BILL ANALYSIS                                                                                                                                                                                                    Ó



          SENATE COMMITTEE ON ENERGY, UTILITIES AND COMMUNICATIONS
                              Senator Ben Hueso, Chair
                                2015 - 2016  Regular 

          Bill No:          AB 1979           Hearing Date:    6/21/2016
           ----------------------------------------------------------------- 
          |Author:    |Bigelow                                              |
          |-----------+-----------------------------------------------------|
          |Version:   |5/23/2016    As Amended                              |
           ----------------------------------------------------------------- 
           ------------------------------------------------------------------ 
          |Urgency:   |No                     |Fiscal:      |Yes             |
           ------------------------------------------------------------------ 
           ----------------------------------------------------------------- 
          |Consultant:|Jay Dickenson                                        |
          |           |                                                     |
           ----------------------------------------------------------------- 
          
          SUBJECT: Renewable feed-in tariff:  hydroelectric facilities

            DIGEST:  This bill makes an exception to the feed-in-tariff  
          program three-megawatt limit on the generating capacity of an  
          eligible electric generation facility to newly allow  
          participation by a conduit hydroelectric facility with a  
          nameplate generating capacity of up to four megawatts that meets  
          certain conditions.

          ANALYSIS:
          
          Existing law:
          
          1)Requires all investor-owned utilities (IOUs) and publicly  
            owned utilities (POUs) that serve more than 75,000 retail  
            customers, to develop a standard contract or tariff (aka  
            feed-in-tariff or FIT) available for renewable energy  
            facilities up to three megawatts (MW).  Statewide  
            participation is capped at 750 MW.  (Public Utilities Code  
            §399.20 and 387.8)


          2)Directs the electrical corporations to develop standard  
            contract terms and conditions that reflect the operational  
            characteristics of the projects, and to provide a streamlined  
            contracting process.  (Public Utilities Code §399.20)


          3)Counts renewable energy generation FIT contracts to qualify  
            for credit toward and IOUs Renewable Portfolio Standard (RPS)  
            goals and resource adequacy requirements.  (Public Utilities  








          AB 1979 (Bigelow)                                     PageB of?
          
            Code §399.20)

          This bill:

          1)Creates an exception to the existing FIT program eligibility  
            limit of three MW to allow a conduit hydroelectric facility  
            with a nameplate generating capacity of up to four MW if the  
            conduit hydroelectric facility meets the following conditions:  


                 It delivers no more than three megawatts to the grid at  
               any time.
                 It complies with the electrical corporation's Electric  
               Rule 21 tariff or other distribution access tariff.
                 Payment is made pursuant to the FIT program no payment  
               is made for any deliveries in excess of three MW at any  
               time.
                 It was operational as of January 1, 1990, and is an  
               eligible renewable energy resource.

          1)Prohibits the California Public Utilities Commission (CPUC)  
            from reducing the MW limitation for a conduit hydroelectric  
            facility described above.

          Background

          Feed-in-tariff programs.  According to the National Renewable  
          Energy Laboratory (NREL), a FIT offers a guarantee of payments  
          to renewable energy developers for the electricity they produce.  
           NREL reports that FITs are used in many U.S. states and around  
          the world.<1>

          California, too, offers a FIT program to renewable resources.   
          In 2006, legislation<2> authorized the state's first FIT  
          program, which authorized the state's largest IOU's to purchase  
          up to 480 MW of renewable generating capacity from renewable  
          facilities with an "effective capacity" of not more than 1.5 MW.  
           The FIT program set the price paid to small generators, on a  
          first-come, first-served basis, at a price comparable to the  
          ---------------------------


          <1>  
          http://www.nrel.gov/tech_deployment/state_local_governments/basic 
          s_tariffs.html.
          <2> AB 1969 (Yee), Chapter 731, Statutes of 2006.








          AB 1979 (Bigelow)                                     PageC of?
          
          price of electricity generated using natural gas plus the value  
          of some environmental attributes. 


          Legislation expanded the state's FIT program in 2009.<3>  First,  
          the program limit was increased from 480 MW to 750 MW.  Second,  
          the cap on the size of an electric generation facility eligible  
          to participate in the FIT program was increased from 1.5 MW  
          effective capacity to three MW effective capacity.   This bill  
          notes that the Legislature finds and declares that small  
          projects of less than three MW that are otherwise eligible  
          renewable energy resources may face difficulties in  
          participating in competitive solicitations under the RPS  
          program. 


          Effective capacity versus nameplate capacity.  As described  
          above, existing statute limits participation in the bioenergy  
          FIT program to electric generation facilities with and  
          "effective capacity" of three MW.  Creates a conditional  
          exception to the existing FIT program eligibility limit of three  
          MW to allow a conduit hydroelectric facility with a "nameplate  
          generating capacity" of up to four MW.  So, what's the  
          difference between effective capacity and nameplate capacity?   
          The practical answer:  there is none.  The CPUC determined, in  
          Decision 12-05-035, that he three MW limitation corresponds to  
          the nameplate capacity of the facility, meaning the capacity  
          stamped on the metal nameplate attached to the generation  
          facility by the manufacturer.

          The problem of being a little bit too big.  Statute, in  
          legislative findings and declarations, provides a market-based  
          rationale for limiting participation in the FIT program to those  
          facilities with an effective capacity no more than three MW.   
          That is, statute declares that small projects of less than three  
          MW that are otherwise eligible renewable energy resources may  
          face difficulties in participating in competitive solicitations  
          under the RPS program.  


          Bill proponents do not object to the fundamental rationale  
          behind the FIT program's three-MW limit.  They do, however,  

          ---------------------------


          <3> SB 32 (Negrete-McLeod), Chapter 328, Statutes of 2009.








          AB 1979 (Bigelow)                                     PageD of?
          
          object to the exclusion of facilities that have a nameplate  
          capacity of greater than three MW but that are incapable of  
          exporting more than three MW to the grid.  As a particular  
          example, proponents point to the Utica Water & Power Authority  
          (UWPA), which owns and operates a small conduit hydroelectric  
          generator with a nameplate capacity of 3.6 MW.  Proponents  
          assert that, despite its nameplate capacity, the generator will  
          never produce more than three MW of electricity because of  
          existing water system constraints.


          This bill crafts a narrow exemption to the FIT program capacity  
          limitation for hydroelectric facilities like that UWPA's, as  
          characterized by bill proponents.  In fact, the exemption is so  
          narrowly crafted that it is unlikely that any facility other  
          than UWPA's will qualify for the exemption.  In any case, the  
          effect of the exemption should be minor from the perspective of  
          both ratepayers and grid operators. 


          Prior/Related Legislation
          
          AB 1969 (Yee, Chapter 731, Statutes of 2006) authorized the  
          state's first FIT program, which authorized the state's largest  
          IOU's to purchase up to 480 MW of renewable generating capacity  
          from renewable facilities with an effective capacity of not more  
          than 1.5 Ms.


          SB 32 (Negrete-McLeod, Chapter 328, Statutes of 2009) increased  
          the FIT program limit from 480 MW to 750 MW and increased from  
          1.5 MW effective capacity to three MW effective capacity the  
          limit on electric generating facilities eligible to participate  
          in the FIT program.


          SB 1112 (Rubio, Chapter 612, Statutes of 2012) required an  
          additional 250 MW of renewable FIT procurement from small-scale  
          bioenergy projects that commence operation on or after June 1,  
          2013.


          AB 1923 (Wood, 2016) would increase, from three MW nameplate to  
          five MW, the limit on the nameplate capacity of a bioenergy  
          electric generation facility that may participate in the IOU's  









          AB 1979 (Bigelow)                                     PageE of?
          
          bioenergy feed-in-tariff programs.  The bill is pending  
          consideration by this committee.


          FISCAL EFFECT:                 Appropriation:  No    Fiscal  
          Com.:             Yes          Local:          No


            SUPPORT:  

          Utica Water and Power Authority (Source)
          Calaveras County Supervisor, District 3
          Calaveras County Water District
          City of Angels Camp
          Murphys Sanitary District
          NLine energy

          OPPOSITION:

          Sierra Club California

          ARGUMENTS IN SUPPORT:    According to the author:

          Small hydroelectric generators with a nameplate of over three MW  
          are prohibited from participating in the FIT even though the  
          generator will never actually run above the three-MW threshold.   
          For example, the Utica Water & Power Authority owns and operates  
          a small conduit hydroelectric generator with a nameplate of 3.6  
          MW.  However, due to the existing water system, the generator  
          will never run above three MW.  In fact, it will likely never  
          run above 2.5 MW.  Despite this, the facility is ineligible to  
          participate in this important program aimed at promoting these  
          exact types of small renewable generators.  


          This bill will allow an existing conduit hydroelectric  
          generation facility to be eligible for the renewable FIT program  
          if it has a nameplate generating capacity of up to four MW but  
          does not operate above three MW, and was operational as of  
          January 1, 1990. 


          ARGUMENTS IN OPPOSITION:    According to the opponents, this  
          bill would allow larger hydroelectric generating facilities to  
          qualify for the renewable FIT while starving out other more  









          AB 1979 (Bigelow)                                     PageF of?
          
          truly renewable and environmentally sound projects.  It would  
          also increase workload at the CPUC for projects that are barely  
          renewable.


                                      -- END --