BILL ANALYSIS                                                                                                                                                                                                    Ó




           ----------------------------------------------------------------- 
          |SENATE RULES COMMITTEE            |                       AB 2374|
          |Office of Senate Floor Analyses   |                              |
          |(916) 651-1520    Fax: (916)      |                              |
          |327-4478                          |                              |
           ----------------------------------------------------------------- 


                                      CONSENT 


          Bill No:  AB 2374
          Author:   Chiu (D) 
          Introduced:2/18/16  
          Vote:     21 

           SENATE TRANS. & HOUSING COMMITTEE:  11-0, 6/21/16
           AYES:  Beall, Cannella, Allen, Bates, Gaines, Galgiani, Leyva,  
            McGuire, Mendoza, Roth, Wieckowski

           ASSEMBLY FLOOR:  77-0, 4/11/16 (Consent) - See last page for  
            vote

           SUBJECT:   Construction Manager/General Contractor method:   
                     regional transportation agencies:  ramps


          SOURCE:    Author

          DIGEST:   This bill extends existing authority for regional  
          transportation agencies (RTAs) to use the Construction  
          Manager/General Contractor (CM/GC), as specified.


          ANALYSIS:  


          Existing law:


          1)Sets forth provisions governing public works contracting.   
            These provisions generally prohibit public agencies from  
            contracting with the same firm for both the design and the  
            construction phases of a project.  










                                                                    AB 2374  
                                                                    Page  2



          2)Requires, generally, public works construction contracts to be  
            awarded to the lowest responsible bidder.  


          3)Describes the CM/GC procurement method and makes legislative  
            findings and declarations regarding benefits related to risk  
            transfer and project phasing using CM/GC.


          4)Authorizes the California Department of Transportation  
            (Caltrans) to use CM/GC on no more than six projects, at least  
            five of which must have construction costs greater than $10  
            million.  


          5)Authorizes the Santa Clara County Valley Transportation  
            Authority, the San Mateo County Transit District, and the San  
            Diego Association of Governments to use CM/GC for transit  
            projects.  


          6)Authorizes an RTA to use the CM/GC project delivery method to  
            design and construct projects on expressways that are not on  
            the state highway system if the projects are developed in  
            accordance with an expenditure plan approved by the voters.


          7)Defines key terms relative to the authority granted to RTAs to  
            use CM/GC, as specified.  


          8)Provides that the entity responsible for maintenance of local  
            streets and roads within the same jurisdiction of the  
            expressway shall be responsible for the maintenance of the  
            expressway.


          9)Sets forth provisions governing the process for procuring  
            CM/GC services.  


          This bill extends existing authority for RTAs to use the CM/GC  








                                                                    AB 2374  
                                                                    Page  3



          procurement method for ramp projects that are not on the state  
          highway system, and additionally removes the limitation that an  
          authorized CM/GC project must be included in a sales tax measure  
          expenditure plan.


          Comments


          1)Purpose.  The author notes that this bill will extend CM/GC  
            authorization to ramps that are not on the state highway  
            system and remove the requirement that authorized projects be  
            included in a voter-approved expenditure plan. As a result,  
            this bill authorizes the San Francisco County Transportation  
            Authority to utilize CM/GC for the Yerba Buena Island (YBI)  
            West-Side Bridges Retrofit project - which is a seismic safety  
            project on a locally owned and operated road facility.    


          2)Major transportation project.  YBI West-Side Bridges  
            Interchange Improvement Project includes two major components:


             a)   On the east side of Treasure Island, the YBI I-80 Ramps  
               project will construct new westbound on and off ramps to  
               the new Eastern Span of the Bay Bridge.


             b)   On the west side of the island, the YBI West-Side  
               Bridges Retrofit project will seismically retrofit the  
               existing bridge structures-critical components of island  
               traffic circulation between the islands and the Bay Bridge.


            Specifically, the $66 million YBI West-Side Bridges Retrofit  
            project will seismically retrofit or replace eight locally  
            owned bridge structures that connect Treasure Island to the  
            San Francisco Bay Bridge. The facility is locally owned and  
            not a part of the state highway system, and partially funded  
            with state transportation revenues.  This project has been  
            identified by the San Francisco Transportation Authority as a  
            "complicated public safety project, dealing with unique  








                                                                    AB 2374  
                                                                    Page  4



            topographical, environmental, and construction staging  
            issues."  


          1)Traditional project delivery.  Traditionally, state and local  
            entities develop and construct transportation projects with a  
            process known as the design-bid-build (DBB) delivery method.   
            This method requires the public agency to fully design a  
            project and then ask general contractors to bid on the  
            construction contract based on the agency's design.  DBB  
            procurement results in project risks being largely borne by  
            the agency that designs the project, because the agency bears  
            the financial burden if the plans are inadequate or  
            unanticipated construction issues arise. 


          2)What is CM/GC?  The CM/GC project-delivery method allows an  
            agency to engage a construction manager during the design  
            process to provide assistance to the design team, which can  
            ultimately lead to a more constructible project.  When design  
            is nearly complete, the agency and the construction manager  
            negotiate a guaranteed maximum price for the construction of  
            the project based on the defined scope and schedule.  If this  
            price is acceptable to both parties, they execute a contract  
            for construction services, and the construction manager  
            becomes the general contractor.  Studies suggest CM/GC often  
            leads to less costly or more expediently delivered projects  
            because of the construction manager's involvement in the  
            design process.


          3)Why pursue alternative project delivery approaches?  For  
            decades, state and local agencies have relied on the DBB  
            procurement method for transportation projects.  DBB reduces  
            the risk for the construction contractor because the state or  
            local agency has a completed design, procured right-of-way,  
            and achieved environmental clearance before letting the  
            contract.  Agencies using this traditional method generally  
            receive the lowest initial-cost construction contracts for a  
            given project, because contractors are competitively bidding  
            on a relatively risk-free project.  Drawbacks to DBB can  
            include longer completion times, constructability challenges  








                                                                    AB 2374  
                                                                    Page  5



            unforeseen by the designers, and increasing costs over time  
            due to change orders and claims.


            The CM/GC process is meant to provide continuity and  
            collaboration between the design and construction phases of  
            the project.  Construction managers have an incentive to  
            provide input during the design phase that will enhance  
            constructability of the project later, because they know that  
            they will have the opportunity to become the general  
            contractor for the project.  Furthermore, CM/GC promises to  
            save project delivery time, provide earlier cost certainty,  
            transfer some risks from the public agency to the contractor,  
            and ensure project constructability.  Finally, it allows each  
            agency to design the project to complement the general  
            contractor's strengths and capabilities, thereby providing  
            maximum competitiveness in a low-bid procurement.  


          4)Current status.  Regarding current CMGC projects underway,  
            while none of the projects have yet been completed, no  
            significant problems have been reported.  In fact, the San  
            Francisco County Transportation Authority has analyzed the  
            potential use of CM/GC for this project and estimates that  
            this procurement method could reduce construction time by an  
            estimated six months, reduce costs by between 10% and 15%, and  
            reduce project risk.


            As these projects move toward completion, a more thorough  
            examination of the advantages and disadvantages of CM/GC  
            contracting will be required. However, as the pros and cons  
            continue to be evaluated, utilizing CM/GC for other types of  
            projects may be beneficial for evaluation purposes.




          FISCAL EFFECT:   Appropriation:    No          Fiscal  
          Com.:NoLocal:    No










                                                                    AB 2374  
                                                                    Page  6



          SUPPORT:   (Verified6/23/16)


          Automobile Club of Southern California 
          California Transportation Commission
          San Francisco County Transportation Authority 
          Santa Clara Valley Transportation Authority


          OPPOSITION:   (Verified6/23/16)


          None received

          ASSEMBLY FLOOR:  77-0, 4/11/16
          AYES:  Achadjian, Alejo, Travis Allen, Atkins, Baker, Bigelow,  
            Bloom, Bonilla, Bonta, Brough, Brown, Burke, Calderon, Campos,  
            Chang, Chau, Chávez, Chiu, Chu, Cooley, Cooper, Dababneh,  
            Dahle, Daly, Dodd, Eggman, Frazier, Beth Gaines, Gallagher,  
            Cristina Garcia, Eduardo Garcia, Gatto, Gipson, Gomez, Gordon,  
            Gray, Grove, Hadley, Harper, Roger Hernández, Holden, Irwin,  
            Jones, Jones-Sawyer, Kim, Lackey, Levine, Linder, Lopez, Low,  
            Maienschein, Mathis, Mayes, McCarty, Medina, Melendez, Mullin,  
            Nazarian, Obernolte, O'Donnell, Olsen, Patterson, Quirk,  
            Ridley-Thomas, Rodriguez, Salas, Santiago, Steinorth, Mark  
            Stone, Thurmond, Ting, Wagner, Waldron, Weber, Wilk, Williams,  
            Wood
          NO VOTE RECORDED:  Gonzalez, Rendon


          Prepared by:Manny Leon / T. & H. / (916) 651-4121
          6/24/16 14:33:43


                                   ****  END  ****


          












                                                                    AB 2374  
                                                                    Page  7