BILL ANALYSIS                                                                                                                                                                                                    



                                                                  AB 1511
                                                                  Page  1

          Date of Hearing:   May 4, 2005

                       ASSEMBLY COMMITTEE ON LOCAL GOVERNMENT
                                Simon Salinas, Chair
                      AB 1511 (Evans) - As Amended:  May 2, 2005
           
          SUBJECT  :   Design-build contracting.

           SUMMARY  :   Authorizes 19 additional counties to enter into  
          design-build contracts, extends the sunset of the authorization  
          from 2006 to 2011, and makes specified changes to the conditions  
          and requirements for design-build contracting by counties.   
          Specifically,  this bill  :  

          1)Authorizes the Counties of Butte, Del Norte, Fresno, Humboldt,  
            Madera, Mariposa, Mendocino, Merced, Monterey, Napa, Placer,  
            San Diego, San Joaquin, San Luis Obispo, Shasta, Siskiyou,  
            Stanislaus, Yolo and Yuba to enter into design-build  
            contracts.

          2)Reduces the cost threshold above which a county may award  
            design-build contracts from 
          $10 million to $5 million.

          3)Defines "best value" as a value determined by objective  
            criteria related to price, features, functions, and life-cycle  
            costs.

          4)Defines "project" as the erection, construction, alteration,  
            painting, or improvements of any office facility or other  
            building.

          5)Requires that the mandated factors of price, expertise, life  
            cycle costs, labor availability, and safety in a best value  
            design-build competition be weighed equally in the evaluation  
            of a proposal.

          6)Extends the sunset date for authorization for counties to  
            employ design-build to 
          January 1, 2011.

           EXISTING LAW  : 

          1)Requires local officials, under the Local Agency Public  
            Construction Act, to invite bids for construction projects and  








                                                                  AB 1511
                                                                  Page  2

            then award contracts to the lowest responsible bidder under  
            the traditional design-bid-build project delivery system.

          2)Defines "design-build" as a procurement process in which both  
            the design and construction of a project are procured from a  
            single entity.

          3)Defines "best value" as a value determined by objective  
            criteria that may include, but not be limited to, price,  
            features, functions, life-cycle costs, and other criteria  
            deemed appropriate by the county.

          4)Authorizes the counties of Alameda, Contra Costa, Sacramento,  
            Santa Clara, Solano, Sonoma, and Tulare to use the  
            design-build method under the following conditions:

             a)   The design-build method shall only be used for projects  
               with costs exceeding 
             $10 million;

             b)   For projects with costs ranging from $10 million to $20  
               million, the counties must award the contract to the lowest  
               responsible bidder, as specified;

             c)   For projects with costs exceeding $20 million, the  
               counties may award the contract to either the lowest  
               responsible bidder, or the bid that represents the best  
               value, as specified.

          5)Requires county officials to prepare documents describing the  
            project and its specifications; prepares a detailed request  
            for proposals, inviting competitive bids; establishes a  
            detailed procedure to pre-qualify design-build entities; and  
            establishes the procedures to select the design-build entity.

          6)Requires county supervisors to establish and enforce labor  
            compliance programs.

          7)Requires counties to collect specified types of information  
            when pre-qualifying design-build entities.

          8)Requires a prospective design-build entity to list its  
            proposed mechanical subcontractors and licenses, report past  
            worker safety violations, contracting problems, contract  
            defaults, license violations, payroll violations, and  








                                                                  AB 1511
                                                                  Page  3

            bankruptcies, and verify this information under oath.

          9)Requires county officials to select the design-build entity by  
            using either a competitive bidding process in which the award  
            goes to the lowest responsible bidder, or a best value  
            competition in which county officials set the criteria.

          10)Requires that at least 50% of the weight of these best value  
            factors must include price, expertise, life cycle costs, labor  
            availability, and safety records.

          11)Requires the county to rank the top three responsive bidders,  
            award the contract to the responsible bidder whose proposal  
            county officials rank as "the most advantageous," and identify  
            the second and third ranked bidders after it publicly  
            announces the award.

          12)Requires the winning design-build entity to be bonded and  
            carry errors-and-omissions insurance to cover its design and  
            architectural services.

          13)Requires the entity to adhere to the county's performance  
            criteria and design standards and obtain the county's written  
            consent for any deviations from these standards, and  
            authorizes the county to hire a design professional to ensure  
            compliance.

          14)Authorizes the winning design-build entity to use  
            subcontractors not listed in its original bid, but requires  
            the entity must award these subcontracts by following a  
            process set by the county, including publishing notices and  
            setting deadlines.

          15)Permits the county to retain no more than 5% of the contract  
            if the county's bid request required the design-build entity  
            to carry a performance and payment bond.

          16)Repeals the authorization for the specified counties to use  
            design-build contracts on 
          January 1, 2006.
           
           FISCAL EFFECT  :   None

           COMMENTS  :









                                                                  AB 1511
                                                                  Page  4

          1)The Local Agency Public Construction Act requires local  
            officials to invite bids for construction projects and then  
            award contracts to the lowest responsible bidder.  This  
            design-bid-build method is the traditional approach to public  
            works construction.

          2)Private companies often use the design-build method for  
            construction projects.  Under the design-build method, a  
            single contract covers the design and construction of a  
            project with a single company or consortium that acts as both  
            the project designer and builder.  The design-build entity  
            arranges all architectural, engineering, and construction  
            services, and is responsible for delivering the project at a  
            guaranteed price and schedule based upon performance criteria  
            set by the public agency.  The design-build method can be  
            faster 
          (and therefore, cheaper) than the design-bid-build method, but  
            it requires a higher level 
          of management sophistication since design and construction may  
            occur simultaneously.

          3)The Legislature has granted authority to some public agencies  
            to use the design-build project delivery method under  
            specified circumstances.  Special legislation has authorized  
            seven counties, six cities, one special district, transit  
            districts, and school districts to use the design-
          build project delivery method for a limited time.  The  
            design-build language in current law is a compromise struck in  
            2000 among local officials, labor groups, and contractors (AB  
            2296 (Dutra), Chapter 594, Statutes of 2000).  Local officials  
            wanted the flexibility and potential cost savings offered by  
            design-build contracts.  Labor unions wanted to ensure that  
            counties pre-qualify employers to protect workers' interests.   
            Contractors wanted to be sure they had fair access to county  
            contracts.

          4)Advocates for the design-build method of contracting for  
            public works contend that project schedule savings can be  
            realized because only a single request for proposals is needed  
            to select the project's designer and builder.  The more  
            traditional design-bid-build project approach requires the  
            separate selection of the design consultant or contractor,  
            completion of design, and then advertising for bids and  
            selection of the construction contractor.  Proponents add that  
            design-build allows the overlap of design and construction  








                                                                  AB 1511
                                                                  Page  5

            activities, resulting in additional time savings and lower  
            project costs.  By avoiding the delays and change orders that  
            result from the traditional design-bid-build method of  
            contracting, proponents argue that officials can deliver  
            public works faster and cheaper.

          5)By allowing local officials to pick just one company to  
            orchestrate an entire construction project, the design-build  
            method contains an implicit preference for large companies and  
             partnerships.  The design-build method may exclude smaller,  
            local firms that lack the capital or expertise to compete  
            against big partnerships or vertically integrated companies.   
            However, smaller firms may still be able to participate in a  
            support role as a subcontractor in the design-build method.



          6)Opponents of design-build in the past have contended that the  
            cost savings afforded by design-build are overstated and  
            unproven, citing cases where costs have significantly  
            increased because the public agency loses responsibility for  
            the project.  Opponents also caution that design-build  
            endeavors are extremely complicated from a management  
            perspective, requiring a thorough understanding of the roles  
            and responsibilities of each participant in the process.  

          7)Past opponents have also objected to the fact that, for  
            projects costing over $20 million, an authorized county has  
            the option of awarding a contract to the lowest responsible  
            bidder or a bidder on a best value basis.  Best value  
            currently may include, but not be limited to, criteria such as  
            price, features, functions, life-cycle costs, and "other  
            criteria deemed appropriate."  AB 1511 tightens this  
            definition up significantly by requiring that price, features,  
            functions, life-cycle costs, and nothing else, are the  
            objective criteria by which best value is to be determined.

          8)SB 1759 (Johannessen), Chapter 976, Statutes of 2002, placed a  
            moratorium on the enactment of any additional legislation  
            relating to design-build contracting until any reports  
            required by existing law have been received by the  
            Legislature.  Local officials were required to submit reports  
            detailing their experience with the design-build method to the  
            Legislative Analyst's Office (LAO) by December 1, 2004, and  
            the LAO was required to report its findings to the Legislature  








                                                                  AB 1511
                                                                  Page  6

            by January 1, 2005.  That report found that, of the counties  
            authorized to use design-build contracting, Alameda,  
            Sacramento, and Solano counties had used the design-build  
            statute and that Contra Costa, Santa Clara, Sonoma, and Tulare  
            had not.  After reviewing the counties' experiences, the LAO  
            recommended that:

             a)   The Legislature should adopt an inclusive, uniform  
               statute.

             b)   Design-build should be optional and not replace  
               design-bid-build.

             c)   Contracts for most project costs should be based on  
               competitive bidding, not best value.

             d)   State law should ensure access for the greatest number  
               of contractors.

             e)   There should be no cost limitations.

             f)   Design-build should apply only to buildings.

          9)AB 1511 fully incorporates two of these recommendations:  
            design-build should be optional and should apply only to  
            buildings.  While it still includes cost limitations, it  
            lowers the threshold above which design-build may be employed.  
             It does not limit the types of contracts based on best value,  
            but it does tighten up the definition of best value.  It  
            expands the number of counties that may use design-build from  
            seven to 26, but that is still fewer than half of the state's  
            counties - far from an "inclusive, uniform statute."

          10)One of the principal reasons for the imposition of the  
            moratorium on design-build legislation was to find an  
            alternative to the piecemeal approach to the matter that saw  
            separate bills proposing to extend design-build to additional  
            counties, cities, districts, and even individual projects.   
            The LAO's report recommended that the Legislature enact a  
            uniform design-build statute that all local governments can  
            use.  Proponents of this and other design-build bills may  
            argue that the express condition for lifting the moratorium -  
            the issuance of the LAO report - has been met, but the  
            Committee may wish to consider whether resuming the scattergun  
            approach to the issue that existed prior to the moratorium  








                                                                  AB 1511
                                                                  Page  7

            runs counter to the spirit, if not the letter, of the  
            moratorium, and merely returns the Legislature to the status 
          quo ante.

          11)To illustrate the point made previously, AB 1511 is far from  
            the only measure before the Legislature this year seeking to  
            expand and extend public agencies' use of the design-build  
            contracting method.  So far the list includes AB 1511, AB 245  
            (Walters), AB 508 (Richman), AB 948 (Oropeza), AB 1162  
            (Mullin), AB 1329 (Wolk), AB 1663 (Jones), AB 1714 (Plescia),  
            AB 1725 (La Malfa), SB 287 (Cox), SB 371 (Torlakson), and SB  
            705 (Runner).  The Committee may wish to suggest that these  
            authors and other legislators should collaborate with  
            interested parties and one another in the study, drafting, and  
            adoption of a single bill that creates a permanent, uniform  
            design-build method for both state and local public works  
            projects as a means of actually implementing some or all of  
            the recommendations from the LAO report.  The Committee has  
            received a letter from the Construction Employers'  
            Association, representing over 100 of the largest unionized  
            commercial and industrial general contractors in California,  
            requesting that the Legislature do precisely that.

           REGISTERED SUPPORT / OPPOSITION  :   

           Support 
           
          Counties of Napa, Solano, and Sonoma [CO-SPONSORS]
          CA Association of Councils of Governments
          Counties of Alameda, Butte, Contra Costa, Del Norte, Fresno,  
          Humboldt, Madera, Mariposa, Mendocino, Merced, Placer,  
          Sacramento, San Diego, San Joaquin, San Luis Obispo, Santa  
          Clara, Shasta, Siskiyou, Stanislaus, Tulare, Yolo, and Yuba 

           Opposition 
           
          None on file

           
          Analysis Prepared by  :    J. Stacey Sullivan / L. GOV. / (916)  
          319-3958