BILL ANALYSIS                                                                                                                                                                                                    Ó






           ----------------------------------------------------------------- 
          |SENATE RULES COMMITTEE            |                       AB 1979|
          |Office of Senate Floor Analyses   |                              |
          |(916) 651-1520    Fax: (916)      |                              |
          |327-4478                          |                              |
           ----------------------------------------------------------------- 


                                   THIRD READING 


          Bill No:  AB 1979
          Author:   Bigelow (R)
          Amended:  8/19/16 in Senate
          Vote:     21 

           SENATE ENERGY, U. & C. COMMITTEE:  10-0, 6/21/16
           AYES:  Hueso, Morrell, Cannella, Gaines, Hertzberg, Lara,  
            Leyva, McGuire, Pavley, Wolk
           NO VOTE RECORDED:  Hill

          SENATE APPROPRIATIONS COMMITTEE:  Senate Rule 28.8

           ASSEMBLY FLOOR:  72-0, 5/27/16 - See last page for vote

           SUBJECT:   Renewable feed-in tariff: hydroelectric facilities


          SOURCE:    Utica Water and Power Authority


          DIGEST:  This bill makes an exception to the feed-in-tariff  
          program three-megawatt limit on the generating capacity of an  
          eligible electric generation facility to newly allow  
          participation by a conduit hydroelectric facility with a  
          nameplate generating capacity of up to four megawatts that meets  
          certain conditions.
          
          Senate Floor Amendments of 8/19/16 avoid conflict with another  
          bill (the budget trailer bill) that amend the same code section  
          as this bill would have amended.  

          ANALYSIS:  









                                                                    AB 1979  
                                                                    Page  2


          Existing law:
          
          1)Requires all investor-owned utilities (IOUs) and publicly  
            owned utilities (POUs) that serve more than 75,000 retail  
            customers, to develop a standard contract or tariff (aka  
            feed-in-tariff or FIT) available for renewable energy  
            facilities up to three megawatts (MW).  Statewide  
            participation is capped at 750 MW.  (Public Utilities Code  
            §§399.20 and 387.8)


          2)Directs the electrical corporations to develop standard  
            contract terms and conditions that reflect the operational  
            characteristics of the projects, and to provide a streamlined  
            contracting process.  (Public Utilities Code §399.20)


          3)Counts renewable energy generation FIT contracts to qualify  
            for credit toward and IOUs Renewable Portfolio Standard (RPS)  
            goals and resource adequacy requirements.  (Public Utilities  
            Code §399.20)

          This bill:

          1)Creates an exception to the existing FIT program eligibility  
            limit of three MW to allow a conduit hydroelectric facility  
            with a nameplate generating capacity of up to four MW if the  
            conduit hydroelectric facility meets the following conditions:  


                 It delivers no more than three MW to the grid at any  
               time.
                 It complies with the electrical corporation's Electric  
               Rule 21 tariff or other distribution access tariff.
                 Payment is made pursuant to the FIT program no payment  
               is made for any deliveries in excess of three MW at any  
               time.
                 It was operational as of January 1, 1990, and is an  
               eligible renewable energy resource.

          1)Prohibits the California Public Utilities Commission (CPUC)  
            from reducing the MW limitation for a conduit hydroelectric  
            facility described above.








                                                                    AB 1979  
                                                                    Page  3


          Background

          Feed-in tariffs.  According to the National Renewable Energy  
          Laboratory (NREL), a FIT offers a guarantee of payments to  
          renewable energy developers for the electricity they produce.   
          NREL reports that FITs are used in many U.S. states and around  
          the world. California, too, offers a FIT program.  State law  
          requires all IOUs and POUs that serve more than 75,000 retail  
          customers to develop a standard FIT contract available to  
          renewable energy facilities up to three MW.  Statewide  
          participation is capped at 750 MW. 
            
          Effective capacity versus nameplate capacity.  As described  
          above, existing statute limits participation in the bioenergy  
          FIT program to electric generation facilities with and  
          "effective capacity" of three MW.  This bill creates a  
          conditional exception to the existing FIT program eligibility  
          limit of three MW to allow a conduit hydroelectric facility with  
          a "nameplate generating capacity" of up to four MW.  So, what's  
          the difference between effective capacity and nameplate  
          capacity?  The practical answer:  there is none.  The CPUC  
          determined, in Decision 12-05-035, that he three MW  
          effective-capacity limitation corresponds to the nameplate  
          capacity of the facility, meaning the capacity stamped on the  
          metal nameplate attached to the generation facility by the  
          manufacturer.

          A little bit too big.  Statute, declares that small projects of  
          less than three MW that are otherwise eligible renewable energy  
          resources may face difficulties in participating in competitive  
          solicitations under the RPS program.  Bill proponents object to  
          the exclusion of facilities that have a nameplate capacity of  
          greater than three MW but that are incapable of exporting more  
          than three MW to the grid.  As a particular example, proponents  
          point to the Utica Water & Power Authority (UWPA), which owns  
          and operates a small conduit hydroelectric generator with a  
          nameplate capacity of 3.6 MW.  Proponents assert that, despite  
          its nameplate capacity, the generator will never produce more  
          than three MW of electricity because of existing water system  
          constraints.


          This bill crafts a narrow exemption to the FIT program capacity  
          limitation for hydroelectric facilities like that UWPA's, as  







                                                                    AB 1979  
                                                                    Page  4


          characterized by bill proponents.  In fact, the exemption is so  
          narrowly crafted that it is unlikely that any facility other  
          than UWPA's will qualify for the exemption.  In any case, the  
          effect of the exemption should be minor from the perspective of  
          both ratepayers and grid operators. 


          Related/Prior Legislation
          
          AB 1923 (Wood, 2016) increases, from three MW nameplate to five  
          MW, the limit on the nameplate capacity of a bioenergy electric  
          generation facility that may participate in the IOU's bioenergy  
          feed-in-tariff programs.  The bill is pending consideration by  
          the full Senate.


          SB 1112 (Rubio, Chapter 612, Statutes of 2012) required an  
          additional 250 MW of renewable FIT procurement from small-scale  
          bioenergy projects that commence operation on or after June 1,  
          2013.


          SB 32 (Negrete-McLeod, Chapter 328, Statutes of 2009) increased  
          the FIT program limit from 480 MW to 750 MW and increased from  
          1.5 MW effective capacity to three MW effective capacity the  
          limit on electric generating facilities eligible to participate  
          in the FIT program.


          AB 1969 (Yee, Chapter 731, Statutes of 2006) authorized the  
          state's first FIT program, which authorized the state's largest  
          IOU's to purchase up to 480 MW of renewable generating capacity  
          from renewable facilities with an effective capacity of not more  
          than 1.5 MW.




          FISCAL EFFECT:   Appropriation:    No          Fiscal  
          Com.:YesLocal:   No


          SUPPORT:   (Verified8/19/16)








                                                                    AB 1979  
                                                                    Page  5



          Utica Water and Power Authority (source)
          Calaveras County Supervisor, District 3
          Calaveras County Water District
          City of Angels Camp
          Murphys Sanitary District
          NLine energy


           OPPOSITION:          (Verified8/19/16)


          Sierra Club California

          ARGUMENTS IN SUPPORT:  According to the author:  

             Small hydroelectric generators with a nameplate of over  
             three MW are prohibited from participating in the FIT  
             even though the generator will never actually run above  
             the three-MW threshold.  For example, the UWPA owns and  
             operates a small conduit hydroelectric generator with a  
             nameplate of 3.6 MW.  However, due to the existing water  
             system, the generator will never run above three MW.  In  
             fact, it will likely never run above 2.5 MW.  Despite  
             this, the facility is ineligible to participate in this  
             important program aimed at promoting these exact types of  
             small renewable generators.   This bill will allow an  
             existing conduit hydroelectric generation facility to be  
             eligible for the renewable FIT program if it has a  
             nameplate generating capacity of up to four MW but does  
             not operate above three MW, and was operational as of  
             January 1, 1990.  

          ARGUMENTS IN OPPOSITION:According to the opponents, this bill  
          would allow larger hydroelectric generating facilities to  
          qualify for the renewable FIT while starving out other more  
          truly renewable and environmentally sound projects.  It would  
          also increase workload at the CPUC for projects that are barely  
          renewable.




          ASSEMBLY FLOOR:  72-0, 5/27/16







                                                                    AB 1979  
                                                                    Page  6


          AYES:  Achadjian, Alejo, Travis Allen, Arambula, Atkins, Baker,  
            Bigelow, Bloom, Bonilla, Bonta, Burke, Calderon, Campos,  
            Chang, Chau, Chávez, Chu, Cooley, Cooper, Dababneh, Dahle,  
            Daly, Eggman, Frazier, Beth Gaines, Gallagher, Cristina  
            Garcia, Eduardo Garcia, Gatto, Gipson, Gomez, Gonzalez,  
            Gordon, Gray, Harper, Roger Hernández, Holden, Irwin, Jones,  
            Jones-Sawyer, Kim, Lackey, Levine, Linder, Lopez, Low,  
            Maienschein, Mathis, Mayes, McCarty, Medina, Mullin, Nazarian,  
            Obernolte, Olsen, Patterson, Quirk, Ridley-Thomas, Rodriguez,  
            Salas, Santiago, Steinorth, Mark Stone, Thurmond, Ting,  
            Wagner, Waldron, Weber, Wilk, Williams, Wood, Rendon
          NO VOTE RECORDED:  Brough, Brown, Chiu, Dodd, Grove, Hadley,  
            Melendez, O'Donnell

          Prepared by:Jay Dickenson / E., U., & C. / (916) 651-4107
          8/22/16 22:10:23


                                   ****  END  ****