BILL ANALYSIS                                                                                                                                                                                                    Ó



                                                                    AB 1171


                                                                    Page  1





          Date of Hearing:  April 27, 2015


                        ASSEMBLY COMMITTEE ON TRANSPORTATION


                                 Jim Frazier, Chair


          AB 1171  
          (Linder) - As Amended April 21, 2015


          SUBJECT:  Construction Manager/General Contractor method:   
          regional transportation agencies:  projects on expressways


          
          SUMMARY:   Authorizes regional transportation agencies (RTAs) to  
          use an alternative procurement method referred to as  
          construction manager/general contractor (CMGC) contracts, under  
          limited circumstances.  Specifically,  this bill  :  

          1)Describes the CMGC procurement method and makes legislative  
            findings and declarations regarding benefits related to risk  
            transfer and project phasing using CMGC.

          2)Defines key terms as follows:  

             a)   "Construction manager/general contractor method" to mean  
               a project delivery method in which a construction manager  
               is procured to provide preconstruction services during the  
               design phase of the project and construction services  
               during the construction phase of the project.  Contracts  
               for preconstruction services and construction services can  
               be, but need not be, entered into at the same time and the  
               design and construction phases of a project may be carried  
               out sequentially or concurrently; 









                                                                    AB 1171


                                                                    Page  2





             b)   "Preconstruction services" to mean advice given during  
               the design phase of a project related to, for example,  
               scheduling, pricing, and phasing;

             c)   "Project" to mean the construction of an expressway that  
               is not on the state highway system; and

             d)   "Regional transportation agency" to broadly include,  
               among other entities, regional transportation planning  
               agencies, county transportation commission, joint powers  
               authorities, and local transportation authorities.

          2)Authorizes an RTA to use the CMGC project delivery method to  
            design and construct projects on expressways that are not on  
            the state highway system if the projects are developed in  
            accordance with an expenditure plan approved by the voters as  
            of January 1, 2014.  

          3)Provides that the entity responsible for maintenance of local  
            streets and roads within the same jurisdiction of the  
            expressway shall be responsible for the maintenance of the  
            expressway.

          5)Sets forth provisions governing the process for procuring CMGC  
            services.  




          EXISTING LAW:
          
          1)Sets forth provisions governing public works contracting.   
            These provisions generally prohibit public agencies from  
            contracting with the same firm for both the design and the  
            construction phases of a project.  

          2)Generally requires public works construction contracts to be  
            awarded to the lowest responsible bidder.  









                                                                    AB 1171


                                                                    Page  3





          3)Authorizes the California Department of Transportation  
            (Caltrans) to use CMGC on no more than six projects, at least  
            five of which must have construction costs greater than  
            $10,000,000.  

          4)Authorizes the Santa Clara County Valley Transportation  
            Authority, the San Mateo County Transit District, and the San  
            Diego Association of Governments to use CMGC for transit  
            projects.  

          FISCAL EFFECT:  Unknown





          COMMENTS:  For decades, the traditional process for procuring  
          public works projects has been the design-bid-build process.   
          This process relies on: 1) a design entity preparing complete  
          project design specifications and estimates; 2) the project  
          owner putting the complete package out to bid for construction;  
          and 3) awarding the construction contract to the lowest  
          responsible bidder.  The design-bid-build process was developed  
          to protect taxpayers from extravagance, corruption, and other  
          improper practices by public officials as well as to secure a  
          fair and reasonable price for public works construction by  
          injecting competition amongst bidders into the process.  

          Although design-bid-build generally results in the lowest cost  
          construction contract, it is not without its drawbacks,  
          including:  

          1)Projects generally take longer to complete because designs  
            must be entirely completed, permits obtained, and right-of-way  
            acquired before the construction contract can be bid and  
            awarded.  

          2)Designs prepared for a competitive low-bid procurement are  
            developed to allow for a broad range of construction  








                                                                    AB 1171


                                                                    Page  4





            approaches.  As a result, low-bid designs do not always equate  
            to the most efficient designs possible, depending on a  
            particular contractor's strengths or capabilities.  

          3)Because the project designer does not have the benefit of  
            consulting with the entity that will ultimately be responsible  
            for construction of the project, there may be significant  
            issues that the designer does not anticipate, particularly  
            constructability issues.  This can result in change orders  
            that ultimately drive up the price of the contract.  

          4)Low-bid is not always the least expensive option, once change  
            orders and contractor claims are factored into the overall  
            project costs.  

          In the early 1990s, public works agencies grew frustrated with  
          design-bid-build and began experimenting with more innovative  
          project delivery methods, namely design-build.  Design-build is  
          an alternate method for procuring design and construction  
          services that provides for the delivery of public works projects  
          from a single entity.  Design-build combines project design,  
          permit, and construction schedules in order to streamline the  
          traditional design-bid-build environment.  

          Design-build differs from design-bid-build in some key areas,  
          including:

          1)Overall elapsed project delivery times are shorter because  
            construction can begin before final design is complete.  

          2)Project costs and schedule risks are more heavily borne by the  
            design-build contractor.  

          3)Construction claims and change orders are minimized.  

          4)Designs can be developed to take advantage of a particular  
            contractor's strengths and abilities, thereby reducing the  
            need to "over-design" for generic use as in design-bid-build.   









                                                                    AB 1171


                                                                    Page  5






          5)Project specifications are typically based on definitive  
            performance criteria (which may or may not be well established  
            by the project owner) rather than established specifications.   


          6)Contracts are awarded based on best-value analyses rather than  
            low-bid.  

          Design-build contracts are not without their drawbacks as well.   
          For example, with a design-build project, the project owner must  
          give up a good deal of control over the details of the project  
          design.  Additionally, design-build contractors are typically  
          selected using qualifications-based selection criteria or best  
          value analysis.  These approaches are more subjective than a  
          low-bid approach, potentially subjecting the public works owner  
          to greater contract challenges and higher costs.  

          This bill provides limited authority for RTAs to use CMGC, an  
          emerging project delivery method that potentially combines the  
          best of both design-bid-build and design-build, similar to  
          authority already granted to Caltrans, the Santa Clara County  
          Valley Transportation Authority, the San Mateo County Transit  
          District, and the San Diego Association of Governments.  Using  
          CMGC, RTAs will be able to engage a design and construction  
          management consultant (construction manager) to act as its  
          consultant during the pre-construction phase and as the general  
          contractor during construction.  During the design phase, the  
          construction manager acts in an advisory role, providing  
          constructability reviews, value engineering suggestions,  
          construction estimates, and other construction-related  
          recommendations.  Later, each agency and the construction  
          manager can agree that the project design has progressed to a  
          sufficient enough point that construction may begin.  The two  
          parties then work out mutually agreeable terms and conditions  
          for the construction contract, and, if all goes well, the  
          construction manager becomes the general contractor and  
          construction on the project commences, well before design is  
          entirely complete.  








                                                                    AB 1171


                                                                    Page  6






          The CMGC process provides continuity and collaboration between  
          the design and construction phases of the project.  Construction  
          managers have an incentive to provide input during the design  
          phase that will enhance constructability of the project later  
          because they know that they will have the opportunity to become  
          the general contractor for the project.  Furthermore, CMGC  
          promises to save project delivery time, provide earlier cost  
          certainty, transfer risks from the RTA to the contractor, and  
          ensure project constructability.  Additionally, CMGC allows each  
          agency to have greater control of design decisions.  It also  
          allows each agency to design the project to compliment the  
          CMGC's strengths and capabilities, thereby avoiding the need to  
          over-design the project to provide maximum competitiveness in a  
          low-bid procurement.  

          At one point, the Federal Highway Administration (FHWA)  
          considered CMGC "innovative" and required prior approval before  
          states could use the process on a federal-aid contract; however,  
          that approval is no longer necessary.  According to FHWA,  
          projects that are best suited for the CMGC process are those for  
          which the owner needs contractor feedback during the design  
          phase.  These projects include complex components that require  
          innovation and are typically located in urban, more congested  
          areas.  Other projects that are a good fit for the CMGC process  
          are projects that entail extensive public involvement or include  
          right-of-way or utility issues that affect the overall schedule.  
           Seventeen states authorize the use of CMCG contracts for  
          transportation.  
           
           There are potential drawbacks of using CMGC contracts.   
          According to guidance published by the City of Seattle, CMGC  
          contracts carry risks, including:

          1)They are difficult and complex.  

          2)The procurement process takes longer and consumes greater  
            project staff time than traditional design-bid-build  
            contracts.  








                                                                    AB 1171


                                                                    Page  7






          3)Project teams face steep learning curves.  

          4)Successful construction cost negotiations require experienced  
            staff.  

          Other literature on the use of CMGC contracts is generally  
          consistent with Seattle's guidance regarding concerns for risks  
          associated with CMGC contracts and cautions that CMGC is not  
          appropriate for every project.  However, the same literature  
          suggests that, if carefully implemented, CMGC has the potential  
          to significantly improve project delivery.  

          AB 1171 provides limited authority for RTAs to use CMGC on  
          expressway projects that are not on the state highway system,  
          similar to authority already granted to Caltrans, Santa Clara  
          County Valley Transportation Authority, the San Mateo County  
          Transit District, and the San Diego Association of Governments  
          to use CMGC for transit projects.  These other entities have not  
          yet completed any projects using CMGC so their overall  
          experience with this procurement method is not yet known. 

          Supporters of this bill suggest that early collaboration and  
          coordination between the designer and the construction  
          contractor should lead to innovations that reduce costs,  
          increase efficiency, or accelerate project delivery,  
          particularly on large and complex projects.  One of the projects  
          for which CMGC would be used if this bill is successful is the  
          Capital Southeast Connector project in Sacramento County.  
           
           Previous legislation:  AB 1724 (Frazier) of 2014 would have  
          granted RTAs broad authority to use CMGC.  AB 1724 passed the  
          Assembly but was held in Senate Transportation and Housing  
          Committee.

          AB 2498 (Gordon), Chapter 752, Statutes of 2012, authorized  
          Caltrans to use CMGC on no more than six projects, at least five  
          of which must have construction costs greater than $10 million.   









                                                                    AB 1171


                                                                    Page  8






          SB 1549 (Vargas), Chapter 767, Statutes of 2012, authorized the  
          San Diego Association of Governments to use CMGC contracting on  
          transit projects.  

          AB 797 (Gordon), Chapter 320, Statutes of 2013, authorized the  
          Santa Clara Valley Transportation Authority and the San Mateo  
          County Transit District to use CMGC contracting on transit  
          projects.  



          REGISTERED SUPPORT / OPPOSITION:


          


          Support





          Associated General Contractors


          Capital SouthEast Connector JPA Board of Directors


          Riverside County Transportation Commission


          Sacramento Metropolitan Chamber of Commerce













                                                                    AB 1171


                                                                    Page  9





          Opposition


          


          None on file





          Analysis Prepared by:Janet Dawson / TRANS. / (916) 319-2093