BILL ANALYSIS                                                                                                                                                                                                    Ó



          SENATE COMMITTEE ON TRANSPORTATION AND HOUSING
                              Senator Jim Beall, Chair
                                2015 - 2016  Regular 

          Bill No:          AB 2374           Hearing Date:     6/21/2016
           ----------------------------------------------------------------- 
          |Author:   |Chiu                                                  |
          |----------+------------------------------------------------------|
          |Version:  |2/18/2016                                             |
           ----------------------------------------------------------------- 
           ----------------------------------------------------------------- 
          |Urgency:  |No                     |Fiscal:      |No              |
           ----------------------------------------------------------------- 
           ----------------------------------------------------------------- 
          |Consultant|Manny Leon                                            |
          |:         |                                                      |
           ----------------------------------------------------------------- 
          

          SUBJECT:  Construction Manager/General Contractor method:   
          regional transportation agencies:  ramps

          DIGEST:  This bill extends existing authority for regional  
          transportation agencies (RTAs) to use the Construction  
          Manager/General Contractor (CM/GC), as specified.  


          ANALYSIS:


          Existing law:
          
          1)Sets forth provisions governing public works contracting.   
            These provisions generally prohibit public agencies from  
            contracting with the same firm for both the design and the  
            construction phases of a project.  

          2)Generally requires public works construction contracts to be  
            awarded to the lowest responsible bidder.  

          3)Describes the CM/GC procurement method and makes legislative  
            findings and declarations regarding benefits related to risk  
            transfer and project phasing using CM/GC.

          4)Authorizes the California Department of Transportation  
            (Caltrans) to use CM/GC on no more than six projects, at least  
            five of which must have construction costs greater than $10  
            million.  








          AB 2374 (Chiu)                                      Page 2 of ?
          
          
          5)Authorizes the Santa Clara County Valley Transportation  
            Authority, the San Mateo County Transit District, and the San  
            Diego Association of Governments to use CM/GC for transit  
            projects.  

          6)Authorizes an RTA to use the CM/GC project delivery method to  
            design and construct projects on expressways that are not on  
            the state highway system if the projects are developed in  
            accordance with an expenditure plan approved by the voters.

          7)Defines key terms relative to the authority granted to RTA's  
            to use CM/GC, as specified.  

          8)Provides that the entity responsible for maintenance of local  
            streets and roads within the same jurisdiction of the  
            expressway shall be responsible for the maintenance of the  
            expressway.

          9)Sets forth provisions governing the process for procuring  
            CM/GC services.  

          This bill extends existing authority for RTAs to use CM/GC  
          procurement method for ramp projects that are not on the state  
          highway system, and additionally removes the limitation that an  
          authorized CM/GC project must be included in a sales tax measure  
          expenditure plan.

          COMMENTS:

          Purpose. The author notes that this bill will extend CM/GC  
          authorization to ramps that are not on the state highway system  
          and remove the requirement that authorized projects be included  
          in a voter-approved expenditure plan. As a result, this bill  
          authorizes the San Francisco County Transportation Authority to  
          utilize CM/GC for the Yerba Buena Island West-Side Bridges  
          Retrofit project - which is a seismic safety project on a  
          locally owned and operated road facility.    

          Major transportation project: The Yerba Buena Island (YBI)  
          West-Side Bridges Interchange Improvement Project includes two  
          major components:

          a)On the east side of Treasure Island, the YBI I-80 Ramps  
            project will construct new westbound on and off ramps to the  
            new Eastern Span of the Bay Bridge.








          AB 2374 (Chiu)                                      Page 3 of ?
          
          

          b)On the west side of the island, the YBI West-Side Bridges  
            Retrofit project will seismically retrofit the existing bridge  
            structures-critical components of island traffic circulation  
            between the islands and the Bay Bridge.

          Specifically, the $66 million Yerba Buena Island West-Side  
          Bridges Retrofit project will seismically retrofit or replace  
          eight locally owned bridge structures that connect Treasure  
          Island to the San Francisco Bay Bridge. The facility is locally  
          owned and not a part of the state highway system, and partially  
          funded with state transportation revenues.  This project has  
          been identified by the San Francisco Transportation Authority as  
          a "complicated public safety project, dealing with unique  
          topographical, environmental, and construction staging issues."   


          Traditional project delivery: Traditionally, state and local  
          entities develop and construct transportation projects with a  
          process known as the design-bid-build (DBB) delivery method.   
          This method requires the public agency to fully design a project  
          and then ask general contractors to bid on the construction  
          contract based on the agency's design.  DBB procurement results  
          in project risks being largely borne by the agency that designs  
          the project, because the agency bears the financial burden if  
          the plans are inadequate or unanticipated construction issues  
          arise. 

          What is CM/GC? The CM/GC project-delivery method allows an  
          agency to engage a construction manager during the design  
          process to provide assistance to the design team, which can  
          ultimately lead to a more constructible project.  When design is  
          nearly complete, the agency and the construction manager  
          negotiate a guaranteed maximum price for the construction of the  
          project based on the defined scope and schedule.  If this price  
          is acceptable to both parties, they execute a contract for  
          construction services, and the construction manager becomes the  
          general contractor.  Studies suggest CM/GC often leads to less  
          costly or more expediently delivered projects because of the  
          construction manager's involvement in the design process.

          Why pursue alternative project delivery approaches?  For  
          decades, state and local agencies have relied on the DBB  
          procurement method for transportation projects.  DBB reduces the  
          risk for the construction contractor because the state or local  








          AB 2374 (Chiu)                                      Page 4 of ?
          
          
          agency has a completed design, procured right-of-way, and  
          achieved environmental clearance before letting the contract.   
          Agencies using this traditional method generally receive the  
          lowest initial-cost construction contracts for a given project,  
          because contractors are competitively bidding on a relatively  
          risk-free project.  Drawbacks to DBB can include longer  
          completion times, constructability challenges unforeseen by the  
          designers, and increasing costs over time due to change orders  
          and claims.

          The CM/GC process is meant to provide continuity and  
          collaboration between the design and construction phases of the  
          project.  Construction managers have an incentive to provide  
          input during the design phase that will enhance constructability  
          of the project later, because they know that they will have the  
          opportunity to become the general contractor for the project.   
          Furthermore, CM/GC promises to save project delivery time,  
          provide earlier cost certainty, transfer some risks from the  
          public agency to the contractor, and ensure project  
          constructability.  Finally, it allows each agency to design the  
          project to complement the general contractor's strengths and  
          capabilities, thereby providing maximum competitiveness in a  
          low-bid procurement.  
             
          Current status.  Regarding current CMGC projects underway, while  
          none of the projects have yet been completed, no significant  
          problems have been reported.  In fact, the San Francisco  
          Transportation Authority has analyzed the potential use of CM/GC  
          for this project and estimates that this procurement method  
          could reduce construction time by an estimated six months,  
          reduce costs by between 10% and 15%, and reduce project risk.


          As these projects move toward completion, a more thorough  
          examination of the advantages and disadvantages of CM/GC  
          contracting will be required. However, as the pros and cons  
          continue to be evaluated; utilizing CM/GC for other types of  
          projects may be beneficial for evaluation purposes.  


          Related Legislation:
          
          AB 2126 (Mullin) - increases the number of authorized  
          Construction Manager/General Contractor (CM/GC) projects from  
          six projects to twelve, as specified.  AB 2126 will be heard by  








          AB 2374 (Chiu)                                      Page 5 of ?
          
          
          this Committee at the same hearing as AB 2374. 

          AB 1171 (Linder, Chapter 413, Statutes of 2015) - provided  
          limited authority for RTAs to use CM/GC on expressway projects  
          that are not on the state highway system but are in sales tax  
          measure expenditure plans.
          
          AB 1724 (Frazier, 2014) - would have granted regional  
          transportation agencies broad authority to use CM/GC.  This bill  
          was held in this committee.

          AB 2498 (Gordon, Chapter 752, Statutes of 2012) - authorized  
          Caltrans to use CM/GC on no more than six projects, at least  
          five of which must have construction costs greater than $10  
          million.  

          SB 1549 (Vargas, Chapter 767, Statutes of 2012) - authorized San  
          Diego Association of Governments (SANDAG) to use CM/GC  
          contracting on transit projects.  

          AB 797 (Gordon, Chapter 320, Statutes of 2013) - authorized the  
          Santa Clara Valley Transportation Authority (VTA) and the San  
          Mateo County Transit District to use CM/GC contracting on  
          transit projects.

          


          FISCAL EFFECT:  Appropriation:  No    Fiscal Com.:  No    Local:  
           No


          Assembly Votes:

            Floor:         77-0
            Trans:         16-0
            
          POSITIONS:  (Communicated to the committee before noon on  
          Wednesday,
                          June 15, 2016.)
          
            SUPPORT:  

          Automobile Club of Southern California 
          California Transportation Commission








          AB 2374 (Chiu)                                      Page 6 of ?
          
          
          San Francisco County Transportation Authority 
          Santa Clara Valley Transportation Authority 

          OPPOSITION:

          None received 

          
          

                                      -- END --