BILL ANALYSIS                                                                                                                                                                                                    Ó



          SENATE COMMITTEE ON APPROPRIATIONS
                             Senator Ricardo Lara, Chair
                            2015 - 2016  Regular  Session

          AB 2126 (Mullin) - Public contracts:  Construction  
          Manager/General Contractor contracts
          
           ----------------------------------------------------------------- 
          |                                                                 |
          |                                                                 |
          |                                                                 |
           ----------------------------------------------------------------- 
          |--------------------------------+--------------------------------|
          |                                |                                |
          |Version: February 17, 2016      |Policy Vote: T. & H. 11 - 0     |
          |                                |                                |
          |--------------------------------+--------------------------------|
          |                                |                                |
          |Urgency: No                     |Mandate: Yes                    |
          |                                |                                |
          |--------------------------------+--------------------------------|
          |                                |                                |
          |Hearing Date: August 1, 2016    |Consultant: Mark McKenzie       |
          |                                |                                |
           ----------------------------------------------------------------- 


          This bill may meet the criteria for referral to the Suspense  
          File.



          Bill  
          Summary:  AB 2126 would expand the authority for the Department of  
          Transportation (Caltrans) to use the Construction  
          Manager/General Contractor (CMGC) procurement method.   
          Specifically, the bill would double the number of projects that  
          may be constructed using CMGC from six to12, as specified.


          Fiscal  
          Impact:  Unknown project costs or savings related to Caltrans' expanded  
          authority to use a new project delivery method (State Highway  
          Account and federal funds).  Caltrans anticipates significant  
          long term savings, based on the experience of other states,  
          local entities, and early feedback related to the current CMGC  
          authority.  Staff notes, however, that currently authorized CMGC  
          projects have not been completed or evaluated for cost  
          efficiency.  (see staff comments)







          AB 2126 (Mullin)                                       Page 1 of  
          ?
          
          

          In addition, since a contract for preconstruction and  
          construction services for CMGC is a negotiated process with the  
          most qualified construction manager, rather than a traditional  
          "lowest responsible bidder" process, it is difficult to  
          determine whether the negotiated price would be lower or higher  
          than project delivery costs through a traditional  
          design-bid-build process.  It is expected that use of the CMGC  
          method minimizes change orders, which is currently a significant  
          factor in unexpected cost escalation on Caltrans projects.


          Background:  The traditional project delivery process is the  
          design-bid-build method, whereby complete plans and  
          specifications are prepared prior to the advertising, bidding,  
          and awarding of any construction contracts.  The agency awards  
          the contract to the lowest responsible bidder.  Although this  
          method is structured to ensure a project is built for the lowest  
          cost, oftentimes project costs escalate dramatically as change  
          orders are necessary to address unforeseen problems encountered  
          during the construction phase.  In addition, the bulk of project  
          risk remains with the sponsoring agency.

          In recent years, public agencies have adopted alternative  
          project delivery methods, including design-build,  
          design-sequencing, and CMGC.  The principle reasons for using  
          alternate methods are to shift construction risk from the  
          agency/owner to the project contractor, minimize change order  
          and cost escalation, and to expedite project completion.  

          The CMGC project delivery method allows an agency to engage a  
          construction manager during the design process to provide  
          assistance to the design team, including advice regarding  
          scheduling, pricing, phasing, and other input that helps the  
          owner design a more constructible project.  The agency selects  
          the construction manager on the basis of qualifications, past  
          experience, or a best-value basis.  According to the Federal  
          Highway Administration, when design reaches approximately 60 to  
          90 percent completion, the agency and the construction manager  
          negotiate a guaranteed maximum price for the construction of the  
          project based on the defined scope and schedule.  If this price  
          is acceptable to both parties, a contract is executed for  
          construction services, and the construction manager becomes the  
          general contractor.  The benefits of this procurement method are  








          AB 2126 (Mullin)                                       Page 2 of  
          ?
          
          
          that the public agency does not sacrifice control over the  
          design of the project and the contractor is familiar with the  
          project design during the construction phase, resulting in fewer  
          change orders and disputes over design issues.

          Existing law authorizes Caltrans to use the CMGC method on no  
          more than six projects, five of which must have construction  
          costs of over $10 million.  On at least four of the projects,  
          Caltrans must use Caltrans employees or consultants under  
          contract with the department for project design and engineering  
          services.  In addition, Caltrans must use its own employees or  
          consultants to perform all construction inspection services.   
          The existing CMGC authorization requires annual reports that  
          provide data on the stage of completion, the district, costs,  
          description, status, and estimated time to completion.  Once  
          projects are completed, the annual reports must also include  
          information on the differences between initial cost estimates  
          and actual costs, estimated and actual dates of completion, the  
          reason for any differences, and the number and dollar value of  
          any change orders for all projects completed using CMGC.


          Proposed Law:  
            AB 2126 would increase the number of projects, from six to 12,  
          for which Caltrans may use the CMGC procurement method.  The  
          bill also requires at least 10 of the projects to have  
          construction costs of over $10 million and requires at least  
          eight projects to use Caltrans employees or contracted  
          consultants for project design and engineering services, as  
          specified.


          Related  
          Legislation:  AB 2498 (Gordon), Chap. 752/2012, authorized  
          Caltrans to use CMGC on up to six projects, five of which must  
          have costs of at least $10 million.


          Staff  
          Comments:  The Legislature has generally taken a measured  
          approach to authorizing the use of new project delivery methods.  
           This usually involves some limited authorization initially,  
          either through a fixed number of projects or period of time,  
          which provides the opportunity for evaluation through data  








          AB 2126 (Mullin)                                       Page 3 of  
          ?
          
          
          collection and analysis.  Caltrans has selected projects and  
          construction managers for all six projects authorized under  
          current law, with estimated costs ranging from $52 million to  
          $606 million, and estimated completion dates from March 2018  
          through Summer of 2020.  Contracts have been awarded for parts  
          of three of the projects and are under construction, while the  
          other three are in the preconstruction phase.  To date only one  
          construction package related to one of the projects has been  
          completed (San Francisco/Oakland Bay Bridge Foundation Removal).  
           
          Caltrans anticipates it will realize substantial savings through  
          the use of CMGC on these projects.  Since no projects have been  
          completed, however, Caltrans has not reported on the differences  
          between estimated and actual costs, estimated and actual  
          completion dates, or the number of change orders.  Absent this  
          data, it is unclear whether total projects costs will be higher  
          or lower than estimated costs, whether CMGC results in  
          accelerated project delivery, or whether CMGC project delivery  
          costs would be lower than project costs under the  
          design-bid-build method.  The Committee may wish to consider  
          whether it is prudent to expand CMGC authority until the  
          Legislature has adequate data to evaluate the pilot program.




                                      -- END --