BILL ANALYSIS                                                                                                                                                                                                    Ó



                                                                    AB 2126


                                                                    Page  1





          Date of Hearing:  April 11, 2016


                        ASSEMBLY COMMITTEE ON TRANSPORTATION


                                 Jim Frazier, Chair


          AB 2126  
          (Mullin) - As Introduced February 17, 2016


          SUBJECT:  Public contracts:  Construction Manager/General  
          Contractor contracts


          SUMMARY:  Expands from 6 to 12 the number of projects for which  
          the California Department of Transportation (Caltrans) is  
          authorized to use the Construction Manager/General Contractor  
          (CMGC) procurement method.  Of the 12 projects, at least 10  
          projects have to have construction costs greater than $10  
          million and at least 8 projects have to use Caltrans employees  
          or Caltrans consultants.


          EXISTING LAW:  

          1)Sets forth provisions governing public works contracting.   
            These provisions generally prohibit public agencies from  
            contracting with the same firm for both the design and the  
            construction phases of a project. 
           
          2)Generally requires public works construction contracts to be  
            awarded to the lowest responsible bidder.  

          3)Describes the CMGC procurement method and makes legislative  
            findings and declarations regarding benefits related to risk  
            transfer and project phasing using CMGC.








                                                                    AB 2126


                                                                    Page  2






          4)Authorizes the Caltrans to use CMGC on no more than six  
            projects, at least five of which must have construction costs  
            greater than $10,000,000, and at least four of which have to  
            use Caltrans employees or Caltrans consultants.

          5)Defines key terms as follows relative to authority granted to  
            Caltrans to use CMGC:  

             a)   "Construction manager/general contractor method" to mean  
               a project delivery method in which a construction manager  
               is procured to provide preconstruction services during the  
               design phase of the project and construction services  
               during the construction phase of the project.  The contract  
               for construction services may be entered into at the same  
               time as the contract for preconstruction services, or at a  
               later time.  The execution of the design and the  
               construction of the project may be in sequential phases or  
               concurrent phases; 

             b)   "Preconstruction services" to mean advice given during  
               the design phase of a project related to, for example,  
               scheduling, pricing, and phasing to assist the department  
               design a more constructible project; and,

             c)   "Project" to mean the construction of a highway, bridge,  
               or tunnel.



          6)Sets forth provisions governing the process for procuring CMGC  
            services.  

          FISCAL EFFECT:  Unknown


          COMMENTS:  For decades, the traditional process for procuring  
          public works projects has been the design-bid-build process.   
          This process relies on the project owner: 1) preparing, or  








                                                                    AB 2126


                                                                    Page  3





          causing to be prepared, complete project design specifications  
          and estimates; 2) putting the complete package out to bid for  
          construction; and 3) awarding the construction contract to the  
          lowest responsible bidder.  The design-bid-build process was  
          developed to protect taxpayers from extravagance, corruption,  
          and other improper practices by public officials as well as to  
          secure a fair and reasonable price for public works construction  
          by injecting competition amongst bidders into the process.  

          Although design-bid-build generally results in the lowest cost  
          construction contract, it is not without its drawbacks,  
          including:  

          1)Projects generally take longer to complete because designs  
            must be entirely completed, permits obtained, and right-of-way  
            acquired before the construction contract can be bid and  
            awarded.  

          2)Designs prepared for a competitive low-bid procurement are  
            developed to allow for a broad range of construction  
            approaches.  As a result, low-bid designs do not always equate  
            to the most efficient designs possible, depending on a  
            particular contractor's strengths or capabilities.  

          3)Because the project designer does not have the benefit of  
            consulting with the entity that will ultimately be responsible  
            for construction of the project, there may be significant  
            issues that the designer does not anticipate, particularly  
            constructability issues.  This can result in change orders  
            that ultimately drive up the price of the contract.  

          4)Low-bid is not always the least expensive option, once change  
            orders and contractor claims are factored into the overall  
            project costs.  

          In the early 1990s, public works agencies grew frustrated with  
          design-bid-build and began experimenting with more innovative  
          project delivery methods, namely design-build.  Design-build is  
          an alternate method for procuring design and construction  








                                                                    AB 2126


                                                                    Page  4





          services that provides for the delivery of public works projects  
          from a single entity.  Design-build combines project design,  
          permit, and construction schedules in order to streamline the  
          traditional design-bid-build environment.  

          Design-build differs from design-bid-build in some key areas,  
          including:

          1)Overall elapsed project delivery times are shorter because  
            construction can begin before final design is complete.  

          2)Project costs and schedule risks are more heavily borne by the  
            design-build contractor.  

          3)Construction claims and change orders are minimized.  

          4)Designs can be developed to take advantage of a particular  
            contractor's strengths and abilities, thereby reducing the  
            need to "over-design" for generic use as in design-bid-build.   


          5)Project specifications are typically based on definitive  
            performance criteria, which may or may not be well established  
            by the project owner, rather than established specifications.   


          6)Contracts are awarded based on best-value analyses rather than  
            low-bid.  

          Design-build contracts are not without their drawbacks as well.   
          For example, with a design-build project, the project owner must  
          give up a good deal of control over the details of the project  
          design.  Additionally, design-build contractors are typically  
          selected using qualifications-based selection criteria or best  
          value analysis.  These approaches are more subjective than a  
          low-bid approach, potentially subjecting the public works owner  
          to greater contract challenges and higher costs.  

          In 2012, AB 2498 (Gordon), Chapter 752, Statutes of 2012,  








                                                                    AB 2126


                                                                    Page  5





          authorized Caltrans to use CMGC on no more than six projects, at  
          least five of which must have construction costs greater than  
          $10 million.  CMGC is an emerging project delivery method that  
          potentially combines the best of both design-bid-build and  
          design-build.  Using CMGC, Caltrans can engage a design and  
          construction management consultant (construction manager) to act  
          as its consultant during the pre-construction phase and as the  
          general contractor during construction.  During the design  
          phase, the construction manager acts in an advisory role,  
          providing constructability reviews, value engineering  
          suggestions, construction estimates, and other  
          construction-related recommendations.  Later, Caltrans and the  
          construction manager can agree that the project design has  
          progressed to a sufficient enough point that construction may  
          begin.  The two parties then work out mutually agreeable terms  
          and conditions for the construction contract, and, if all goes  
          well, the construction manager becomes the general contractor  
          and construction on the project commences, well before design is  
          entirely complete.  

          The CMGC process provides continuity and collaboration between  
          the design and construction phases of the project.  Construction  
          managers have an incentive to provide input during the design  
          phase that will enhance constructability of the project later  
          because they know that they will have the opportunity to become  
          the general contractor for the project.  Furthermore, CMGC  
          promises to save project delivery time, provide earlier cost  
          certainty, transfer risks from the department to the contractor,  
          and ensure project constructability.  Additionally, CMGC allows  
          Caltrans to have greater control of design decisions.  It also  
          allows the department to design the project to compliment the  
          CMGC's strengths and capabilities, thereby avoiding the need to  
          over-design the project to provide maximum competitiveness in a  
          low-bid procurement.  

          There are potential drawbacks of using CMGC contracts.   
          According to guidance published by the City of Seattle, CMGC  
          contracts carry risks, including:









                                                                    AB 2126


                                                                    Page  6





          1)They are difficult and complex.  

          2)The procurement process takes longer and consumes greater  
            project staff time than traditional design-bid-build  
            contracts.  

          3)Project teams face steep learning curves.  

          4)Successful construction cost negotiations require experienced  
            staff.  

          Other literature on the use of CMGC contracts is generally  
          consistent with Seattle's guidance regarding concerns for risks  
          associated with CMGC contracts and cautions that CMGC is not  
          appropriate for every project.  However, the same literature  
          suggests that, if carefully implemented, CMGC has the potential  
          to significantly improve project delivery.  

          AB 2126 increases the number of projects for which Caltrans can  
          use CMGC from 6 to 12.  The author introduced the bill to  
          increase the opportunities to reduce costs and expedite highway  
          congestion relief projects in the state.


          Committee comments:  As a part of the authority granted in AB  
          2498, Caltrans is required to report each year on the progress  
          of its CMGC contracts.  Last year, Caltrans reported that,  
          although it was still early in the process, it appears that the  
          department will realize substantial savings through the use of  
          CMGC on these projects.  These early indications are consistent  
          with those reported by other transportation agencies that have  
          been granted statutory authority to use CMGC in recent years.   
          Consequently, modestly increasing the number of projects for  
          which Caltrans can gain additional experience with the use of  
          CMGC seems reasonable and prudent.

          Related legislation:  The Administration is proposing trailer  
          bill language that would increase from 6 to 12 the number of  
          contracts for which Caltrans can use CMGC.  








                                                                    AB 2126


                                                                    Page  7







          AB 2374 (Chiu),  Extends existing authority for regional  
          transportation agencies to use the CMGC procurement method to  
          include ramp projects that are not on the state highway system  
          and removes the limitation that a CMGC project is in a sales tax  
          measure expenditure plan.


          Previous legislation: AB 2498 (Gordon), Chapter 752, Statutes of  
          2012, authorized Caltrans to use CMGC on no more than six  
          projects, at least five of which must have construction costs  
          greater than $10 million.  



          REGISTERED SUPPORT / OPPOSITION:




          Support


          Associated General Contractors


          Bay Area Council


          California Transportation Commission


          City/County Association of San Mateo County


          San Mateo County Economic Development Association










                                                                    AB 2126


                                                                    Page  8







          Opposition


          None on file




          Analysis Prepared by:Janet Dawson / TRANS. / (916) 319-2093