BILL ANALYSIS                                                                                                                                                                                                    



                                                                  AB 2573
                                                                  Page  1

          Date of Hearing:   April 17, 2006

                    ASSEMBLY COMMITTEE ON UTILITIES AND COMMERCE
                               Lloyd E. Levine, Chair
                  AB 2573 (Leno) - As Introduced:  February 23, 2006
          
          SUBJECT  :   Electricity: Hetch Hetchy Water and Power solar  
          generation.

           SUMMARY  :   Increases the amount of solar generation permissible  
          for the City and County of San Francisco's (City's) net-metering  
          facilities, and permits the City to generate photovoltaic  
          (solar) power at one location and have that electricity be used  
          at another City-designated remote location.  Specifically,  this  
          bill  :  

          1)Increases the amount of power that the City can generate from  
            solar electric generation facilities, from 5 megawatts (MW) to  
            25 MW.

          2)Defines "qualifying remote new load (QRNL)," permits the City  
            to designate the QRNL site both inside and outside of the  
            City, requires the QRNL to begin operations after January 1,  
            2006, and exempts this load from the 25 MW cap.

          3)Deletes the 1 MW cap on how much electricity a single solar  
            generation facility can generate.

          4)Excludes the amount of electricity provided for QRNL from the  
            monthly true-up between City-generated electricity provided to  
            Pacific Gas and Electric Company (PG&E), and PG&E electricity  
            provided to the City.

          5)Deletes a provision that states that if the City engages in  
            retail sales to PG&E customers as a result of becoming a  
            community choice aggregator or municipalization, the section  
            that defines the City's on-site solar production and  
            Interconnection Agreement offsets would become inoperative.

          6)Permits the City to use its solar generation to serve the QRNL  
            sites and requires PG&E to treat any electricity exported to  
            the grid by the City's solar generation as "behind the meter"  
            generation that offsets the electrical usage of the QRNL  
            sites.









                                                                  AB 2573
                                                                  Page  2

           EXISTING LAW  :

          1)Defines a customer generator who would be eligible to  
            participate in net metering to generate no more than 1 MW; be  
            located on the customer's owned, leased, or rented premises;  
            and whose electricity produced is primarily to offset part or  
            all of the customer's own electrical needs.  A customer  
            generator can be a residential, commercial, industrial, or  
            agricultural customer of an electric service provider that  
            uses solar or wind.

          2)Requires the total amount of electricity generated by  
            City-owned solar generators to not exceed 5 MW of peak  
            generation capacity and requires that no single solar  
            generation project exceed 1 MW of peak generation capacity.

          3)Requires PG&E to identify the appropriate tariff for energy  
            generated at the City-owned solar sites, and apply a monetary  
            credit to offset amounts invoiced by PG&E pursuant to the  
            Interconnection Agreement between PG&E and the City.

          4)Specifies that if the City is a net energy producer, the City  
            shall receive no credit or offset for the electricity exported  
            to the grid in excess of the electricity delivered to the site  
            from the grid.    

           FISCAL EFFECT  :   Unknown.

           COMMENTS  :   According to the author, the purpose of this bill is  
          to allow the City to generate an increased amount of solar  
          electricity for use at off-site or non-adjacent City-designated  
          municipal buildings and be treated in the same manner as current  
          net-metering arrangements. 

           1) Background  : The City owns Hetch Hetchy Water and Power, which  
          provides water from the Tuolumne River to the City and its  
          residents.  The federal Raker Act (1913) permitted the City to  
          dam the Tuolumne River, build a 167-mile aqueduct, and construct  
          powerhouses and transmission lines below Hetch Hetchy Reservoir  
          for generation, sale, and distribution of electric energy.   The  
          Act also established priorities for the use of Hetch Hetchy  
          hydropower: first to drive the system's waterworks, next to  
          supply the City's municipal government agencies, and then to  
          farmers and municipal governments within the Modesto and Turlock  
          irrigation districts. Any remaining hydropower could be sold to  








                                                                  AB 2573
                                                                  Page  3

          the City's residential and business users but never to a  
          corporation, such as PG&E.

          At that time, PG&E was the sole provider of gas and electricity  
          in the City. Although the City built a transmission line from  
          the Hetch Hetchy hydroelectric plant to Newark (across the bay,  
          south of Oakland), it was unable to obtain funding for the last  
          stretch into the City.  

          The City has a unique arrangement.  PG&E continues to procure  
          generation, and provide transmission and distribution services  
          to all bundled-service ratepayers such as residential,  
          commercial, and industrial customers within the City's  
          boundaries.  However, the City owns the Hetch Hetchy power which  
          requires the City to use it for its municipal load first. As  
          such, PG&E does not procure electricity for the City's municipal  
          load.  The City needs PG&E to provide the transmission across  
          the bay and into the City, and it needs PG&E for the local  
          distribution of the power to the municipal facilities.  Over the  
          years, the City and PG&E negotiated a federally approved  
          Interconnection Agreement that identifies the terms and  
          conditions under which PG&E will transport and distribute the  
          City's Hetch Hetchy power to the City's municipal locations. 

           2) One size does not necessarily fit all  :  SB 656 (Alquist,  
          Chapter 369, Statutes of 1995) created the net metering  
          guidelines to provide an incentive to residential customers to  
          install solar panels on their homes. The intent was to decrease  
          dependence on remote generators and the transmission grid.   
          Under net metering, all electric utilities are required to buy  
          back any electricity generated by a customer-owned solar system.  
           This "buy back" works by having the solar generated electricity  
          spin the meter backward.  By spinning the meter backward, the  
          excess solar power offsets the power the customer already  
          consumed from the utility.  The end result of a net-metered  
          transaction is equivalent to the utility buying the excess solar  
          power at the utility's retail rate, which includes the utility's  
          transmission and distribution costs, taxes, the utility's return  
          on investment, and public goods charges (funding for low-income  
          assistance, energy efficiency, and renewable power programs).  
          The utilities would prefer to only pay the average wholesale  
          generation costs to the utility, or a reasonable index that  
          reflects its opportunity cost of purchasing electricity from  
          another generator.  By requiring the utility to buy back the  
          power at the retail rate, the utility's remaining customers are  








                                                                  AB 2573
                                                                  Page  4

          essentially subsidizing these net-metered customers. 

          The current net-metering provisions permit a solar generator to  
          be located on or adjacent to the facility that would use the  
          electricity, and only permit the singular solar generator to  
          generate less than 1 MW.  Net metering arrangements are  
          restricted to a specific percentage of the utilities' total load  
          to mitigate the cost shifts. At the end of each year, the  
          utility "nets out" the amount of electricity provided to the  
          utility by the customer with the amount of electricity the  
          customer purchased from the utility.  The net-metering  
          provisions discourage over-building by permitting any  
          electricity that was over-generated as determined at the end of  
          the year to be free to the utility.

          The City, as its own municipal utility, is different than a  
          singular IOU-served homeowner. Two years ago, the Legislature  
          passed AB 594 (Leno, Chapter 790, Statutes of 2004), which  
          enabled the City's municipal facilities to engage in  
          net-metering arrangements and install solar facilities to serve  
          some of the City's municipal load at the site of the municipal  
          facility.  PG&E doesn't send a typical electricity bill to the  
          City as it does with a homeowner, so it couldn't offset the  
          solar generation.  To allow for a similar end-result, AB 594  
          required PG&E to provide a credit against the Interconnection  
          Agreement.  The 1 MW cap on the size of a single facility was  
          consistent with existing net-metering provisions, however, AB  
          594 permitted the City to generate up to an aggregated total of  
          5 MW using its solar facilities. This bill would delete the 1 MW  
          cap on an individual facility, and would increase the cap on the  
          City's total net-metering load to 25 MW. The City, as the  
          sponsor of this bill, requested that these caps be increased  
          because the City is a municipal utility, and not an individual  
          homeowner. 

          The City is planning new redevelopment projects at Hunters Point  
          and Treasure Island.  It cannot serve the electricity needs with  
          solar generation because neither of these locations would  
          optimize the generating capacity of solar panels. The City is  
          located in one of the most geographically and climatically  
          diverse environments and possesses the ability to optimize solar  
          energy generation at one location during peak times, which may  
          not be on or adjacent to the facility it needs to serve.  As  
          such, placing a solar facility at or adjacent to the proposed  
          redevelopment sites, as required by current net-metering  








                                                                  AB 2573
                                                                  Page  5

          provisions, would render little benefit to the City's municipal  
          needs.

           3)  The big picture  :  Over the past few years the Legislature  
          and Governor have enacted legislation that would encourage the  
          use of clean renewable energy and localized generation.  There  
          are currently two bills in the Legislature that are trying to  
          streamline the complex and multi-jurisdictional process to  
          upgrade existing or build new transmission systems.  The City's  
          geographic position makes it vulnerable to unreliable  
          electricity supplies. It is located at the terminus of just two  
          transmission lines.  In addition, for over 40 years, the City  
          relied on old PG&E fossil-fuel burning power plants to serve  
          some of the residential and commercial customers. These plants  
          are either being retrofitted or shut down altogether.  

          Against this backdrop, the City developed its Electricity  
          Resource Plan (ERP) that proposes increasing renewable  
          generation to 50 MW by 2015.  Two years ago the City's voters  
          approved local Propositions B and H, which could potentially  
          provide over $100 million in revenue bond financing for  
          municipal and private solar projects.  Recently, the Moscone  
          Convention Center was retrofitted with solar panels that produce  
          688 kW of electricity and a second site is proposed at a  
          wastewater treatment plant that will generate 600 kW.

          It appears as if the City is progressing toward the legislative  
          directives of becoming less dependent on fossil-fuel power  
          plants and precarious transmission lines.  However, this bill  
          attempts to facilitate attaining the legislative goals by  
          confusingly trying to put the proverbial "square peg in a round  
          hole."  The bill language inserts exceptions and specifications  
          into the existing net-metering provisions. This could be  
          confusing and cause much debate. To clarify that this new  
          arrangement, the QRNL, is different than the existing  
          net-metering arrangements,  the committee may wish to consider  
          defining each of the two types of solar generation and specify  
          which provisions apply to solar generation facilities using the  
          system of credits to the Interconnection Agreement, and which  
          provisions apply to solar generation facilities that supply  
          QRNL.
           
           3)  The City's desire to build solar  :  The City's voters  
          approved bond financing for the City to self-generate its own  
          solar energy for its own use.  Under current law, if the City  








                                                                  AB 2573
                                                                  Page  6

          placed a solar facility in a sunny location to generate  
          electricity, it would over-generate for the on-site municipal  
          facility (i.e. a reservoir) and would be required to send most  
          of the energy to the PG&E grid with no compensation for the  
          generation.  This would be contrary to the intent of the City  
          propositions that authorized bond financing, and unfeasible for  
          voters.  As such, the City would likely not develop the solar  
          facility.  
           
           PG&E states that the City can build the facilities using the  
          voter-approved bonds and the City would be able to participate  
          in PG&E's Renewable Portfolio Standard (RPS) solicitations or  
          enter into a bilateral agreement to sell the solar power at  
          negotiated rates.  The City claims that this arrangement is not  
          what voters intended.  They did not vote to finance independent  
          solar generators to help PG&E meet its RPS, regardless of the  
          price that PG&E would be willing to pay for the solar energy.  

          PG&E also suggested that the City could request a separate  
          arrangement directly with PG&E in order to compensate PG&E for  
          transporting the power from the solar facility to the QRNL  
          location over PG&E's distribution system.  The City is concerned  
          that this arrangement would place it in an undesirable  
          negotiating position because the City needs PG&E to move the  
          power through the distribution system, and PG&E doesn't have the  
          same criticality and therefore is in a far superior negotiating  
          position. The City's municipal locations could be placed at risk  
          at the expense of the City's voters. If this were the case, the  
          City would likely refrain from building the solar facilities.

          The California Public Utilities Commission (PUC) regulates PG&E  
          and requires that PG&E be compensated for any system impact  
          costs.   The committee may wish to amend the bill to require PG&E  
          to distribute City-owned power to City-designated QRNL sites.   
          Include directives that there shall be no cost shifts to PG&E  
          bundled-service ratepayers as a result of engaging in this  
          arrangement.  The committee may wish to clarify that the City,  
          and not PG&E ratepayers, will pay for all reports and system  
          impacts of interconnection and reliable delivery of electricity  
          from the solar generation sites to facilities designated as  
          QRNL.  In the determination of costs, the committee may wish to  
          employ established PUC decisions for evaluating system impacts. 
           
           REGISTERED SUPPORT / OPPOSITION  :   









                                                                  AB 2573
                                                                  Page  7

           Support 
           
          California League of Cities
          California Solar Energy Industries Association (CALSEIA)
          Clean Power Campaign
          Environment California
          Planning and Conservation League
          PV Manufacturers Alliance (PVMA)
          PV Now
          San Francisco Public Utilities Commission (SFPUC) (sponsor)
          Vote Solar

           Opposition 
           
          Pacific Gas & Electric Company (PG&E)
           
          Analysis Prepared by  :    Gina Adams / U. & C. / (916) 319-2083