AB 2630,
as amended, Salas. begin deleteSan Joaquin Valley Clean Energy and Jobs Act. end deletebegin insertCalifornia Renewables Portfolio Standard Program: electrical transmission planning.end insert
Existing law relative to electrical restructuring, within the Public Utilities Act, establishes the Independent System Operator to ensure the efficient use and reliable operation of the electric transmission grid. The California Renewables Portfolio Standard Program requires the Public Utilities Commission (PUC) to establish a renewables portfolio standard requiring all retail sellers, as defined, to procure a minimum quantity of electricity products from eligible renewable energy resources, as defined, so that the total kilowatthours sold to their retail end-use customers achieves 25% of retail sales by December 31, 2016, 33% by December 31, 2020, 40% by December 31, 2024, 45% by December 31, 2027, and 50% by December 31, 2030. The program additionally requires each local publicly owned electric utility, as defined, to procure a minimum quantity of electricity products from eligible renewable energy resources to achieve the procurement requirements established by the program.begin insert The Renewable Energy Transmission Initiative is a statewide initiative to help identify transmission projects to accommodate the state’s renewable energy goals.end insert
This bill would require the PUC and the State Energy Resources Conservation and Development Commission (Energy Commission) to evaluate, while taking into consideration ratepayer costs and benefits, potential eligible renewable energy resource projects in the San Joaquin Valley that provide specified benefits or attributes. The bill would require the PUC and the Energy Commission, on or before January 31, 2017, using that evaluation, to recommend to the Independent System Operator an amount of electricity to be generated from eligible renewable energy resources in the San Joaquin Valley that reasonably maximizes, consistent with the state’s overall need for electricity and the California Renewables Portfolio Standard Program, the amount of electricity to be generated from eligible renewable energy resources that accomplishes specified objectives. The bill would require the PUC and the Energy Commission, on or before January 31, 2017, using the results of the evaluation, to recommend to the Independent System Operator any network transmission upgrades needed to fulfill the above-described generation quantity recommendations and would require that the transmission upgrade recommendations seek to minimize the need for new transmission by prioritizing the use of existing transmission corridors consistent with specified principles developed by the Energy Commission.
end deleteThis bill would require the Independent System Operator, when undertaking transmission planning activities, to take into account a specified report relating to solar photovoltaic system development in the San Joaquin Valley and specified principles of transmission corridor planning developed by the State Energy Resources Conservation and Development Commission (Energy Commission). The bill would require the Energy Commission, the PUC, and the Independent System Operator, when undertaking activities as part of the Renewable Energy Transmission Initiative, to take into account the above-specified report and principles.
end insertVote: majority. Appropriation: no. Fiscal committee: yes. State-mandated local program: no.
The people of the State of California do enact as follows:
It is the intent of the Legislature that the state’s
2processes for identifying and planning for electrical transmission
3projects take into account the May 2016 Solar Convening Report,
4titled “A Path Forward: Identifying Least-Conflict Solar PV
5Development in California’s San Joaquin Valley, ” and the
6principles of transmission corridor planning developed by the
7State Energy Resources Conservation and Development
8Commission in response to Senate Bill 2431 (Chapter 1457 of the
9Statutes of 1988), known as the Garamendi Principles.
begin insertSection 399.23 is added to the end insertbegin insertPublic Utilities Codeend insertbegin insert,
11to read:end insert
(a) The Independent System Operator, when
13undertaking transmission planning activities, shall take into
14account the May 2016 Solar Convening Report, titled “A Path
15Forward: Identifying Least-Conflict Solar PV Development in
16California’s San Joaquin Valley,” and the principles of
17transmission corridor planning developed by the Energy
18Commission in response to Senate Bill 2431 (Chapter 1457 of the
19Statutes of 1988), known as the Garamendi Principles.
20
(b) The Energy Commission, the commission, and the
21Independent System Operator, when undertaking activities as part
22of the Renewable Energy Transmission Initiative, shall take into
23account the May 2016 Solar Convening Report and the Garamendi
24Principles.
This act shall be known, and may be cited, as the
26San Joaquin Valley Clean Energy and Jobs Act.
The Legislature finds and declares all of the following:
28(a) The California Global Warming Solutions Act of 2006
29(Division 25.5 (commencing with Section 38500) of the Health
30and Safety Code) established a policy to reduce emissions of
31greenhouse gases to 1990 levels by 2020 and to continue reductions
32of emissions of greenhouse gases beyond 2020.
33(b) The Clean Energy and Pollution Reduction Act of 2015
34(Chapter 547 of the Statutes of 2015) established further clean
35energy policies to reduce emissions of greenhouse gases and
36expand generation from eligible renewable energy resources to at
37
least 50 percent of total retail sales of electricity in California by
38December 31, 2030.
P4 1(c) The San Joaquin Valley remains mired in chronic double
2digit unemployment, unprecedented rates of poverty, a severe
3ongoing drought, and poor air quality.
4(d) California’s energy sector is undergoing significant
5advancement and transformation driven by evolving regulation,
6expanding renewable energy goals, and increasing greenhouse gas
7emissions reduction efforts.
8(e) While rich in natural resources and clean energy
9opportunities, the San Joaquin Valley has largely been left behind
10in California’s clean energy revolution. The overwhelming majority
11of the state’s new transmission assets have been sited in other
12regions,
particularly southern California, and renewable energy
13resource project investment, jobs, and economic and environmental
14benefits have followed grid access.
15(f) Unlocking the renewable energy potential of the San Joaquin
16Valley by providing more equitable investment in a clean energy
17economy should be a key priority of California policymakers.
18(g) Timely investment and improved transmission access are
19critical to the San Joaquin Valley and will allow the region to more
20effectively and efficiently develop clean energy
opportunities at
21all solar project locations, create jobs, and derive cobenefits for
22disadvantaged communities.
23(h) The Governor’s office has completed the San Joaquin Valley
24Solar Convening identifying high potential solar energy
25developments in the San Joaquin Valley that maximize renewable
26energy benefits and minimize environmental biological and habitat
27impacts.
28(i) The report issued by the University of California in May
292016 on the outcome of the convening, entitled “A Path Forward:
30Identifying Least-Conflict Solar PV Development in California’s
31San Joaquin Valley,” identified 470,000 acres of least-conflict
32land, amounting to roughly 5 percent of the 9.5 million acres in
33the stakeholder study area.
34(j) In order to identify least-conflict lands, the project team
35convened four stakeholder groups early in the process: (1) an
36environmental conservation group, (2) an agricultural farmland
37conservation group, (3) a solar industry group, and (4) a
38transmission group. An agricultural rangeland stakeholder group
39was later added to gain a better understanding of regional land
40value from this stakeholder perspective.
P5 1(k) The project team generated the final result, the composite
2least-conflict area, using the information developed with the solar
3industry, environmental conservation, and agricultural farmland
4conservation stakeholder groups.
5(l) Given the proximity to existing transmission corridors, solar
6projects in the San Joaquin Valley can be developed in a way that
7minimizes
the need for new transmission by prioritizing the use
8of existing transmission corridors consistent with the principles
9of transmission corridor planning developed by the State Energy
10Resources Conservation and Development Commission in response
11to Senate Bill 2431 (Chapter 1457 of the Statutes of 1988), known
12as the Garamendi Principles.
13(m) As future clean energy investments are planned and
14implemented, state officials must ensure an appropriate share is
15targeted to improve environmental quality, expand economic
16development, contribute to environmental solutions, and create
17jobs in the San Joaquin Valley.
Section 399.23 is added to the Public Utilities Code,
19to read:
(a) The commission and the Energy Commission shall
21evaluate, while taking into consideration ratepayer costs and
22benefits, potential eligible renewable energy resource projects in
23the San Joaquin Valley. Evaluation of projects that provide the
24following benefits or attributes shall be prioritized:
25(1) The economically viable and environmentally beneficial
26reuse of drainage-impaired agricultural lands.
27(2) The retirement of drainage-impaired agricultural land and
28facilitation of regional agricultural drainage solutions.
29(3) The
facilitation of surface water supply redirection from
30drainage-impaired agricultural lands to other productive agricultural
31land.
32(b) Using the results of the evaluation, on or before January 31,
332017, the commission and the Energy Commission shall
34recommend to the Independent System Operator an amount of
35electricity to be generated from eligible renewable energy resources
36in the San Joaquin Valley that reasonably maximizes the amount
37of electricity to be generated from eligible renewable energy
38resources, consistent with the state’s overall need for electricity
39and the requirements of this article, and that accomplishes all of
40the following:
P6 1(1) Takes into account the 470,000 acres identified in the
2Governor’s May 2016 Solar Convening Report, entitled “A Path
3Forward:
Identifying Least-Conflict Solar PV Development in
4California’s San Joaquin Valley,” along with all other lands in the
5Central Valley that have entitlements for solar development.
6(2) Provides eligible renewable energy resources within the San
7Joaquin Valley with full capacity deliverability status.
8(3) Minimizes the need for new transmission by prioritizing the
9use of existing transmission corridors consistent with the principles
10of transmission corridor planning developed by the Energy
11Commission in response to Senate Bill 2431 (Chapter 1457 of the
12Statutes of 1988), known as the Garamendi Principles.
13(c) Using the results of the evaluation, on or before January 31,
142017, the commission and the Energy Commission shall
15recommend
to the Independent System Operator any network
16transmission upgrades needed to fulfill the recommendations made
17pursuant to subdivision (b). This recommendation shall seek to
18minimize the need for new transmission by prioritizing the use of
19existing transmission corridors consistent with the Garamendi
20Principles of transmission corridor planning.
O
96