BILL ANALYSIS                                                                                                                                                                                                    Ó



          SENATE COMMITTEE ON TRANSPORTATION AND HOUSING
                              Senator Jim Beall, Chair
                                2015 - 2016  Regular 

          Bill No:          AB 2126           Hearing Date:  6/21/ 2016   
           ----------------------------------------------------------------- 
          |Author:   |Mullin                                                |
          |----------+------------------------------------------------------|
          |Version:  |2/17/2016                                             |
           ----------------------------------------------------------------- 
           ----------------------------------------------------------------- 
          |Urgency:  |No                     |Fiscal:      |Yes             |
           ----------------------------------------------------------------- 
           ----------------------------------------------------------------- 
          |Consultant|Manny Leon                                            |
          |:         |                                                      |
           ----------------------------------------------------------------- 
          

          SUBJECT:  Public contracts:  Construction Manager/General  
          Contractor contracts

            DIGEST:  This bill increases the number of authorized  
          Construction Manager/General Contractor (CM/GC) projects from  
          six projects to twelve, as specified. 

          ANALYSIS:
          
          Existing law:
          
          1)Sets forth provisions governing public works contracting.   
            These provisions generally prohibit public agencies from  
            contracting with the same firm for both the design and the  
            construction phases of a project.  

          2)Generally requires public works construction contracts to be  
            awarded to the lowest responsible bidder.  

          3)Describes the CM/GC procurement method and makes legislative  
            findings and declarations regarding benefits related to risk  
            transfer and project phasing using CM/GC.

          4)Authorizes the California Department of Transportation  
            (Caltrans) to use CM/GC on no more than six projects, at least  
            five of which must have construction costs greater than $10  
            million.  

          5)Authorizes the Santa Clara County Valley Transportation  
            Authority, the San Mateo County Transit District, and the San  







          AB 2126 (Mullin)                                   Page 2 of ?
          
          
            Diego Association of Governments to use CM/GC for transit  
            projects.  

          6)Authorizes a regional transportation agency (RTA) to use the  
            CM/GC project delivery method to design and construct projects  
            on expressways that are not on the state highway system if the  
            projects are developed in accordance with an expenditure plan  
            approved by the voters.
          7)Defines key terms relative to the authority granted to RTA's  
            to use CM/GC, as specified.  

          8)Provides that the entity responsible for maintenance of local  
            streets and roads within the same jurisdiction of the  
            expressway shall be responsible for the maintenance of the  
            expressway.

          9)Sets forth provisions governing the process for procuring  
            CM/GC services.  

          This bill expands, from six to 12, the number of projects for  
          which Caltrans is authorized to use the CM/GC procurement  
          method.  Further specifies that of the 12 projects, at least 10  
          projects must have construction costs greater than $10 million  
          and at least eight projects are required to use Caltrans  
          employees or Caltrans consultants, as specified.

          COMMENTS:

          1)Purpose. The author notes that "this bill will extend CM/GC  
            authorization by increasing the number of projects that  
            Caltrans can build using CM/GC delivery method from six to  
            twelve, thus increasing the opportunities to reduce costs and  
            expedite congestion relief projects in the state." 

          2)Traditional project delivery. Traditionally, state and local  
            entities develop and construct transportation projects with a  
            process known as the design-bid-build (DBB) delivery method.   
            This method requires the public agency to fully design a  
            project and then ask general contractors to bid on the  
            construction contract based on the agency's design.  DBB  
            procurement results in project risks being largely borne by  
            the agency that designs the project, because the agency bears  
            the financial burden if the plans are inadequate or  
            unanticipated construction issues arise. 









          AB 2126 (Mullin)                                   Page 3 of ?
          
          
          3)What is CM/GC? The CM/GC project-delivery method allows an  
            agency to engage a construction manager during the design  
            process to provide assistance to the design team, which can  
            ultimately lead to a more constructible project.  When design  
            is nearly complete, the agency and the construction manager  
            negotiate a guaranteed maximum price for the construction of  
            the project based on the defined scope and schedule.  If this  
            price is acceptable to both parties, they execute a contract  
            for construction services, and the construction manager  
            becomes the general contractor.  Studies suggest CM/GC often  
            leads to less costly or more expediently delivered projects  
            because of the construction manager's involvement in the  
            design process.

          4)Why pursue alternative project delivery approaches?  For  
            decades, state and local agencies have relied on the DBB  
            procurement method for transportation projects.  DBB reduces  
            the risk for the construction contractor because the state or  
            local agency has a completed design, procured right-of-way,  
            and achieved environmental clearance before letting the  
            contract.  Agencies using this traditional method generally  
            receive the lowest initial-cost construction contracts for a  
            given project, because contractors are competitively bidding  
            on a relatively risk-free project.  Drawbacks to DBB can  
            include longer completion times, constructability challenges  
            unforeseen by the designers, and increasing costs over time  
            due to change orders and claims.

            The CM/GC process is meant to provide continuity and  
            collaboration between the design and construction phases of  
            the project.  Construction managers have an incentive to  
            provide input during the design phase that will enhance  
            constructability of the project later, because they know that  
            they will have the opportunity to become the general  
            contractor for the project.  Furthermore, CM/GC promises to  
            save project delivery time, provide earlier cost certainty,  
            transfer some risks from the public agency to the contractor,  
            and ensure project constructability.  Finally, it allows each  
            agency to design the project to complement the general  
            contractor's strengths and capabilities, thereby providing  
            maximum competitiveness in a low-bid procurement.  

          5)Prior authorization. AB 2498 (Gordon, Chapter 752, Statutes of  
            2012) authorized Caltrans to use CM/GC on no more than six  
            projects, at least five of which must have construction costs  








          AB 2126 (Mullin)                                   Page 4 of ?
          
          
            greater than $10 million.  At that time, the author introduced  
            AB 2498 to authorize Caltrans to use CM/GC to start evaluating  
            the effectiveness of this emerging project-delivery method  
            that combined the best of both design-bid-build and  
            design-build.  To date, all six authorized slots have been  
            granted and the projects are moving forward to completion.   
            This bill proposes to double the amount of authorized CM/GC  
            projects from six to twelve; however, preserves all the  
            design, engineering, inspection, and reporting requirements  
            established in AB 2498. 

          6)Current status. Regarding current CMGC projects underway,  
            while none of the projects have yet been completed, no  
            significant problems have been reported.  As these projects  
            move toward completion, a more thorough examination of the  
            advantages and disadvantages of CM/GC contracting will be  
            required. However, as the pros and cons continue to be  
            evaluated; utilizing CM/GC for various types of transportation  
            projects may be beneficial for evaluation purposes.  






          Related Legislation:
          
          AB 2374 (Chiu) - extends existing authority for regional  
          transportation agencies to use the CM/GC procurement method to  
          include ramp projects that are not on the state highway system,  
          as specified.  AB 2374 will be heard by the Committee at the  
          same hearing as AB 2126. 

          AB 1171 (Linder, Chapter 413, Statutes of 2015) - provided  
          limited authority for regional transportation agencies to use  
          CM/GC on expressway projects that are not on the state highway  
          system but are in sales tax measure expenditure plans.
          
          AB 1724 (Frazier, 2014) - would have granted regional  
          transportation agencies broad authority to use CM/GC.  This bill  
          was held in this committee.

          AB 2498 (Gordon, Chapter 752, Statutes of 2012) - authorized  
          Caltrans to use CM/GC on no more than six projects, at least  
          five of which must have construction costs greater than $10  








          AB 2126 (Mullin)                                   Page 5 of ?
          
          
          million.  

          SB 1549 (Vargas, Chapter 767, Statutes of 2012) - authorized  
          SANDAG to use CM/GC contracting on transit projects.  

          AB 797 (Gordon, Chapter 320, Statutes of 2013) - authorized the  
          VTA and the San Mateo County Transit District to use CM/GC  
          contracting on transit projects.

          FISCAL EFFECT:  Appropriation:  No    Fiscal Com.:  Yes     
          Local:  Yes


          Assembly votes:

            Floor:         77-0
            Appr:          19-0
            Trans:         16-0

            POSITIONS:  (Communicated to the committee before noon on  
          Wednesday,
                          June 15, 2016.)
          






            SUPPORT:  

          Associated General Contractors
          Bay Area Council
          City/County Association of Governments of San Mateo County 
          California Transportation Commission 
          San Mateo County Economic Development Association
          San Mateo County Transportation Authority

          OPPOSITION:

          None received 
          
          

                                      -- END --








          AB 2126 (Mullin)                                   Page 6 of ?