BILL ANALYSIS                                                                                                                                                                                                    Ó



                                                                     AB 935


                                                                    Page  1


          CONCURRENCE IN SENATE AMENDMENTS


          AB  
          935 (Salas)


          As Amended  August 17, 2016


          Majority vote


           -------------------------------------------------------------------- 
          |ASSEMBLY:  |80-0  |(June 3, 2016) |SENATE: |30-3  |(August 22,      |
          |           |      |               |        |      |2016)            |
          |           |      |               |        |      |                 |
          |           |      |               |        |      |                 |
           -------------------------------------------------------------------- 


          Original Committee Reference:  W., P., & W.


          SUMMARY:  This bill requires the Department of Water Resources  
          (DWR), upon appropriation by the Legislature, to fund a reverse  
          flow pump-back project on the Friant-Kern Canal that  
          substantially conforms to the project description set forth by  
          the draft investment strategy released by the San Joaquin River  
          Restoration Program in December 2014.


          The Senate amendments delete the Assembly version of the bill,  
          and instead:


          1)Requires the DWR, upon appropriation by the Legislature, to  
            grant up to $7 million for the Reverse Flow Pump-back  
            Facilities on the Friant-Kern Canal Restoration Project  
            (Project).










                                                                     AB 935


                                                                    Page  2


          2)Limit the DWR's funding share of the Project to up to 80% of  
            the total.


          3)Establish prerequisites to funding, including:


             a)   All feasibility studies are complete and draft  
               environmental impact reports (EIRs) required pursuant to  
               the California Environmental Quality Act (CEQA) are  
               available for public review.


             b)   Financial commitments to the DWR director are equal to  
               or greater than 75% of the non-state cost share of the  
               project.  


          4)Requires the Project, if funded, to comply with any applicable  
            provisions of state and federal law. 


          EXISTING LAW:


          1)Establishes the DWR within the Natural Resources Agency, which  
            manages and undertakes planning with regard to water resources  
            in the state.


          2)Prohibits a public agency, under CEQA, from making a  
            discretionary decision to approve a project, including funding  
            a project, if there are potentially significant impacts on the  
            environment that could be reduced by feasible alternatives or  
            feasible mitigation measures.  


          FISCAL EFFECT:  Unknown


          COMMENTS:  The Assembly version of this bill contained a general  
          requirement for the DWR to fund local and regional conveyance  








                                                                     AB 935


                                                                    Page  3


          projects.  The Senate version of this bill deletes the general  
          requirement and instead, specifies a project that would help  
          minimize water supply impacts to Friant Division long-term  
          contractors from actions to help implement the San Joaquin River  
          Restoration Program (SJRRP).


          The San Joaquin River is the second longest river in California  
          and historically supported large runs of salmon and other  
          cold-water fish.  After Friant Dam was constructed by the United  
          States Department of Interior, Bureau of Reclamation  
          (Reclamation), parts of the San Joaquin River went completely  
          dry in most years.  Environmental groups then brought litigation  
          citing, among other claims, the requirements in California law  
          that the owner of any dam must allow sufficient water to pass  
          through to keep fish in good condition below the dam.  In 2006,  
          after 18 years of litigation, a federal court approved a  
          settlement between the federal government, the environmental  
          plaintiffs, and the Friant Water Users Authority.  The SJRRP  
          settlement had two objectives:  a restoration program that would  
          provide the river with continuous flows to the Sacramento-San  
          Joaquin River Delta and support naturally reproducing  
          populations of Chinook salmon, and a water management goal of  
          minimizing water supply impacts to San Joaquin River water  
          users.


          Thereafter, Reclamation initiated an investment strategy in  
          support of the SJRRP water management goal in order to identify  
          projects that, in conjunction with other activities, could  
          cost-effectively reduce or avoid water supply impacts to the  
          Friant Contractors.  Reclamation, in collaboration with the  
          Friant Contractors, identified, screened, developed, evaluated,  
          and ranked over 500 project concepts to form a list of  
          approximately 60 projects.  Of these, 21 projects were further  
          evaluated as ready-to-implement priority projects.  The results  
          were presented in a March 2015 report titled Water Management  
          Goal Investment Strategy Final Report (Final Report).  


          The Reverse Flow Pump-Back Facilities on the Friant-Kern Canal  
          project that would be funded through this bill is among the 21  








                                                                     AB 935


                                                                    Page  4


          projects evaluated in the Final Report. 


          The Friant-Kern Canal is a Federal Central Valley Project canal  
          that conveys water from Friant Dam on the San Joaquin River near  
          Fresno, southward to various Friant Contractors along the east  
          side of the San Joaquin Valley, terminating at the Kern River  
          near Bakersfield.  Currently, the Friant-Kern Canal has limited  
          pump-back operational capacity which is used occasionally to  
          deliver north the water from the Cross Valley Canal or water  
          extracted from water banks on the Kern River fan.  This project  
          would install permanent pump-back facilities with higher  
          capacities along the southern portion of the Friant-Kern Canal.   
          The project would allow water that was released for restoration  
          flows on the San Joaquin River, captured downstream, and  
          conveyed via the Cross Valley Canal, to be pumped back up the  
          Friant-Kern Canal to a number of Friant Contractors.  The Final  
          Report ranked this project 4th of 21, with an estimated cost of  
          $7.6 million that included planning and environmental review,  
          and a little over two years to complete. The project has been  
          estimated to convey approximately 15,000-30,000 acre-feet  
          annually and is expected to avoid 2,750 metric tons of carbon  
          emissions over the life of the project.


          Analysis Prepared by:                                             
                          Ryan Ojakian / W., P., & W. / (916) 319-2096   
          FN: 0004764