our state. 
              
             There is no law in place requiring agencies to pay claims,  
             in a timely manner, made by contractors for extra work  
             performed and approved by the agency, even when the public  
             agency acknowledges that it owes the contractor for work  
             performed.  This places contractors and their workers in  
             difficult financial circumstances. 
              
             Furthermore, there is a lack in uniformity for disputing a  
             claim.  In many cases, some public agencies have no  
             requirements to respond to a claim or respond to a claim  
             in a timely manner.  The breakdown of communication  
             between the public agency and the contractor adds to the  
             burden on the contractor and meeting their payroll  
             obligations. 
              
             AB 626, a bill very similar to AB 1347 of 2015, which  
             passed out of this committee unanimously, creates a  
             process that requires agencies to respond to a  
             contractor's claim, to pay out portions of the work they  
             acknowledge and agree they owe the contractor, and to  
             resolve disputed portions of payment through non-binding  
             mediation.
              
             Specifically, the bill would require a public agency to  
             respond in 45 days to a claim. If the public agency does  
             not respond within 45 days then the claim is deemed  
             denied. If the contractor wishes to continue the claim,  
             then the contractor must respond via registered mail. The  
             public agency then has 30 days to meet & confer with the  
             contractor.

             If there is no agreement with the claim during the meet  
             and confer process, if requested by the contractor, again  
             via registered mail, then the public agency and contractor  
             has 10 days to find a mutually agreed upon mediator and  
             set a mediation date.  If mediation doesn't settle the  
             claim, then current practice takes over, which is a civil  
             lawsuit and what this bill is attempting to avoid.   
             Nothing in this measure requires an agency to pay for work  
             they do not approve or agree with.








          AB 626 (Chiu)
          Page 14 of ? 


              
             Many public agencies have removed their opposition as we  
             have worked diligently to address their concerns and  
             establish a fair and equitable process.

             To address the Governor's veto [of AB 1347 (Chiu, 2015)],  
             the bill removes California state agencies from the  
             requirements of AB 626.  

          2.  Public works contracts and change orders  

          Change orders are at the heart of the controversy involving this  
          bill.  When a public work requires extra work unanticipated by  
          the contractor, a change order may be necessary, signed by the  
          public agency and the contractor, to amend the contract to  
          provide that the contractor is performing additional work for  
          which the public agency will pay.  When a change order is not  
          executed by the public agency, or its governing body or  
          responsible department, the contractor, having provided the  
          necessary extra work or materials, submits a claim to the public  
          agency alleging the public agency owes the contractor payment  
          for the extra work.

          Several cases provide the responsibilities of the contracting  
          parties that emerge when a public work requires additional  
          material or services than originally expected by the contractor.  
           First, case law has established that "a contractor that has  
          agreed to a particular performance at a specified price may not  
          avoid its contractual obligations or seek additional  
          compensation for performing them because unanticipated  
          difficulties are encountered."  (United States v. Spearin (1918)  
          248 U.S. 132, 136.)  However, case law has also settled that a  
          "contractor of public works who, acting reasonably, is misled by  
          incorrect plans and specifications issued by the public  
          authorities as the basis for bids and who, as a result, submits  
          a bid which is lower than he would have otherwise made may  
          recover in a contract action for extra work or expenses  
          necessitated by the conditions being other than as represented."  
           (Suiza & McCue Constr. Co. v. Superior Court (1962) 57 Cal.2d  
          508, 510.)  Although Public Contract Code Section 7104 requires  
          change orders related to unanticipated difficulties from site  
          conditions to be included in public work contracts, there is no  
          statute requiring change orders resulting from other kinds of  
          unanticipated conditions to be included in public work  








          AB 626 (Chiu)
          Page 15 of ? 


          contracts.  Specifically, case law has established that there  
          are two types of differing site conditions that a public entity  
          cannot circumvent or otherwise disclaim liability for through  
          other provisions in the contract:  (1) Type 1 differing site  
          conditions, in which the actual site conditions differ from  
          those originally described to bidders; and (2) Type 2 differing  
          site conditions, in which the actual site conditions differ from  
          the conditions ordinarily encountered in the particular type of  
          work in the particular locality.  (Condon-Johnson & Associates  
          v. Sacramento Municipal Utility District (2007) 149 Cal.App.4th  
          1384.)  For other unanticipated difficulties not associated with  
          the site conditions for which a change order is not executed,  
          the contractor is left to file a claim for the work performed.

          3.  Providing informal procedures to submit claims to public  
            agency  

          Existing law prescribes various requirements regarding the  
          formation, content, and enforcement of state and local public  
          contracts.  Existing law applicable to state public contracts  
          generally requires that the resolution of claims related to  
          those contracts be subject to arbitration.  Existing law for  
          local agency public works requires all claims made for work  
          arising out of the contract, but not expressly provided for in  
          that contract, that are $375,000 or less to first be resolved  
          through administrative resolution procedures.  However, if the  
          contract provides for arbitration, the claim will have to be  
          arbitrated according to express arbitration statutes.  The  
          arbitration statutes apply to both local agency and state agency  
          public work contracts.  

          This bill would prescribe a new claims resolution process by  
          which a contractor can submit a claim to a public entity as  
          follows:
           applies to all claims submitted by a contractor to a public  
            entity, as specified;
           the contractor must furnish reasonable documentation to  
            support the claim;
           the public entity must conduct a reasonable review of the  
            claim and, within 45 days, provide the contractor with a  
            written statement identifying what portion of the claim is  
            disputed and what portion is undisputed;
           the time frame may be extended by mutual agreement or if the  
            public entity needs approval from its governing body to  








          AB 626 (Chiu)
          Page 16 of ? 


            provide the claimant a written statement identifying the  
            disputed portion and the undisputed portion of the claim, then  
            the public entity may have additional time, as specified;
           any payment due on an undisputed portion of the claim must be  
            processed and made within 60 days of issuance of the written  
            statement;
           if no statement is issued by the public agency, the claim is  
            rejected in its entirety;
           the claimant may demand an informal meet-and-confer conference  
            for settlement of the issues in dispute, as specified,; and
           establishes time frames for payment of settled claims and  
            provide for nonbinding mediation for disputed claims.

          Proponents of this bill state that existing laws protect public  
          agencies from having to pay any unfair or unjust claims made by  
          a contractor.  However, proponents argue, these conflict  
          resolution statutes do not require the public agency to pay  
          contractors in a timely manner for extra work performed on  
          public works contracts, even when that work was requested by the  
          owner and subsequently performed by the contract in good faith.   
          Proponents contend that "contractors who perform extra work put  
          themselves in great financial risk.  California public works  
          contractors often have to wait months, and in some cases up to  
          years, for payment for work.  Contractors who perform this work  
          to the benefit of the public agency must still pay for their  
          construction materials, employee wages and benefits and their  
          overhead.  Not being compensated in a timely manner can result  
          in a contractor being forced to reduce capacity, or worse, close  
          their business."

          Proponents contend that this bill would put a process in place  
          that requires public agencies to respond to a contractor claim,  
          would require the agency to pay out portions of the work they  
          acknowledge or agree they owe to the contractor, and implements  
          a fair process for resolving any disputed portions of the claim.  
           The proponents note that this bill does not require public  
          agencies to pay for any work it does not request, accept, or  
          approve but allows the public agency to deny or dispute any  
          claim for payment.  Yet, the delay of trust fund contributions  
          with respect to trade unions can cause the loss of health  
          insurance due to a contractor's inability to make payments, and  
          the lack of prompt payment for extra work leaves many  
          contractors without the necessary resources needed to bid the  
          next project and continue doing business, which ultimately  








          AB 626 (Chiu)
          Page 17 of ? 


          diminishes work opportunities.

          4.  Providing clarity for subcontractor pass-through claims  

          On public work projects, the public entity typically contracts  
          directly with a general contractor to perform the work.  The  
          general contractor then contracts with subcontractors, such as  
          roofers, excavators, and plumbers, who perform specialized work  
          on the project.  In this way, a subcontractor does not have a  
          direct contract with the public agency and therefore lacks  
          privity of contract.  Accordingly, the subcontractor seeking  
          payment on extra work performed must rely on one of a few  
          methods for payment.

          First, the subcontractor may attempt to recover payment from the  
          general contractor.  However, depending upon the public agency's  
          position on which party is responsible for the extra work needed  
          to continue or complete the project, the public agency may have  
          failed to pay the general contractor for extra work, and the  
          general contractor may be unable to pay the subcontractor for  
          the extra work.

          Second, the subcontractor may submit a stop notice to the public  
          entity to withhold a portion of the construction funds  
          sufficient to satisfy the subcontractor's claim. Rather than  
          attaching to real property, the stop notice attaches to the  
          construction loan fund, or to money in the hands of the public  
          entity that otherwise is to be paid to the general contractor.   
          The stop notice has the effect of intercepting these funds, and  
          the ultimate result of the enforcement of a stop notice is entry  
          of a judgment against the public agency for the amount claimed  
          in the stop notice.  This procedure is not preferred as it does  
          not provide payment to the subcontractor in a timely fashion.   
          As discussed above, a subcontractor who is unable to recover  
          payment for work or materials provided in a good faith effort to  
          keep the public project moving forward or reaching completion  
          puts himself or herself at risk if the payment is necessary to  
          pay employees, purchase materials, or bid on other contracts.

          Another method for recovering payment is to request the claim be  
          presented to the public agency through the general contractor,  
          known as a "pass-through" claim.  Case law provides that "[a]s a  
          matter of law, a general contractor can present a  
          subcontractor's claim on a pass-through basis.  (Maurice L.  








          AB 626 (Chiu)
          Page 18 of ? 


          Bein, Inc. v. Housing Authority (1958) 157 Cal.App.2d 670. . .  
          .)  When a public agency breaches a construction contract with a  
          contractor, damage often ensues to a subcontractor.  In such a  
          situation, the subcontractor may not have legal standing to  
          assert a claim directly against the public agency due to a lack  
          of privity of contract, but may assert a claim directly against  
          the general contractor.  In such a case, a general contractor is  
          permitted to present a pass-through claim on behalf of the  
          subcontractor against the public agency.  (Citation omitted.)"   
          (Howard Contracting, Inc. v. G.A. MacDonald Construction Co.,  
          Inc. (1998) 71 Cal.App.4th 38, 60.)  In the Howard case, the  
          City of Los Angeles was held to have failed to disclose material  
          information to the general contractor and its subcontractors  
          concerning project restrictions and difficulties, failed to  
          timely obtain construction permits from regulatory agencies, and  
          failed to provide access to the work site.  (Id. at p. 48.)  The  
          Howard case provides a poignant example of the types of  
          situations in which the general contractor and subcontractor has  
          performed their duties under their respective contracts in good  
          faith, yet the public agency created delays that required the  
          extra work performed, then failed and refused to pay the general  
          contractor work performed, who had then failed to pay the  
          subcontractor.

          In these situations, the quickest method for a subcontractor to  
          receive payment for extra work performed is to request that the  
          general contractor submit the claim for payment to the public  
          agency.  Although a subcontractor can already attempt this line  
          of recourse, the general contractor is under no obligation to  
          submit the claim to the public agency.  Further, the general  
          contractor, who may also be attempting to recover payment for  
          extra work from the public agency, may decide against submitting  
          the claim in order to maintain positive communication with the  
          public agency.  The general contractor is under no obligation to  
          advise the subcontractor whether or not the claim was submitted  
          to the public agency for payment.  Accordingly, this bill would  
          allow the subcontractor to submit the claim through the general  
          contractor, but establish a timeframe of 45 days of receipt of  
          the written request for the general contractor to notify the  
          subcontractor whether the general contractor presented the claim  
          to the public agency.  Further, if the general contractor opted  
          against presenting the claim to the public agency, the bill  
          would require the general contractor to provide the  
          subcontractor a statement of reasons for not presenting the  








          AB 626 (Chiu)
          Page 19 of ? 


          claim.  These provisions would provide better clarity of the  
          claim review process and important claim information for general  
          contractors and subcontractors.

          5.  "Home Rule" Doctrine  

          The California Constitution, Article XI, Section 7, provides  
          that a county or city may make and enforce within its limits all  
          local, policy, sanitary, and other ordinances and regulations  
          not in conflict with general laws.  However, a charter city is  
          provided the ability to make and enforce all ordinances and  
          regulations in respect to municipal affairs, subject only to  
          restrictions and limitations provided in its several charters,  
          and, in respect to other matters, the charter city is subject to  
          general laws.  (Cal. Const., art. XI, sec. 5.)  A city charter  
          or municipal law which may have precedence over a conflicting  
          state statute purporting to regulate a municipal matter is known  
          as the "home rule" doctrine.

          In Dibbs v. County of San Diego (1994) 8 Cal.4th 1200, the  
          California Supreme Court in contracting the home rule authority  
          of charter cities and chartered counties stated that, whereas  
          charter county "home rule" authority is limited to matters  
          concerning the structure and operation of local government, the  
          version of "home rule" afforded to a charter city is  
          substantially more expansive.  However, the California  
          Constitution does not define what constitutes a municipal  
          affair.  Accordingly, courts must determine whether the facts of  
          each case implicate a matter under municipal or state concern.   
          (County of Riverside v. Superior Court (2003) 30 Cal.4th 278,  
          292.)

          The "home rule" doctrine becomes important in a public work if  
          the public agency is a charter city asserting that a state  
          statute does not apply to the charter city.  Such was the case  
          in Howard Contracting, Inc. v. G.A. MacDonald Construction Co.  
          (1998) 71 Cal.App.4th 38, 51, in which the City of Los Angeles  
          claimed not to be subject to a state law interfering with the  
          City's public work contract.  At issue was Public Contract Code  
          Section 7102, which provides that contract provisions in public  
          works construction contracts, and the subcontracts thereunder,  
          which attempt to limit the public entity's liability for delays  
          it causes, do not preclude the recovery of damages by the  
          contractor or subcontractor.  The statute also provides that a  








          AB 626 (Chiu)
          Page 20 of ? 


          public agency cannot require the waiver, alteration, or  
          limitation of the applicability of this section.  However, the  
          statute cannot be construed to void any provision in a public  
          works construction contract that requires notice of delays or  
          provides for liquidated damages.  

          In the Howard case, the court discussed the City's claim under  
          the home rule doctrine of immunity from liability for damages  
          caused by its own delays: 

            In California Federal, the Supreme Court established a test to  
            determine whether the state has infringed upon a charter  
            city's sovereignty under the "home rule" doctrine. (54 Cal. 3d  
            at pp. 16-18.)  Under the first prong of the test, the  
            existence of an actual conflict between a state statute and a  
            local measure must be ascertained.  Once a conflict is found  
            to exist, a further determination must be made whether the  
            subject matter of the statutory enactment is more properly  
            characterized as a local or statewide concern. 

            In this case, the purported conflict with a provision of a  
            state statute does not relate to a charter provision or  
            municipal enactment, but to a "no damage for delay" clause  
            contained in the Standard Specifications of the contract  
            between MacDonald Construction and the City.  Because the City  
            fails to establish a conflict between the Public Contract Code  
            and any charter provision or municipal enactment, Public  
            Contract Code section 7102 applies.  As a consequence, the  
            contract clause purporting to exempt the City from liability  
            for damages resulting from delays caused by the City is  
            unenforceable under section 7102.  (Id.)

          Because the Howard case established that charter city public  
          work contracts are subject to state statutes under the Public  
          Contract Code, the provisions in this bill would likely not be  
          superseded by a city's charter or municipal laws because the  
          provisions of the bill involve a statewide concern, are not  
          solely aimed at regulating charter cities, and the bill's  
          provisions likely do not relate to a city's charter or municipal  
          laws but rather relate to public work contracts and obligations  
          thereon.  


           Support :  Air Conditioning Sheet Metal Association;  








          AB 626 (Chiu)
          Page 21 of ? 


          Air-Conditioning & Refrigeration Contractors Association;  
          Advanced Cable Solutions, Inc.; Architectural Glass& Aluminum;  
          Associated General Contractors (AGC); Ayoob & Perry Plumbing  
          Co.; Baker Electric; Big Sky Electric; California Chapters of  
          the National Electrical Contractors Association (NECA);  
          California Legislative Conference of the Plumbing;  
          California-Nevada Conference of Operating Engineers; California  
          State Association of Electrical Workers; California State Pipe  
          Trades Council; Carter, Wetch & Associates; Collins Electrical  
          Company, Inc.; Creative Shower Door Corp.; Cupertino Electric,  
          Inc.; Electro Construction Corp.; Finishing Contractors  
          Association of Southern California; Fuller Electric; Giroux  
          Glass, Inc.; Heating and Piping Industry; International Union of  
          Elevator Constructors; KBI Painting, Inc.; Mike Cox Electric  
          Company, Inc.; Morrow-Meadows Corporation; Neal Electric Corp.;  
          Neubauer Electric, Inc.; Northern California Allied Trades;  
          Pacific Glazing Contractors; Painting and Decorating Contractors  
          Association of Sacramento; Piping Industry Progress & Education  
          Trust Fund; Pyramid Painting, Inc.; Roundtree Glass Company;  
          Santa Barbara Glass Company; Schetter Electric, Inc.; Smith and  
          Sons Electric, Inc.; State Building and Construction Trades  
          Council, AFL-CIO; TNT Industrial Contractors, Inc.; Wall and  
          Ceiling Alliance; Western States Council of Sheet Metal Workers;  
          44 individuals

           Opposition :  None Known

                                        HISTORY
           
           Source  :  California State Council of Laborers; United  
          Contractors

           Related Pending Legislation  :  None Known

           Prior Legislation  :

          AB 1347 (Chiu, 2015) nearly identical to this bill.  This bill  
          was vetoed by the Governor.

          AB 2471 (Frazier, 2014) would have required state and local  
          public entities engaged in a public works contract awarded to  
          the lowest bidder to promptly issue change orders when extra  
          work is required of the contractor or subcontractor.  AB 2471  
          died in the Senate Appropriations Committee without a hearing.








          AB 626 (Chiu)
          Page 22 of ? 



          AB 2096 (Miller, 2010) would have allowed a public agency and a  
          contractor to mutually agree to resolve a claim through  
          independent arbitration.  AB 2096 died in the Assembly Judiciary  
          Committee without a hearing.

          AB 541 (Duvall, 2009) was substantially similar to AB 2096 and  
          died in the Assembly Judiciary Committee without a hearing.

          AB 216 (Beall, 2009) would have reformed pre-litigation claims  
          resolution procedures for local public works projects.  AB 216  
          was held under submission in the Assembly Appropriations  
          Committee.

          SB 1642 (Yee, 2008) would have established alternative dispute  
          resolution procedures for local public works projects costing  
          over $50,000.  SB 1642 was held under submission in the Senate  
          Appropriations Committee.

           Prior Vote  :

          Assembly Floor (Ayes 55, Noes 24)
          Assembly Appropriations Committee (Ayes 12, Noes 4)
          Assembly Higher Education Committee (Ayes 11, Noes 2)

                                   **************