Amended in Assembly April 16, 2015

Amended in Assembly April 6, 2015

Amended in Assembly March 25, 2015

California Legislature—2015–16 Regular Session

Assembly BillNo. 674


Introduced by Assembly Member Mullin

February 25, 2015


An act to add Section 354 to the Public Utilities Code, relating to electricity.

LEGISLATIVE COUNSEL’S DIGEST

AB 674, as amended, Mullin. Electricity: distributed generation.

Under existing law, the Public Utilities Commission has regulatory authority over public utilities, including electrical corporations, as defined. Existing law authorizes thebegin delete commissionend deletebegin insert Public Utilities Commissionend insert to fix the rates and charges for every public utility, and requires that those rates and charges be just and reasonable. Existing law requires thebegin delete commissionend deletebegin insert Public Utilities Commissionend insert to require each electrical corporation under the operational control of the Independent System Operator as of January 1, 2001, to modify tariffs so that all customers that install new distributed energy resources, as defined, in accordance with specified criteria are served under rates, rules, and requirements identical to those of a customer within the same rate schedule that does not use distributed energy resources, and to withdraw any provisions in otherwise applicable tariffs that activate other tariffs, rates, or rules if a customer uses distributed energy resources. Existing law provides, notwithstanding these requirements, that a customer that installs new distributed energy resources not be exempted from (1) reasonable interconnection charges, (2) charges imposed pursuant to the Reliable Electric Service Investment Act, and (3) charges imposed to repay the Department of Water Resources for electricity procurement expenses incurred in response to the electricity crisis of 2000-01. Existing law requires thebegin delete commission,end deletebegin insert Public Utilities Commission,end insert in establishing the rates applicable to customers that install new distributed energy resources, to create a firewall that segregates distribution cost recovery so that any net costs, taking into account the actual costs and benefits of distributed energy resources, proportional to each customer class, as determined by thebegin delete commission,end deletebegin insert Public Utilities Commission,end insert resulting from the tariff modifications granted to members of each customer class may be recovered only from that class.

This bill would, to the extent authorized by federal law, require thebegin delete commission,end deletebegin insert Public Utilities Commission,end insert by July 1, 2016, to do both of the following for those electrical corporation customers that have installed clean distributed energy resources, as defined, after January 1, 2016: (1) require each electrical corporation to collect all applicable nonbypassable charges fixed, implemented, administered, or imposed by thebegin delete commissionend deletebegin insert Public Utilities Commissionend insert based only on the actual metered consumption of electricity delivered to the customer through the electrical corporation’s transmission or distribution system, which charges are to be at the same rate per kilowatthour as paid by other customers that do not employ a clean distributed energy resource, and (2) calculate abegin delete reservationend deletebegin insert reserveend insert capacity for standby service, if applicable, based on the capacity needed by an electrical corporation to serve a customer’s electrical demand during an outage of the clean distributed energy resource providing electric service for that customer. The bill would require the State Energy Resources Conservation and Development Commission to report to the Legislature and the relevant policy committees of the Legislature on the impact of its provisions on specified issues by July 1, 2021.

Under existing law, a violation of the Public Utilities Act or any order, decision, rule, direction, demand, or requirement of the commission is a crime.

Because the provisions of this bill would be a part of the act and because a violation of an order or decision of the commission implementing its requirements would be a crime, the bill would impose a state-mandated local program by creating a new crime.

The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.

This bill would provide that no reimbursement is required by this act for a specified reason.

Vote: majority. Appropriation: no. Fiscal committee: yes. State-mandated local program: yes.

The people of the State of California do enact as follows:

P3    1

SECTION 1.  

The Legislature finds and declares all of the
2following:

3(a) Clean onsite generation of electricity yields multiple benefits,
4including increased electrical reliability and efficiency, reduced
5emissions of greenhouse gases and oxides of nitrogen (NOx), and
6electrical grid resiliency.

7(b) In 2011, Governor Jerry Brown released a Clean Energy
8Jobs Plan that called for 12,000 megawatts of localized electrical
9generation, also known as distributed generation, to maximize
10energy efficiency and minimize environmental impacts, while
11increasing reliability and security.

12(c) Increased deployment of clean onsite electrical generation
13reduces the need for generation that emits higher levels of
14greenhouse gases that contribute to climate change and higher
15levels of NOx that contribute to smog formation.

16(d) Several types of clean onsite electrical generation
17technologies currently exist and others are being developed, with
18many being developed and manufactured in California.

19(e) Residential, commercial, and industrial customers are willing
20to invest their own capital to install clean onsite generation
21technologies.

22(f) Nonbypassable charges create an economic barrier to the
23installation of clean onsite electrical generation and, as a result,
24prevent cost savings for all ratepayers and environmental benefits
25for all Californians.

26(g) Among states with similarly high energy prices and
27environmental goals, California is the only state that allows
28electrical corporations to apply nonbypassable charges to electricity
29produced and consumed onsite.

P4    1(h) Ratepayers would see a net cost savings from increased
2deployment of onsite electricity generation at customer sites that
3pay nonbypassable charges only on their electricity purchases from
4the grid. This ratepayer savings arises because onsite electricity
5generation reduces demand on the electrical grid, which reduces
6market electricity prices, and avoids transmission and distribution
7costs and energy losses.

8(i) Other cost-saving benefits to all ratepayers from clean onsite
9electrical generation include reductions in future generating
10capacity requirements, reductions in electrical grid congestion
11prices, reductions in emissions of greenhouse gases and criteria
12air pollutants, and increases in electrical grid resiliency and
13 security.

14

SEC. 2.  

Section 354 is added to the Public Utilities Code, to
15read:

16

354.  

(a) As used in this section, “clean distributed energy
17resource” means a facility that is located on the customer’s
18premises and generates electricity, or electricity and useful heat,
19where the electricity generated is used for a purpose described in
20paragraph (1) or (2) of subdivision (b) of Section 218, and that
21meets either of the following requirements:

22(1) It meets all of the following criteria:

begin delete

23(A) Produces emission of carbon dioxide (CO2) at a rate per
24megawatthour, accounting for waste heat recovery, where
25applicable, and savings on transmission and distribution losses,
26that is less than the emissions of CO2 from the marginal generating
27unit dispatched to meet the demand on the electrical grid that is
28avoided by the electricity generated by the clean distributed energy
29resource, as determined by the Energy Commission as of January
3030, 2016.

31(B) Has an oxide of nitrogen (NOx) emissions rate, including
32credit for waste heat recovery, when applicable, that is less than
33or equal to 0.07 pounds per megawatthour, or a lower NOx
34emissions rate that the State Air Resources Board determines
35reflects the best performance achieved in practice by existing
36electrical generation technologies pursuant to Section 41514.9 of
37the Health and Safety Code.

end delete
begin insert

38(A) Produces emissions of greenhouse gases that are less than
39the levels established by the commission pursuant to paragraph
40(2) of subdivision (b) of Section 379.6.

end insert
begin insert

P5    1(B) Produces emissions of nitrogen oxides and sulfur oxides
2that are less than the levels permitted for an advanced electrical
3distributed generation technology pursuant to Section 379.8.

end insert

4(C) Has a nameplate rated generation capacity of 20 megawatts
5or less.

6(D) Is sized to meet the electrical demand of, or use the available
7waste heat of, the customer that will be served by the generating
8facility.

9(2) It is an “eligible renewable energy resource” pursuant to the
10California Renewables Portfolio Standard Program (Article 16
11(commencing with Section 399.11)), has a nameplate rated
12generation capacity of 20 megawatts or less, is sized to meet the
13electrical demand of the customer that will be served by the
14generating facility, and will not otherwise be addressed in the
15commission’s implementation of Section 769 or 2827.1.

16(b) To the extent authorized by federal law, by July 1, 2016, the
17commission shall require each electrical corporation to do the
18following for customers served by clean distributed energy
19resources installed after January 1, 2016:

20(1) Collect all applicable nonbypassable charges fixed,
21implemented, administered, or imposed by the commission based
22only on the actual metered consumption of electricity delivered to
23the customer through the electrical corporation’s transmission or
24distribution system. All charges shall be at the same rate per
25kilowatthour as paid by other customers that do not employ a clean
26distributed energy resource under the electrical corporation’s
27applicable rate schedule.

28(2) (A) Calculate abegin delete reservationend deletebegin insert reserveend insert capacity for standby
29service, if applicable, based on the capacity needed by an electrical
30corporation to serve a customer’s electrical demand during an
31outage of the clean distributed energy resource providing electric
32service for that customer.

33(B) Initialbegin delete reservationend deletebegin insert reserveend insert capacity shall be established by
34the customer for a minimum of 12 months based on the clean
35distributed energy resource generation technology’s historical
36operation, the number, size, and outage diversity of the clean
37distributed energy resource, and the annual average reduction of
38customer load that could occur during an outage.

39(C) If after the initial 12-month period, the electrical corporation
40reasonably determines that thebegin delete reservationend deletebegin insert reserveend insert capacity does
P6    1not reflect the customer’s actual standby demand, averaged over
2the previous 12 months, the electrical corporation shall modify the
3begin delete reservationend deletebegin insert reserveend insert capacity once every 12 months to reflect the
4customer’s actual average annualbegin delete reservationend deletebegin insert reserveend insert capacity
5based on the same criteria used to establish the initialbegin delete reservationend delete
6begin insert reserveend insert capacity. Calculation of actual average annualbegin delete reservationend delete
7begin insert reserveend insert capacity shall exclude the customer’s electrical demand
8served by the electrical corporation within 24 hours following an
9outage of the clean distributed energy resource resulting from any
10event on the electrical corporation’s transmission or distribution
11grid that is outside of the customer’s control that requires the
12customer to reduce onsite generation.

13(c) (1) By July 1, 2021, the Energy Commission, in consultation
14with the commission, shall report on the impacts of this section to
15the Legislature and the relevant policy committees of the
16Legislature in regard to all of the following:

17(A) Avoided transmission and distribution costs.

18(B) Avoided energy losses.

19(C) Wholesale electricity market prices.

20(D) Electricity costs to ratepayers.

21(E) Air quality.

22(F) Emissions of greenhouse gases.

23(G) Job creation.

24(H) Energy reliability.

begin delete

25(I) The extent to which the incentives provided pursuant to this
26section contribute to achieving the state’s distributed generation
27and combined heat and power goals.

end delete

28(2) The report to be submitted to the Legislature pursuant to
29this subdivision shall be submitted in compliance with Section
309795 of the Government Code.

31(3) The requirement for submitting a report pursuant to this
32subdivision is inoperative on July 1, 2025, pursuant to Section
3310231.5 of the Government Code.

34

SEC. 3.  

No reimbursement is required by this act pursuant to
35Section 6 of Article XIII B of the California Constitution because
36the only costs that may be incurred by a local agency or school
37district will be incurred because this act creates a new crime or
38infraction, eliminates a crime or infraction, or changes the penalty
39for a crime or infraction, within the meaning of Section 17556 of
40the Government Code, or changes the definition of a crime within
P7    1the meaning of Section 6 of Article XIII B of the California
2Constitution.



O

    96