AB 674, as amended, Mullin. Electricity: distributed generation.
Under existing law, the Public Utilities Commission has regulatory authority over public utilities, including electrical corporations, as defined. Existing law authorizes the commission to fix the rates and charges for every public utility, and requires that those rates and charges be just and reasonable. Existing law requires the commission to require each electrical corporation under the operational control of the Independent System Operator as of January 1, 2001, to modify tariffs so that all customers that install new distributed energy resources, as defined, in accordance with specified criteria are served under rates, rules, and requirements identical to those of a customer within the same rate schedule that does not use distributed energy resources, and to withdraw any provisions in otherwise applicable tariffs that activate other tariffs, rates, or rules if a customer uses distributed energy resources. Existing law provides, notwithstanding these requirements, that a customer that installs new distributed energy resources not be exempted from (1) reasonable interconnection charges, (2) charges imposed pursuant to the Reliable Electric Service Investment Act, and (3) charges imposed to repay the Department of Water Resources for electricity procurement expenses incurred in response to the electricity crisis of 2000-01. Existing law requires the commission, in establishing the rates applicable to customers that install new distributed energy resources, to create a firewall that segregates distribution cost recovery so that any net costs, taking into account the actual costs and benefits of distributed energy resources, proportional to each customer class, as determined by the commission, resulting from the tariff modifications granted to members of each customer class may be recovered only from that class.
This bill would, to the extent
authorized by federal law, require the commission, by July 1, 2016, to do both of the following for those electrical corporation customers that have installed clean distributed energy resources, as defined,begin delete prior toend deletebegin insert beforeend insert January 1, 2016: (1) require each electrical corporation to collect all applicable nonbypassable charges fixed, implemented, administered, or imposed by the commission based only on the actual metered consumption of electricity delivered to the customer through the electrical corporation’s transmission or distribution system, which charges are to be at the same rate per kilowatthour as paid by other customers that do not employ a clean distributed energy resource, and (2) calculate a reservation capacity for standby service, if applicable, based on the capacity needed by an electrical corporation to
serve a customer’s electrical demand during an outage of the clean distributed energy resource providing electric service for that customer. The bill would require the State Energy Resources Conservation and Development Commission to report to the Legislature and the relevant policy committees of the Legislature on the impact ofbegin delete the program upon specified matterend deletebegin insert its provisions on specified issuesend insert by July 1, 2021.
Under existing law, a violation of the Public Utilities Act or any order, decision, rule, direction, demand, or requirement of the commission is a crime.
Because the provisions of this bill would be a part of the act and because a violation of an order or decision of the commission implementing its requirements would be a crime, the bill would impose a state-mandated local program by creating a new crime.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.
Vote: majority. Appropriation: no. Fiscal committee: yes. State-mandated local program: yes.
The people of the State of California do enact as follows:
The Legislature finds and declares all of the
2following:
3(a) Clean onsite generation of electricity yields multiple benefits,
4including increased electrical reliability and efficiency, reduced
5emissions of greenhouse gases and oxides of nitrogen (NOx), and
6electrical grid resiliency.
7(b) In 2011, Governor Jerry Brown released a Clean Energy
8Jobs Plan that called for 12,000 megawatts of localized electrical
9generation, also known as distributed generation, to maximize
10energy efficiency and minimize environmental impacts, while
11increasing reliability and security.
12(c) Increased deployment of clean onsite electrical generation
13reduces the need for generation that emits higher levels of
14greenhouse gases that contribute to climate change and higher
15levels of NOx that contribute to smog formation.
16(d) Several types of clean onsite electrical generation
17technologies currently exist and others are being developed, with
18many being developed and manufactured in California.
19(e) Residential, commercial, and industrial customers are willing
20to invest their own capital to install clean onsite generation
21technologies.
22(f) Nonbypassable charges create an economic barrier to the
23installation of clean onsite electrical generation and, as
a result,
24prevent cost savings for all ratepayers and environmental benefits
25for all Californians.
26(g) Among states with similarly high energy prices and
27environmental goals, California is the only state that allows
28electrical corporations to apply nonbypassable charges to electricity
29produced and consumed onsite.
30(h) Ratepayers would see a net cost savings from increased
31deployment of onsite electricity generation at customer sites that
32pay nonbypassable charges only on their electricity purchases from
33the grid. This ratepayer savings arises because onsite electricity
34generation reduces demand on the electrical grid, which reduces
P4 1market electricity prices, and avoids transmission and distribution
2costs and energy losses.
3(i) Other cost-saving benefits to all ratepayers from clean onsite
4electrical generation include reductions in future generating
5capacity requirements, reductions in electrical grid congestion
6prices, reductions in emissions of greenhouse gases and criteria
7air pollutants, and increases in electrical grid resiliency and
8
security.
Section 354 is added to the Public Utilities Code, to
10read:
(a) As used in this section, “clean distributed energy
12resource” means a facility that is located on the customer’s
13premises and generates electricity, or electricity and useful heat,
14where the electricity generated is used for a purpose described in
15paragraph (1) or (2) of subdivision (b) of Section 218, and that
16meets either of the following requirements:
17(1) It meets all of the following criteria:
18(A) Has a carbon dioxide (CO2) emissions rate, including credit
19for waste heat recovery, where applicable, and savings on
20transmission and distribution losses, that is no greater than 437
21kilograms per
megawatthour.
22(A) Produces emission of carbon dioxide (CO2) at a rate per
23megawatthour, accounting for waste heat recovery, where
24applicable, and savings on transmission and distribution losses,
25that is less than the emissions of CO2 from the marginal generating
26unit dispatched to meet the demand on the electrical grid that is
27avoided by the electricity generated by the clean distributed energy
28resource, as determined by the Energy Commission as of January
2930, 2016.
30(B) Has an oxide of nitrogen (NOx) emissions rate, including
31credit for waste heat recovery, when applicable, that is less than
32or equal to 0.07 pounds per megawatthour, or a lower NOx
33emissions rate that the State Air Resources Board
determines
34reflects the best performance achieved in practice by existing
35electrical generation technologies pursuant to Section 41514.9 of
36the Health and Safety Code.
37(C) Has a nameplate rated generation capacity of 20 megawatts
38or less.
P5 1(D) Is sized to meet the electrical demand of, or use the available
2waste heat of, the customer that will be served by the generating
3facility.
4(2) It is an “eligible renewable energy resource” pursuant to the
5California Renewables Portfolio Standard Program (Article 16
6(commencing with Section 399.11)), has a nameplate rated
7generation capacity of 20 megawatts or less, is sized to meet the
8 electrical demand of the customer that will be served by the
9generating facility,
and will not otherwise be addressed in the
10commission’s implementation of Section 769 or 2827.1.
11(b) To the extent authorized by federal law, by July 1, 2016, the
12commission shall require each electrical corporation to do the
13following for customers served by clean distributed energy
14resources installedbegin delete prior toend deletebegin insert beforeend insert January 1, 2016:
15(1) Collect all applicable nonbypassable charges fixed,
16implemented, administered, or imposed by the commission based
17only on the actual metered consumption of electricity delivered to
18the customer through the electrical corporation’s transmission or
19distribution system. All
charges shall be at the same rate per
20kilowatthour as paid by other customers that do not employ a clean
21distributed energy resource under the electrical corporation’s
22applicable rate schedule.
23(2) (A) Calculate a reservation capacity for standby service, if
24applicable, based on the capacity needed by an electrical
25corporation to serve a customer’s electrical demand during an
26outage of the clean distributed energy resource providing electric
27service for that customer.
28(B) Initial reservation capacity shall be established by the
29customer for a minimum of 12 months based on the clean
30distributed energy resource generation technology’s historical
31operation, the number, size, and outage diversity of the clean
32distributed energy resource, and the annual average
reduction of
33customer load that could occur during an outage.
34(C) If after the initial 12-month period, the electrical corporation
35reasonably determines that the reservation capacity does not reflect
36the customer’s actual standby demand, averaged over the previous
3712 months, the electrical corporation shall modify the reservation
38capacity once every 12 months to reflect the customer’s actual
39average annual reservation capacity based on the same criteria
40used to establish the initial reservation capacity. Calculation of
P6 1actual average annual reservation capacity shall exclude the
2customer’s electrical demand served by the electrical corporation
3within 24 hours following an outage of the clean distributed energy
4resource resulting from any event on the electrical corporation’s
5transmission or distribution grid that is outside of the customer’s
6control
that requires the customer to reduce onsite generation.
7(c) (1) By July 1, 2021, the Energy Commission, in consultation
8with the commission, shall reportbegin insert on the impacts of this sectionend insert to
9the Legislature and the relevant policy committees of the
10Legislaturebegin delete onend deletebegin insert
in regard toend insert all of the following:
11(A) Avoided transmission and distribution costs.
12(B) Avoided energy losses.
13(C) Wholesale electricity market prices.
14(D) Electricity costs to ratepayers.
15(E) Air quality.
16(F) Emissions of greenhouse gases.
17(G) Job creation.
18(H) Energy reliability.
19(I) The extent to which the
incentives providedbegin delete by the programend delete
20begin insert
pursuant to this sectionend insert contribute to achieving the state’s
21distributed generation and combined heat and power goals.
22(2) The report to be submittedbegin insert to the Legislatureend insert pursuant to
23this subdivision shall be submitted in compliance with Section
249795 of the Government Code.
25(3) The requirement for submitting a report pursuant to this
26subdivision is inoperative on July 1, 2025, pursuant to Section
2710231.5 of the Government Code.
No reimbursement is required by this act pursuant to
29Section 6 of Article XIII B of the California Constitution because
30the only costs that may be incurred by a local agency or school
31district will be incurred because this act creates a new crime or
32infraction, eliminates a crime or infraction, or changes the penalty
33for a crime or infraction, within the meaning of Section 17556 of
34the Government Code, or changes the definition of a crime within
35the meaning of Section 6 of Article XIII B of the California
36Constitution.
O
98