BILL ANALYSIS Ó SENATE JUDICIARY COMMITTEE Senator Hannah-Beth Jackson, Chair 2015-2016 Regular Session AB 1347 (Chiu) Version: June 1, 2015 Hearing Date: June 30, 2015 Fiscal: Yes Urgency: No TMW SUBJECT Public contracts: claims DESCRIPTION This bill would establish, for public works contracts entered into on or after January 1, 2016, a claim resolution procedure by which a general contractor can seek public agency review of the claim. This bill would also prescribe a procedure by which a subcontractor or lower tier contractor may make a claim against the public agency through the general contractor. (This analysis reflects author's amendments to be offered in Committee.) BACKGROUND In general, public works refers to construction, alteration, demolition, installation, or repair work (including maintenance) of any public structure, building, road, or other improvement done under contract and paid by public funds, or if private funds are used, more than 50 percent of the square footage is leased to a public entity. Because of this, there are laws regarding many aspects of the construction projects to protect the public's interest. Public works projects do not include those done by a public agency with its own employees. On public works projects, a public agency contracts with a AB 1347 (Chiu) Page 2 of ? general contractor, who has submitted a bid or estimated cost to provide the materials and services for the construction, alteration, demolition, installation, or repair work. At times, the cost of the materials and services is more than the general contractor's bid due to changes in the project, which may be attributed to inaccurate or incomplete project plans and specifications, the public agency orders extra work to be performed, or unexpected difficulties arise. These increases in costs may be submitted to the public agency for payment. Typically, unless a change order is issued by the public agency or its legislative body or appropriate department approving the increase in cost, the general contractor, who may not be responsible for the underlying cause of the increase in costs but has accrued the expense for the sake of completing the project, will be unable to resolve a claim dispute outside of arbitration or civil action. Further, a subcontractor, who has performed additional services or provided materials outside the scope of the original contract with the general contractor but necessary to the completion of the project, may be seeking payment from the public agency. Delays in payment for the extra work provided by the contractor or subcontractor may place the contractor or subcontractor at financial risk with their employees or continued work on the public work. Additionally, the failure of the public agency to issue a change order or the denial of claims has resulted in costly litigation for the public agency, contractors, and subcontractors. Multiple legislative attempts to address pre-litigation claim disputes have failed. Existing law authorizes state agencies to arbitrate claim disputes, while local agencies are subject to a different claims resolution process. Subcontractors must rely on submitting their claims for payment through the general contractor or other subcontractor through which they have contracted for services or materials to be provided on the public works project. However, depending upon the general contractor and its desire, on one hand, to help the subcontractor get paid, or, on the other hand, to maintain positive relations with the public agency, the subcontractor may or may not receive an answer from the general contractor as to whether the claim was submitted to the public agency. AB 1347 (Chiu) Page 3 of ? This bill seeks to provide a simplified, cost-effective claims resolution procedure to resolve contractor claims prior to arbitration or civil action. This bill would also provide a clear process for a subcontractor to submit claims through a general contractor in order to provide the subcontractor with information as to whether the general contractor has rejected the request to submit the subcontractor's claim to the public agency. CHANGES TO EXISTING LAW Existing law prohibits a local public entity, charter city, or charter county from requiring a bidder (i.e., general contractor) to assume responsibility for the completeness and accuracy of architectural or engineering plans and specifications on public works projects, except on clearly designated design build projects. (Pub. Contract Code Sec. 1104.) However, the local public entity, charter city, or charter county may require a bidder to review architectural or engineering plans and specifications prior to submission of a bid, and report any errors and omissions noted by the contractor to the architect or owner. (Id.) The review by the contractor shall be confined to the contractor's capacity as a contractor, and not as a licensed design professional. (Id.) Existing law , prior to the commencement of the public work costing more than $15,000, other than maintenance work or work occasioned by emergency, requires the engineer to prepare and file in his office either full, complete and accurate plans and specifications or a work authorization approved by the engineer describing the work to be performed, and an estimate of the cost thereof, except where other and adequate provision is made by law requiring the preparation and filing of such plans, specifications and estimates of cost by some other officer or in some other office. (Gov. Code Sec. 4004.) Existing law requires any public works contract of a local public entity which involves digging trenches or other excavations that extend deeper than four feet below the surface to contain a clause which provides the following: that the contractor shall promptly, and before the following conditions are disturbed, notify the local public entity, in writing, of any material that may be hazardous waste, as specified, subsurface or latent physical conditions at the AB 1347 (Chiu) Page 4 of ? site differing from those indicated by information about the site made available to bidders prior to the deadline for submitting bids, and unknown physical conditions at the site of any unusual nature, different materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in the contract; that the local public entity shall promptly investigate the conditions, and if it finds that the conditions do materially so differ, or do involve hazardous waste, and cause a decrease or increase in the contractor's cost of, or the time required for, performance of any part of the work shall issue a change order under the procedures described in the contract; and that, in the event that a dispute arises between the local public entity and the contractor whether the conditions materially differ, or involve hazardous waste, or cause a decrease or increase in the contractor's cost of, or time required for, performance of any part of the work, the contractor shall not be excused from any scheduled completion date provided for by the contract, but shall proceed with all work to be performed under the contract. (Pub. Contract Code Sec. 7104.) Existing law provides that the contractor retains any and all rights provided either by contract or by law which pertain to the resolution of disputes and protests between the contracting parties. (Pub. Contract Code Sec. 7104.) Existing law prohibits a public agency, including the state, the Regents of the University of California, a city, county, district, public authority, public agency, municipal utility, and any other political subdivision or public corporation of the state, from requiring the contractor to be responsible for the cost of repairing or restoring damage to the work, which damage is determined to have been proximately caused by an act of God (earthquakes in excess of a magnitude of 3.5 on the Richter Scale and tidal waves) in excess of 5 percent of the contracted amount, provided, that the work damaged is built in accordance with accepted and applicable building standards and the plans and specifications of the awarding authority. (Pub. Contract Code Sec. 7105(a).) Existing law authorizes public agencies to make changes in construction contracts for public improvements in the course of construction to bring the completed improvements into compliance with environmental requirements or standards established by AB 1347 (Chiu) Page 5 of ? state and federal statutes and regulations enacted after the contract has been awarded or entered into. The contractor is required to be paid for the changes in accordance with the provisions of the contract governing payment for changes in the work or, if no provisions are set forth in the contract, payment shall be as agreed to by the parties. (Pub. Contract Code Sec. 7105(c).) Existing law provides that where authority to contract is vested in any public agency, excluding the state, the authority includes the power, by mutual consent of the contracting parties, to terminate, amend, or modify any contract within the scope of such authority. (Pub. Contract Code Sec. 7105(d).) However, this provision does not apply to contracts entered into pursuant to any statute expressly requiring that contracts be let or awarded on the basis of competitive bids. (Id.) Contracts of public agencies, excluding the state, required to be let or awarded on the basis of competitive bids pursuant to any statute may be terminated, amended, or modified only if the termination, amendment, or modification is so provided in the contract or is authorized under provision of law. (Id.) Existing law provides that the compensation payable, if any, for amendments and modifications shall be determined as provided in the contract, and the compensation payable, if any, in the event the contract is so terminated shall be determined as provided in the contract or applicable statutory provision providing for the termination. (Pub. Contract Code Sec. 7105(d).) Existing law , except as otherwise provided, prohibits a suit for money or damages against a public entity on a cause of action for which a claim is required to be presented until a written claim therefor has been presented to the public entity and has been acted upon by the board, or has been deemed to have been rejected by the board. (Gov. Code Sec. 945.4.) Existing law prescribes a contract claims resolution process for contracts entered into with a state agency. (Pub. Contract Code Sec. 10240 et seq.) Existing law requires arbitration of a claim, defined to mean a demand for monetary compensation or damages, arising under or relating to the performance of contracts with a state agency. (Pub. Contract Code Sec. 10240.) AB 1347 (Chiu) Page 6 of ? Existing law authorizes a claimant to initiate arbitration no later than 90 days after the date of personal or mail service on the claimant of the final written decision by the appropriate public agency department on the claim; however, this limitation does not apply to any claim founded on any cost audit, latent defect, warranty, or guarantee under the contract. (Pub. Contract Code Sec. 10240.1.) Existing law prohibits arbitration until the claimant pursues diligently and exhausts, as to the claim, the required administrative procedures set forth in the contract under which the claim arose, unless more than 240 days have elapsed since acceptance of the work by the department. (Pub. Contract Code Sec. 10240.2.) Existing law provides that unless otherwise agreed by the parties, the arbitration shall be conducted by a single arbitrator selected by the parties from the certified list created by the Public Works Contract Arbitration Committee. (Pub. Contract Code Sec. 10240.3.) If the parties cannot agree on the arbitrator, either party may petition the superior court to appoint one from the panel of arbitrators certified by the Public Works Contract Arbitration Committee. (Id.) Existing law specifies that no decision made by a department shall be conclusive on any issue in the arbitration. (Pub. Contract Code Sec. 10240.4.) Existing law requires the Departments of General Services, Transportation, and Water Resources to jointly adopt and may, from time to time, modify, revise, or repeal uniform regulations to implement arbitration provisions and may include, but need not be limited to: the method of initiating arbitration; the place of hearing based upon the convenience of the parties; procedures for the selection of a neutral arbitrator; the form and content of any pleading; procedure for conducting hearings; the providing of experts to assist the arbitrator in the event the assistance is needed; the content of the award; and simplified procedures for claims of fifty thousand dollars ($50,000) or less. (Pub. Contract Code Sec. 10240.5.) AB 1347 (Chiu) Page 7 of ? Existing law authorizes a party to the contract to join in the arbitration as a party, any supplier, subcontractor, design professional, surety, or other person who has so agreed and if the joinder is necessary to prevent a substantial risk of the party otherwise being subjected to inconsistent obligations or decisions. (Pub. Contract Code Sec. 10240.9.) Existing law does not prevent the parties to the contract, after the claim has arisen, from mutually agreeing in writing to waive the arbitration statutes and to have the claim litigated in a court of competent jurisdiction. (Pub. Contract Code Sec. 10240.10.) Existing law , within the applicable time periods and upon specified grounds, authorizes a party to petition the court to confirm, correct, or vacate the award rendered by the arbitrator; however, no department may petition to vacate an award without the prior written authorization of its agency secretary. (Pub. Contract Code Sec. 10240.12.) Except where the parties agree not to have the arbitration decision rendered as specified, a court shall vacate the award, or part thereof, if it determines either that the award, or part thereof, is not supported by substantial evidence or that it is not decided under or in accordance with the laws of this state, in which case, the court may order a rehearing before the original arbitrator or remand to the original arbitrator that portion of the dispute which the court concludes the arbitrator failed to determine. (Id.) Existing law provides that the costs of conducting the arbitration shall be borne equally by the parties, but the arbitrator may allow the prevailing party to recover its costs and necessary disbursements, with interest, other than attorney's fees, on the same basis as is allowed in civil actions. (Pub. Contract Code Sec. 10240.13.) Existing law provides a public entity with full authority to compromise or otherwise settle any claim relating to a contract at any time. (Pub. Contract Code Sec. 9201(a).) The public entity is required to include provisions in a public works contract for timely notification of the contractor of the receipt of any third-party claim relating to the contract. (Pub. Contract Code Sec. 9201(b).) This bill would preclude any other claim resolution provision AB 1347 (Chiu) Page 8 of ? and apply to all claims by contractors in connection with public works. This bill would provide the following definitions: "claim" means a separate demand by the contractor for one or more of the following: (a) a time extension, including, without limitation, for relief from damages or penalties for delay; (b) payment of money or damages arising from work done by, or on behalf of, the contractor pursuant to the contract for a public work and payment for which is not otherwise expressly provided or to which the claimant is not otherwise entitled; or (c) payment of an amount that is disputed by the public entity; "contractor" means any type of contractor subject to the Contractor's State License Law who has entered into a direct contract with a public entity for public works; "public entity" means, without limitation, a state agency, department, office, division, bureau, board, or commission, the California State University, the University of California, a city, including a charter city, county, including a charter county, city and county, including a charter city and county, district, special district, public authority, political subdivision, public corporation, or nonprofit transit corporation wholly owned by a public agency and formed to carry out the purposes of the public agency; "public work" means the erection, construction, alteration, repair, or improvement of any public structure, building, road, or other public improvement of any kind; and "subcontractor" means any type of contractor subject to the Contractor's State License Law who either is in direct contract with a contractor or is a lower tier subcontractor. This bill , upon receipt of a claim sent by registered mail, would require the public entity to which the claim applies to conduct a reasonable review of the claim and, within a period not to exceed 30 days, provide the claimant a written statement identifying what portion of the claim is disputed and what portion is undisputed. This bill would require the claimant to furnish reasonable documentation to support the claim. This bill , if the public entity needs approval from its governing body to provide the claimant a written statement identifying the disputed portion and the undisputed portion of AB 1347 (Chiu) Page 9 of ? the claim, and the governing body does not meet within the 30 days following receipt of a claim sent by registered mail, would provide the public agency up to three days following the next duly publicly noticed meeting of the governing body to provide the claimant a written statement identifying the disputed portion and the undisputed portion. This bill would require any payment due on an undisputed portion of the claim to be processed and made within 30 days after the public entity issues its written statement; if the public entity fails to issue a written statement, the claim would be deemed rejected in its entirety. This bill , if the claimant disputes the public entity's written response, or if the public entity fails to respond to a claim issued within the time prescribed, would authorize the claimant to demand in writing an informal conference to meet and confer for settlement of the issues in dispute, and, upon receipt of a demand in writing sent by registered mail, the public entity would be required to schedule a meet and confer conference within 30 days for settlement of the dispute. This bill , within five days following the conclusion of the meet and confer conference, if the claim or any portion of the claim remains in dispute, would require the public entity to provide the claimant a written statement identifying the portion of the claim that remains in dispute and the portion that is undisputed. This bill would require any payment due on an undisputed portion of the claim to be processed and made within 30 days after the public entity issues its written statement, and any disputed portion of the claim, as identified in writing, would be required to be submitted to nonbinding mediation, with the public entity and the claimant sharing the associated costs equally. This bill would require the public entity and claimant to mutually agree to a mediator within 10 days after the disputed portion of the claim has been identified in writing, and, if the parties cannot agree upon a mediator, each party would select a mediator and those mediators would select a qualified neutral third party to mediate with regard to the disputed portion of the claim. AB 1347 (Chiu) Page 10 of ? This bill would provide that if either of the parties rejects the mediator's decision regarding all or part of the disputed portion of the claim, the parts of the claim remaining in dispute would be subject to other applicable claim resolution procedures. This bill would specify that mediation includes any nonbinding process, such as neutral evaluation or a dispute review board, in which an independent third party or board assists the parties in dispute resolution through negotiation or by issuance of an evaluation, and any mediation utilized must conform to the time frames provided in this bill. This bill would require the mediation conducted pursuant to this bill to excuse any further obligation to mediate (meet and confer) after litigation has been commenced. This bill would not preclude an agency from requiring arbitration of disputes under private arbitration or the Public Works Contract Arbitration Program, if mediation does not resolve the parties' dispute. This bill would specify that failure by the public entity to respond to a claim from a contractor within the time period described would result in the claim being deemed rejected in its entirety. This bill would require amounts not paid in a timely manner to bear interest at 7 percent per annum. This bill , if a subcontractor or a lower tier subcontractor lacks legal standing to assert a claim against a public entity because privity of contract does not exist, would authorize the contractor to present to the public entity a claim on behalf of a subcontractor or lower tier subcontractor. This bill would authorize a subcontractor to request in writing, either on his or her own behalf or on behalf of a lower tier subcontractor, that the contractor present a claim for work which was performed by the subcontractor or by a lower tier subcontractor on behalf of the subcontractor. This bill would require the subcontractor requesting that the claim be presented to the public entity to furnish reasonable documentation to support the claim. AB 1347 (Chiu) Page 11 of ? This bill , within 45 days of receipt of that written request, would require the contractor to notify the subcontractor in writing as to whether the contractor presented the claim to the public entity and, if the original contractor did not present the claim, provide the subcontractor with a statement of the reasons for not having done so. This bill would require the text of the provisions provided under this bill or a summary of it to be set forth in the plans or specifications for any public works that may give rise to a claim under this bill. This bill would make a waiver of the rights granted by this bill void and contrary to public policy. This bill would apply to contracts entered into on or after January 1, 2016. This bill would find and declare that it is in the best interests of the state and its citizens to ensure that all construction business performed on public works in the state that is complete and not in dispute is paid in full and in a timely manner. COMMENT 1. Stated need for the bill The author writes: There is no law in place requiring agencies to pay claims, in a timely manner, made by contractors for extra work performed and approved by the agency, even when the public agency acknowledges that it owes the contractor for work performed. This places contractors and their workers in difficult financial circumstances. Furthermore, there is a lack in uniformity for disputing a claim. In many cases, some public agencies have no requirements to respond to a claim or respond to a claim in a timely manner. The breakdown of communication between the public agency and the contractor adds to the burden on the contractor and meeting their payroll obligations. AB 1347 (Chiu) Page 12 of ? AB 1347 creates a process that requires agencies to respond to a contractor's claim, to pay out portions of the work they acknowledge and agree they owe the contractor, and to resolve disputed portions of payment through non-binding mediation. Specifically, the bill would require a public agency to respond in 30 days to a claim. If the public agency does not respond within 30 days then the claim is deemed denied. If the contractor wishes to continue the claim, then the contractor must respond via registered mail. The public agency then has 30 days to meet & confer with the contractor. If there is no agreement with the claim then the public agency has 10 days to find a mutually agreed upon mediator. The public agency has 30 days to pay for any undisputed portions of the claim. 2. Public works contracts and change orders Change orders are at the heart of the controversy involving this bill. When a public work requires extra work unanticipated by the contractor, a change order may be necessary, signed by the public agency and the contractor, to amend the contract to provide that the contractor is performing additional work for which the public agency will pay. When a change order is not executed by the public agency, or its governing body or responsible department, the contractor, having provided the necessary extra work or materials, submits a claim to the public agency alleging the public agency owes the contractor payment for the extra work. Several cases provide the responsibilities of the contracting parties that emerge when a public work requires additional material or services than originally expected by the contractor. First, case law has established that "a contractor that has agreed to a particular performance at a specified price may not avoid its contractual obligations or seek additional compensation for performing them because unanticipated difficulties are encountered." (United States v. Spearin (1918) 248 U.S. 132, 136.) However, case law has also settled that a "contractor of public works who, acting reasonably, is misled by incorrect plans and specifications issued by the public authorities as the basis for bids and who, as a result, submits a bid which is lower than he would have otherwise made may recover in a contract action for extra work or expenses necessitated by the conditions being other than as represented." AB 1347 (Chiu) Page 13 of ? (Suiza & McCue Constr. Co. v. Superior Court (1962) 57 Cal.2d 508, 510.) Although Public Contract Code Section 7104 requires change orders related to unanticipated difficulties from site conditions to be included in public work contracts, there is no statute requiring change orders resulting from other kinds of unanticipated conditions to be included in public work contracts. Specifically, case law has established that there are two types of differing site conditions that a public entity cannot circumvent or otherwise disclaim liability for through other provisions in the contract: (1) Type 1 differing site conditions, in which the actual site conditions differ from those originally described to bidders; and (2) Type 2 differing site conditions, in which the actual site conditions differ from the conditions ordinarily encountered in the particular type of work in the particular locality. (Condon-Johnson & Associates v. Sacramento Municipal Utility District (2007) 149 Cal.App.4th 1384.) For other unanticipated difficulties not associated with the site conditions for which a change order is not executed, the contractor is left to file a claim for the work performed. 3. Providing informal procedures to submit claims to public agency Existing law prescribes various requirements regarding the formation, content, and enforcement of state and local public contracts. Existing law applicable to state public contracts generally requires that the resolution of claims related to those contracts be subject to arbitration. Existing law for local agency public works requires all claims made for work arising out of the contract, but not expressly provided for in that contract, that are $375,000 or less to first be resolved through administrative resolution procedures. However, if the contract provides for arbitration, the claim will have to be arbitrated according to express arbitration statutes. The arbitration statutes apply to both local agency and state agency public work contracts. This bill would prescribe a new claims resolution process by which a contractor can submit a claim to a public entity as follows: applies to all claims submitted by a contractor to a public entity, as specified; the contractor must furnish reasonable documentation to support the claim; the public entity must conduct a reasonable review of the AB 1347 (Chiu) Page 14 of ? claim and, within 30 days, provide the contractor with a written statement identifying what portion of the claim is disputed and what portion is undisputed; the time frame may be extended for public entities that need approval from its governing body; any payment due on an undisputed portion of the claim must be processed and made within 30 days of issuance of the written statement; if no statement is issued by the public agency, the claim is rejected in its entirety; the claimant may demand an informal meet-and-confer conference for settlement of the issues in dispute; and establishes time frames for payment of settled claims and provide for nonbinding mediation for disputed claims. Proponents of this bill state that existing laws protect public agencies from having to pay any unfair or unjust claims made by a contractor. However, proponents argue, these conflict resolution statutes do not require the public agency to pay contractors in a timely manner for extra work performed on public works contracts, even when that work was requested by the owner and subsequently performed by the contract in good faith. Proponents contend that "contractors who perform extra work put themselves in great financial risk. California public works contractors often have to wait months, and in some cases up to years, for payment for work. Contractors who perform this work to the benefit of the public agency must still pay for their construction materials, employee wages and benefits and their overhead. Not being compensated in a timely manner can result in a contractor being forced to reduce capacity, or worse, close their business." Proponents contend that this bill would put a process in place that requires public agencies to respond to a contractor claim, would require the agency to pay out portions of the work they acknowledge or agree they owe to the contractor, and implements a fair process for resolving any disputed portions of the claim. The proponents note that this bill does not require public agencies to pay for any work it does not request, accept, or approve but allows the public agency to deny or dispute any claim for payment. Yet, the delay of trust fund contributions with respect to trade unions can cause the loss of health insurance due to a contractor's inability to make payments, and the lack of prompt payment for extra work leaves many contractors without the necessary resources needed to bid the AB 1347 (Chiu) Page 15 of ? next project and continue doing business, which ultimately diminishes work opportunities. 4. Providing clarity for subcontractor pass-through claims On public work projects, the public entity typically contracts directly with a general contractor to perform the work. The general contractor then contracts with subcontractors, such as roofers, excavators, and plumbers, who perform specialized work on the project. In this way, a subcontractor does not have a direct contract with the public agency and therefore lacks privity of contract. Accordingly, the subcontractor seeking payment on extra work performed must rely on one of a few methods for payment. First, the subcontractor may attempt to recover payment from the general contractor. However, depending upon the public agency's position on which party is responsible for the extra work needed to continue or complete the project, the public agency may have failed to pay the general contractor for extra work, and the general contractor may be unable to pay the subcontractor for the extra work. Second, the subcontractor may submit a stop notice to the public entity to withhold a portion of the construction funds sufficient to satisfy the subcontractor's claim. Rather than attaching to real property, the stop notice attaches to the construction loan fund, or to money in the hands of the public entity that otherwise is to be paid to the general contractor. The stop notice has the effect of intercepting these funds, and the ultimate result of the enforcement of a stop notice is entry of a judgment against the public agency for the amount claimed in the stop notice. This procedure is not preferred as it does not provide payment to the subcontractor in a timely fashion. As discussed above, a subcontractor who is unable to recover payment for work or materials provided in a good faith effort to keep the public project moving forward or reaching completion puts himself or herself at risk if the payment is necessary to pay employees, purchase materials, or bid on other contracts. Another method for recovering payment is to request the claim be presented to the public agency through the general contractor, known as a "pass-through" claim. Case law provides that "[a]s a matter of law, a general contractor can present a subcontractor's claim on a pass-through basis. (Maurice L. AB 1347 (Chiu) Page 16 of ? Bein, Inc. v. Housing Authority (1958) 157 Cal.App.2d 670. . . .) When a public agency breaches a construction contract with a contractor, damage often ensues to a subcontractor. In such a situation, the subcontractor may not have legal standing to assert a claim directly against the public agency due to a lack of privity of contract, but may assert a claim directly against the general contractor. In such a case, a general contractor is permitted to present a pass-through claim on behalf of the subcontractor against the public agency. (Citation omitted.)" (Howard Contracting, Inc. v. G.A. MacDonald Construction Co., Inc. (1998) 71 Cal.App.4th 38, 60.) In the Howard case, the City of Los Angeles was held to have failed to disclose material information to the general contractor and its subcontractors concerning project restrictions and difficulties, failed to timely obtain construction permits from regulatory agencies, and failed to provide access to the work site. (Id. at p. 48.) The Howard case provides a poignant example of the types of situations in which the general contractor and subcontractor has performed their duties under their respective contracts in good faith, yet the public agency created delays that required the extra work performed, then failed and refused to pay the general contractor work performed, who had then failed to pay the subcontractor. In these situations, the quickest method for a subcontractor to receive payment for extra work performed is to request that the general contractor submit the claim for payment to the public agency. Although a subcontractor can already attempt this line of recourse, the general contractor is under no obligation to submit the claim to the public agency. Further, the general contractor, who may also be attempting to recover payment for extra work from the public agency, may decide against submitting the claim in order to maintain positive communication with the public agency. The general contractor is under no obligation to advise the subcontractor whether or not the claim was submitted to the public agency for payment. Accordingly, this bill would allow the subcontractor to submit the claim through the general contractor, but establish a timeframe of 45 days of receipt of the written request for the general contractor to notify the subcontractor whether the general contractor presented the claim to the public agency. Further, if the general contractor opted against presenting the claim to the public agency, the bill would require the general contractor to provide the subcontractor a statement of reasons for not presenting the claim. These provisions would provide better clarity of the AB 1347 (Chiu) Page 17 of ? claim review process and important claim information for general contractors and subcontractors. 5. "Home Rule" Doctrine The California Constitution, Article XI, Section 7, provides that a county or city may make and enforce within its limits all local, policy, sanitary, and other ordinances and regulations not in conflict with general laws. However, a charter city is provided the ability to make and enforce all ordinances and regulations in respect to municipal affairs, subject only to restrictions and limitations provided in its several charters, and, in respect to other matters, the charter city is subject to general laws. (Cal. Const., art. XI, sec. 5.) A city charter or municipal law which may have precedence over a conflicting state statute purporting to regulate a municipal matter is known as the "home rule" doctrine. In Dibbs v. County of San Diego (1994) 8 Cal.4th 1200, the California Supreme Court in contracting the home rule authority of charter cities and chartered counties stated that, whereas charter county "home rule" authority is limited to matters concerning the structure and operation of local government, the version of "home rule" afforded to a charter city is substantially more expansive. However, the California Constitution does not define what constitutes a municipal affair. Accordingly, courts must determine whether the facts of each case implicate a matter under municipal or state concern. (County of Riverside v. Superior Court (2003) 30 Cal.4th 278, 292.) The "home rule" doctrine becomes important in a public work if the public agency is a charter city asserting that a state statute does not apply to the charter city. Such was the case in Howard Contracting, Inc. v. G.A. MacDonald Construction Co. (1998) 71 Cal.App.4th 38, 51, in which the City of Los Angeles claimed not to be subject to a state law interfering with the City's public work contract. At issue was Public Contract Code Section 7102, which provides that contract provisions in public works construction contracts, and the subcontracts thereunder, which attempt to limit the public entity's liability for delays it causes, do not preclude the recovery of damages by the contractor or subcontractor. The statute also provides that a public agency cannot require the waiver, alteration, or limitation of the applicability of this section. However, the AB 1347 (Chiu) Page 18 of ? statute cannot be construed to void any provision in a public works construction contract that requires notice of delays or provides for liquidated damages. In the Howard case, the court discussed the City's claim under the home rule doctrine of immunity from liability for damages caused by its own delays: In California Federal, the Supreme Court established a test to determine whether the state has infringed upon a charter city's sovereignty under the "home rule" doctrine. (54 Cal. 3d at pp. 16-18.) Under the first prong of the test, the existence of an actual conflict between a state statute and a local measure must be ascertained. Once a conflict is found to exist, a further determination must be made whether the subject matter of the statutory enactment is more properly characterized as a local or statewide concern. In this case, the purported conflict with a provision of a state statute does not relate to a charter provision or municipal enactment, but to a "no damage for delay" clause contained in the Standard Specifications of the contract between MacDonald Construction and the City. Because the City fails to establish a conflict between the Public Contract Code and any charter provision or municipal enactment, Public Contract Code section 7102 applies. As a consequence, the contract clause purporting to exempt the City from liability for damages resulting from delays caused by the City is unenforceable under section 7102. (Id.) Because the Howard case established that charter city public work contracts are subject to state statutes under the Public Contract Code, the provisions in this bill would likely not be superseded by a city's charter or municipal laws because the provisions of the bill involve a statewide concern, are not solely aimed at regulating charter cities, and the bill's provisions likely do not relate to a city's charter or municipal laws but rather relate to public work contracts and obligations thereon. 6. Author's amendment This bill provides a definition of "public work" that is defined as a "public works contract." A public work is typically the project to build, alter, or repair a building, road, structure, AB 1347 (Chiu) Page 19 of ? or other public improvement, while a public works contract is the document reflecting the agreement between a public agency and, in this case, a contractor. Although the definition is similar to that contained in Public Contract Code Section 20104, which is not revised by this bill, this bill should be amended to provide a clearer definition of "public work." Accordingly, the author offers the following amendment in Committee to clarify the definition of "public work:" Author's amendment : On page 3, in lines 32 through 33, strike ""public works contract" as defined in Section 1101" and insert "the erection, construction, alteration, repair, or improvement of any public structure, building, road, or other public improvement of any kind." 7. Opposition concerns This bill was recently amended to address multiple concerns and several prior opponents have now taken neutral positions on this bill. However, the California Chapters of the American Public Works Association and the California School Boards Association submitted letters in opposition following the recent amendments. These opponents contend that this bill places a difficult 30-day time restriction to respond to claims received from contractors and will have a negative impact on taxpayers as it will divert limited local government monies away from road safety and maintenance projects by shifting the liability to local governments and the cost onto taxpayers. Opponents also argue that this bill requires disputed claim amounts to be identified within a cumbersome 30-day time frame and requires that interest on those amounts be assessed. Further, opponents argue that this bill requires all construction projects to use non-binding mediation since nearly all construction projects have a least one claim in dispute and will create another cost for which there is no funding source. Opponents contend that this bill allows lower-tier subcontractors to make claims, which creates an untenable increased risk to public agencies on matters that are under the direct supervision and legal responsibility of the prime contractor. The opposition notes that this bill requires that the text of the bill appear on plans and specifications, yet no other requirement exists to place the text of state law on AB 1347 (Chiu) Page 20 of ? contract plans. Opponents also contend that Caltrans expects it would need several dozen more personnel at an annual cost exceeding $10 million and other agencies (the Departments of General Services, Water Resources, and Corrections and Rehabilitation, the University of California, and the California State University) could experience similar impacts from this bill. The Santa Clara Valley Water District (SCVWD), opposed unless amended, argues that the current dispute resolution process between a public entity and a general contractor or subcontractor works to the benefit and protection of both parties. Further, SCVWD states existing law requires contractors to certify any claim, but this bill merely calls for reasonable documentation to support the claim, a much lower standard. SCVWD requests the bill to be amended to clarify that all parties to the non-binding mediation share equally in the cost of the mediation, unless they agree otherwise, and require a claimant to comply with all other requirements set forth in the construction contract with the owner. In response, the author points out that several groups, including the California State Association of Counties, the California Special Districts Association, California's Coalition for Adequate School Housing, the Community College Facility Coalition, and the County School Facilities Consortium, previously in opposition to a prior version of the bill, now contend that the latest version of the bill provides public agencies appropriate time and control to review claims for work performed under a public contract prior to payment to a contractor. In particular, the now-neutral groups agree that the provision deeming a claim rejected in its entirety when a public agency fails to respond to the claim will ensure counties and claimants meet and confer and enter into non-binding mediation before the agency is required to pay disputed claims. Further, the decreased interest rate from 10 percent to 7 percent was appropriate, and this compromise rate will still be an effective incentive for public agencies to pay undisputed claims within the timelines prescribed by this bill. Support : Air Conditioning Sheet Metal Association; Air-Conditioning & Refrigeration Contractors Association; Associated General Contractors; Associated General Contractors, California Chapters; Associated Plumbing & Mechanical AB 1347 (Chiu) Page 21 of ? Contractors; California Association of Sheet Metal and Air Conditioning Contractors' National Association; California Landscape & Irrigation Council; California Legislative Conference of the Plumbing, Heating and Piping Industry; California Plumbing and Mechanical Contractors Association; California State Association of Electrical Workers; California State Pipe Trades Council; Finishing Contractors Association of Southern California; Northern California Mechanical Contractors Association; Small Business California; Southern California Contractors Association; Union Roofing Contractors Association; Wall and Ceiling Alliance; Western States Council of Sheet Metal Workers Opposition : California Chapters of the American Public Works Association; California School Boards Association; City of Camarillo (prior version); City of Indian Wells (prior version); City of San Carlos (prior version); Orange County Transportation Authority Board of Directors (prior version); Santa Clara Valley Water District HISTORY Source : California Chapters of the National Electrical Contractors Association; California-Nevada Conference of Operating Engineers; California State Council of Laborers; State Building and Construction Trades Council of California; United Contractors Related Pending Legislation : None Known Prior Legislation : AB 2471 (Frazier, 2014) would have required state and local public entities engaged in a public works contract awarded to the lowest bidder to promptly issue change orders when extra work is required of the contractor or subcontractor. AB 2471 died in the Senate Appropriations Committee without a hearing. AB 2096 (Miller, 2010) would have allowed a public agency and a contractor to mutually agree to resolve a claim through independent arbitration. AB 2096 died in the Assembly Judiciary Committee without a hearing. AB 541 (Duvall, 2009) was substantially similar to AB 2096 and died in the Assembly Judiciary Committee without a hearing. AB 1347 (Chiu) Page 22 of ? AB 216 (Beall, 2009) would have reformed pre-litigation claims resolution procedures for local public works projects. AB 216 was held under submission in the Assembly Appropriations Committee. SB 1642 (Yee, 2008) would have established alternative dispute resolution procedures for local public works projects costing over $50,000. SB 1642 was held under submission in the Senate Appropriations Committee. Prior Vote : Assembly Floor (Ayes 76, Noes 0) Assembly Appropriations Committee (Ayes 15, Noes 2) Assembly Accountability and Administrative Review Committee (Ayes 9, Noes 0) **************