BILL ANALYSIS                                                                                                                                                                                                    Ó





                             SENATE JUDICIARY COMMITTEE
                         Senator Hannah-Beth Jackson, Chair
                             2015-2016  Regular Session


          AB 1963 (Calderon)
          Version: April 4, 2016
          Hearing Date: June 14, 2016
          Fiscal: No
          Urgency: No
          TH   


                                        SUBJECT
                                           
                 Common Interest Developments: Construction Defects

                                      DESCRIPTION 

          Existing law requires, until July 1, 2017, a homeowner  
          association in a common interest development of more than 20  
          units to follow a pre-litigation dispute resolution procedure  
          before commencing a design or construction defect action against  
          a builder, developer, or general contractor.  This bill would  
          extend the above sunset date to July 1, 2024.

                                      BACKGROUND  

          In California, residential common interest developments (CIDs)  
          are governed by the Davis-Stirling Common Interest Development  
          Act (Davis-Stirling Act).  Owners of separate property in a CID  
          have an undivided interest in the common property of the  
          development and are subject to the CID's covenants, conditions,  
          and restrictions.  Residential CIDs are governed by a homeowner  
          association, which is run by volunteer directors that may or may  
          not have prior experience managing an association.  

          In 1995, the Davis-Stirling Act was amended to require homeowner  
          associations to take part in specified pre-litigation dispute  
          resolution procedures before commencing a design or construction  
          defect action against the builder, developer, or general  
          contractor of the CID.  (See SB 1029, Calderon, Ch. 864, Stats.  
          1995; Civ. Code Sec. 6000.)  According to the Senate Judiciary  
          Committee analysis of that bill:









          AB 1963 (Calderon)
          Page 2 of ? 

            The author has introduced [SB 1029] because in many instances,  
            expensive and time-consuming litigation alleging defects in  
            the design or construction of common interest developments are  
            commenced before the parties have a reasonable opportunity to  
            discuss the merits of the claim, or to consider alternative  
            proposals to resolve the claim.  The author believes that the  
            initiation of such litigation prior to a meaningful  
            opportunity for the parties to meet and confer is detrimental  
            because of the substantial costs to both parties, and to the  
            courts, of complex construction defect litigation which in  
            many instances could be avoided.  (Sen. Com. on Judiciary,  
            Analysis of Sen. Bill No. 1029 (1995-1996 Reg. Sess.) as  
            amended Mar. 29, 1995, p. 7 [for hearing on May 9, 1995].)

          In 2001, the Act was further amended to require an association  
          to serve a "Notice of Commencement of Legal Proceedings" on the  
          respondent builder, developer, or general contractor, including  
          an initial list of defects sufficient to apprise the respondent  
          of the general nature of the defects at issue, and also  
          specified timelines and procedures for parties to follow during  
          the pre-litigation dispute resolution process.  (See AB 1700,  
          Steinberg, Ch. 824, Stats. 2001.)  AB 1700 included a sunset  
          provision that would have rendered the CID pre-litigation  
          dispute resolution requirement inoperative on July 1, 2010.  In  
          2009, AB 927 (Calderon, Ch. 7, Stats. 2009) extended the  
          effective date of the CID pre-litigation dispute resolution  
          requirement to July 1, 2017, and repeals the requirement on  
          January 1, 2018, unless a later enacted statute deletes or  
          extends these dates.

          This bill would extend until July 1, 2024, the requirement that  
          homeowner associations take part in the pre-litigation dispute  
          resolution process, and would repeal this requirement on January  
          1, 2025, unless a later enacted statute deletes or extends these  
          dates.

                                CHANGES TO EXISTING LAW
           
           Existing law  , the Davis-Stirling Common Interest Development  
          Act, defines and regulates residential common interest  
          developments (CIDs), including the ability of the association to  
          levy regular and special assessments sufficient to perform its  
          obligations.  (Civ. Code Sec. 4000 et seq.)

           Existing law  requires, before an association files a complaint  







          AB 1963 (Calderon)
          Page 3 of ? 

          for damages against a builder, developer, or general contractor  
          (respondent) of a common interest development based upon a claim  
          for defects in the design or construction of the common interest  
          development, certain specified requirements to be satisfied.   
          (Civ. Code Sec. 6000 et seq.)

           Existing law  requires an association to serve upon the  
          respondent a "Notice of Commencement of Legal Proceedings,"  
          indicating the name and location of the project, an initial list  
          of defects sufficient to apprise the respondent of the general  
          nature of the defects at issue, a description of the results of  
          the defects, if known, a summary of the results of a survey or  
          questionnaire distributed to homeowners to determine the nature  
          and extent of defects, if a survey has been conducted or a  
          questionnaire has been distributed, and either a summary of the  
          results of testing conducted to determine the nature and extent  
          of defects or the actual test results, if that testing has been  
          conducted. (Civ. Code Sec. 6000(b).)
           Existing law  specifies that service of the notice shall commence  
          a period, not to exceed 180 days, during which the association,  
          the respondent, and all other participating parties shall try to  
          resolve the dispute through a specified process, and states that  
          service of the notice shall toll all applicable statutes of  
          limitation and repose, whether contractual or statutory, by and  
          against all potentially responsible parties, regardless of  
          whether they were named in the notice, including claims for  
          indemnity.  (Civ. Code Sec. 6000(b), (c).)

           Existing law  states that, upon receipt of the notice, the  
          respondent shall provide the association with access to  
          specified information for the project reasonably calculated to  
          lead to the discovery of admissible evidence regarding the  
          defects claimed within 60 days.  (Civ. Code Sec. 6000(e).)

           Existing law  states that within 20 days of sending the notice,  
          the association, respondent, subcontractors, design  
          professionals, and their insurers shall meet and confer in an  
          effort to select a dispute resolution facilitator to preside  
          over the specified mandatory dispute resolution process.  (Civ.  
          Code Sec. 6000(f).)

           Existing law  provides, among other things, that the respondent  
          may submit to the association a request to meet with the board  
          to discuss a written settlement offer.  If the board rejects a  
          settlement offer presented at the meeting, the board shall hold  







          AB 1963 (Calderon)
          Page 4 of ? 

          a meeting open to each member of the association no less than 15  
          days before the association commences an action for damages  
          against the respondent.  No less than 15 days before this  
          meeting is held, a written notice shall be sent to each member  
          of the association specifying all of the following:
           that a meeting will take place to discuss problems that may  
            lead to the filing of a civil action, and the time and place  
            of this meeting;
           the options that are available to address the problems,  
            including the filing of a civil action and a statement of the  
            various alternatives that are reasonably foreseeable by the  
            association to pay for those options and whether these  
            payments are expected to be made from the use of reserve  
            account funds or the imposition of regular or special  
            assessments, or emergency assessment increases; and
           the complete text of any written settlement offer, and a  
            concise explanation of the specific reasons for the terms of  
            the offer received from the respondent.  (Civ. Code Sec.  
            6000(k).)

           Existing law  states that all defect lists and demands,  
          communications, negotiations, and settlement offers made in the  
          course of the pre-litigation dispute resolution process shall be  
          inadmissible, as specified.  (Civ. Code Sec. 6000(l).)

           Existing law  states that any party may at any time petition the  
          superior court in the county where the project is located, upon  
          a showing of good cause, to resolve a dispute or make a  
          determination, as specified.  (Civ. Code Sec. 6000(n).)

           Existing law  states that the pre-litigation dispute resolution  
          process shall become inoperative on July 1, 2017, and, as of  
          January 1, 2018, is repealed, unless a later enacted statute,  
          that becomes operative on or before January 1, 2018, deletes or  
          extends the dates on which it becomes inoperative and is  
          repealed.  (Civ. Code Sec. 6000(s).)

           This bill  extends the above sunset date by seven years, stating  
          that the pre-litigation dispute resolution process shall become  
          inoperative on July 1, 2024, and, as of January 1, 2025, is  
          repealed, unless a later enacted statute, that becomes operative  
          on or before January 1, 2025, deletes or extends the dates on  
          which it becomes inoperative and is repealed.
          
                                        COMMENT







          AB 1963 (Calderon)
          Page 5 of ? 

           
           1.Stated need for the bill  

          According to the author:

            Before a homeowner's association may file a complaint for  
            damages against a builder, developer, or general contractor of  
            a [common interest development] based upon a claim for defects  
            in the design or construction of the development, the  
            association must first engage in the extensive pre-litigation  
            process specified by Civil Code Section 6000, under the  
            Davis-Stirling Act.  This process was initially established by  
            the Legislature in 1995, and since then has been revised and  
            reauthorized twice before for seven-year trial periods, the  
            last one of which ends on July 1, 2017.  This process is also  
            referred to as the "Section 6000 process" and requires among  
            other things:
                 the plaintiff to provide notice;
                 within 25 days, the respondent may request a meeting  
               with the [association] board of directors within 10 days;
                 the association and respondent to exchange information  
               about the defect within 60 days of the notice;
                 the respondent to provide notice to subcontractors,  
               design professionals, and insurers within 60 days of the  
               notice;
                 within 20 days of the notice to subcontractors, that all  
               parties meet to select a mediator and establish a procedure  
               to request the court to select a mediator if they cannot  
               agree; and
                 mediation costs to be split equally.

            AB 1963 would extend the sunset for the "Section 6000"  
            pre-litigation process for an additional seven years.  It  
            encourages disputes about construction defects in common  
            interest developments to be settled or sent to alternative  
            dispute resolution before a lawsuit is filed.  This process  
            has worked for the last twenty years, by providing an avenue  
            for dispute resolution prior to costly and time-consuming  
            lawsuits.  In an era of overcrowded court dockets, the  
            Legislature should act to preserve a process that relieves  
            some of this pressure on our already overburdened courts.  AB  
            1963 will ensure that homeowners and builders are able to  
            continue to resolve disagreements in a cost effective manner  
            that is careful to preserve the legal options of those  
            involved.







          AB 1963 (Calderon)
          Page 6 of ? 


           1.Pre-litigation Dispute Resolution Process  

          Existing law establishes a pre-litigation dispute resolution  
          process that must be followed prior to an association filing a  
          lawsuit against a builder, general contractor, or developer of a  
          common interest development with 20 or more units regarding  
          claims for defects in the design or construction of the  
          development.  While the dispute resolution process is ongoing,  
          the statute of limitation on the association's claim or claims  
          is tolled, generally for a period of 180 days, unless the  
          parties agree to extend the process beyond 180 days.  The five  
          general steps of this process are described below.

           Step 1  :  Before filing suit, the association must give written  
          notice to the builder.  This notice, denoted a "Notice of  
          Commencement of Legal Proceedings," must include, among other  
          things:
           an initial list of defects sufficient to apprise the  
            respondent of the general nature of the defects at issue; and
           either a summary of the results of testing conducted to  
            determine the nature and extent of defects or the actual test  
            results, if that testing has been conducted.

          Service of the notice commences a period, not to exceed 180 days  
          unless extended by the parties, during which the association,  
          the respondent, and all other participating parties try to  
          resolve the dispute through the process.

           Step 2  :  Within 25 days, the respondent may request in writing  
          to meet and confer with the association, which meeting must take  
          place 10 days after the request.  Upon receipt of the notice,  
          the respondent must, within 60 days, provide the association  
          with specified information pertaining to the project that may  
          lead to evidence concerning the defects claimed by the  
          association.  Likewise, the association must provide the  
          respondent with specified information concerning the defects  
          claimed by the association, such as reserve studies, maintenance  
          records, and test results.

          The respondent must also provide written notice by certified  
          mail to all subcontractors, design professionals, their  
          insurers, and the insurers of any additional insured whose  
          identities are known to the respondent or are readily  
          ascertainable and whose potential responsibility appears on the  







          AB 1963 (Calderon)
          Page 7 of ? 

          face of the notice.  This notice must include a copy of the  
          Notice of Commencement of Legal Proceedings, and must specify  
          the date and manner by which the parties shall meet and confer  
          to select a dispute resolution facilitator.

           Step 3:   Within 20 days of sending the above notice, the  
          association, respondent, subcontractors, design professionals,  
          and their insurers must meet and confer in an effort to select a  
          dispute resolution facilitator to preside over a mandatory  
          dispute resolution process.  Once selected, the dispute  
          resolution facilitator and the participating parties agree to a  
          date, time, and location to hold a case management meeting of  
          all parties to discuss the claims being asserted and the  
          scheduling of events in the process.

          The costs of the dispute resolution facilitator are apportioned  
          among the parties as follows: one-third to be paid by the  
          association; one-third to be paid by the respondent; and  
          one-third to be paid by the subcontractors and design  
          professionals, as allocated among them by the dispute resolution  
          facilitator.  The costs of the dispute resolution facilitator  
          are recoverable by the prevailing party in any subsequent  
          litigation.

           Step 4:  No later than the case management meeting, the parties  
          must begin to generate data showing the following information  
          regarding the alleged defects:
           the scope of the work performed by each potentially  
            responsible subcontractor;
           the tract or phase number in which each subcontractor provided  
            goods or services, or both; and
           the units, either by address, unit number, or lot number, at  
            which each subcontractor provided goods or services, or both.

          At the case management meeting, the parties must come to an  
          agreement on several issues with regard to resolving the  
          dispute, including:
           the provision of a detailed list of defects by the association  
            to the respondent after the association completes a visual  
            inspection of the project;
           invasive testing conducted by the association, respondent, or  
            other party, if deemed appropriate;
           provision by the association of a comprehensive demand which  
            provides sufficient detail for the parties to engage in  
            meaningful dispute resolution; and







          AB 1963 (Calderon)
          Page 8 of ? 

           facilitated dispute resolution of the claim, with all parties  
            present and having settlement authority.

           Step 5:   After the selection of a dispute resolution  
          facilitator, and at his or her determination, the respondent may  
          submit to the association a request to meet with the board to  
          discuss a written settlement offer.  No less than 10 days after  
          the respondent submits required settlement information to the  
          association, the respondent and the board must meet and confer  
          about the settlement offer.  If the board rejects the settlement  
          offer, the board must hold a meeting open to each member of the  
          association no less than 15 days before the association  
          commences an action for damages against the respondent.  Fifteen  
          days prior to that open meeting, the board must send the  
          following to each member of the association:
           notice that an open meeting will take place to discuss  
            problems that may lead to the filing of a civil action, and  
            the time and place of the meeting;
           options available to address the problems identified,  
            including the filing of a civil action and a statement of the  
            various alternatives to pay for those options and whether  
            these payments are expected to be made from the use of reserve  
            account funds or the imposition of regular or special  
            assessments, or emergency assessment increases; and
           the text of any written settlement offer, and a concise  
            explanation of the specific reasons for the terms of the  
            offer.

          The respondent is obligated to pay all expenses attributable to  
          sending the settlement offer to members of the association, and  
          for the expense of holding the meeting, up to a specified limit.

          At any point during the pre-litigation dispute resolution  
          process, any party may petition the superior court to resolve a  
          dispute concerning the process, including disagreements relative  
          to the timing of specific events, or to the production of  
          documents or the exchange of information.

           1.Extension of Sunset Date  

          Under current law, the pre-litigation dispute resolution process  
          described in Comment 2 is scheduled to sunset on July 1, 2017.   
          This bill would extend that sunset date by seven years, delaying  
          its terminal date to July 1, 2024.  The California Land  
          Surveyors Association, writing in support, states:







          AB 1963 (Calderon)
          Page 9 of ? 


            The provisions of Section 6000 of the Civil Code set forth a  
            balanced procedure whereby a land surveyor or other party is  
            provided notice of intent to file construction defect  
            litigation and provided an opportunity to present facts to a  
            dispute resolution facilitator.  This pre-litigation process  
            not only results in the non-inclusion of a land surveyor in  
            subsequently filed litigation, but also expedites the court  
            time and expense necessary to try construction defect  
            litigation.  It is important for all parties to continue to  
            use the pre-litigation process in Section 6000.

          In the past, this Committee has raised concerns about imposing  
          mandatory pre-litigation dispute resolution procedures.  First,  
          procedures that are too complex or too time-consuming could  
          place an unfair obstacle in the path of a litigant - here, a  
          homeowner association - who seeks to vindicate its rights.   
          Second, mandatory pre-litigation procedures could be used as a  
          tool by defendants to make procedural objections and prevent a  
          court from ruling on the merits of a litigant's claim.  However,  
          it does not appear that these concerns are warranted with  
          respect to this particular pre-litigation dispute resolution  
          process for several reasons.  First, the process, by its terms,  
          must be completed within 180 days, unless the parties agree to  
          extend that period, and during that time all applicable statutes  
          of limitation are tolled.  Second, as described in Comment 2,  
          the process does not appear to be overly complex or difficult to  
          execute.  Finally, as noted in the Background, this particular  
          process has been in place, in varying forms, for at least 20  
          years, and during that time the Committee has not received any  
          significant indication that the process acts to frustrate the  
          vindication of rights, or that it has been abused by litigants  
          for procedural advantage.


           Support  :  American Subcontractors Association California, Inc.;  
          California Land Surveyors Association; California Professional  
          Association of Specialty Contractors; Community Associations  
          Institute; Construction Employers' Association

           Opposition  :  None Known

                                        HISTORY
           
           Source  :  California Building Industry Association







          AB 1963 (Calderon)
          Page 10 of ? 


           Related Pending Legislation  :  None Known

           Prior Legislation  :

          AB 927 (Calderon, Ch. 7, Stats. 2009) See Background.
          AB 1700 (Steinberg, Ch. 824, Stats. 2001) See Background.
          SB 1029 (Calderon, Ch. 864, Stats. 1995) See Background.

           Prior Vote  :

          Assembly Floor (Ayes 77, Noes 0)
          Assembly Judiciary Committee (Ayes 10, Noes 0)

                                   **************