BILL ANALYSIS                                                                                                                                                                                                    




                                                                  AB 64
                                                                  Page A
          Date of Hearing:   April 1, 2009

                    ASSEMBLY COMMITTEE ON UTILITIES AND COMMERCE
                                Felipe Fuentes, Chair
                   AB 64 (Krekorian) - As Amended:  March 24, 2009
           
          SUBJECT  :   Energy: renewable energy resources: generation and  
          transmission.

           SUMMARY  :   Increases California's Renewables Portfolio Standard  
          (RPS) to require all retail sellers of electricity and all  
          Publicly Owned Utilities (POUs) to procure at least 33% of  
          electricity delivered to their retail customers from renewable  
          resources by 2020.  The bill addresses numerous issues that may  
          facilitate compliance, and creates the Renewables Infrastructure  
          Authority (RIA) to site and finance renewable generation and  
          transmission. 

           EXISTING LAW  :   

          1)Requires investor-owned utilities (IOUs) and certain other  
            retail sellers to achieve a 20 % RPS by 2010 and establishes a  
            process and standards for renewable procurement.  

          2)Provides that publicly-owned utilities (POUs) are not subject  
            to the same detailed process and standards as IOUs, but are  
            required to implement and enforce their own RPS programs.  

          3)Defines eligible renewable technologies to include biomass,  
            solar thermal, photovoltaic, wind, geothermal, renewable fuel  
            cells, small hydroelectric (30 megawatts (MW) or less),  
            digester gas, municipal solid waste conversion, landfill gas,  
            ocean wave, ocean thermal, and tidal current. Provides that  
            eligible renewable resources that are located outside of  
            California may count toward the California RPS if the  
            generator commences operation after January 1, 2005, and the  
            facility is directly connected to California's transmission  
            grid or the associated electricity is delivered to California.  


          4)Requires IOUs to submit annual renewable procurement plans to  
            the Public Utilities Commission (PUC). 

          5)Allows the PUC to authorize the use of Renewable Energy  
            Credits (RECs) from eligible renewable resources for retail  









                                                                  AB 64
                                                                  Page B
            sellers to meet their RPS obligations. Allows POUs to sell  
            RECs to retail sellers of electricity if the POU has  
            established a RPS that is comparable to the RPS of the IOUs  
            and is in compliance with that RPS.

          6)Requires the PUC to establish a market cost for electricity,  
            the market price referent (MPR), in order to determine whether  
            renewable contracts exceed market costs. 

          7)Creates a cap on above-market costs of renewable electricity  
            each IOU is required to spend under the RPS. If the cost cap  
            is reached, IOUs are not required to sign any renewable  
            contract that exceeds the market cost of electricity. 

          8)Requires the PUC to develop flexible rules for compliance for  
            the RPS that allow a retail seller that cannot not meet its  
            annual targets to avoid penalties under certain conditions.

          9)Requires the CEC to certify sufficient sites and related  
            facilities for the construction and operation of thermal  
            powerplants of 50 MW and larger.

          10)Precludes an electrical corporation from constructing a line,  
            plant, or system without having first obtained a certificate  
            from the PUC that the present or future public convenience and  
            necessity require or will require such construction  
            (certificate of public convenience and necessity, or CPCN).


           THIS BILL  :  

          1)Requires retail sellers of electricity to procure at least 20%  
            of electricity delivered to retail customers from renewable  
            sources by 2010, 25% by 2015, and 33% by 2020.

          2)Requires POUs to comply with the same RPS mandates as retail  
            sellers, requires the POUs to meet specified public notice and  
            reporting requirements, and grants the California Air  
            Resources Board (CARB) the authority to issue penalties on the  
            POU if they fail to meet the RPS mandates. 

          3)Provides that the code sections governing California's current  
            RPS shall sunset in 2011 and recasts these provisions in new  
            sections along with the changes noted in this analysis.










                                                                  AB 64
                                                                  Page C
          4)States the intent of the Legislature that the RPS shall  
            accomplish the following objectives:
             a)   Reduce emissions of greenhouse gases. 
             b)   Reduce in-state consumption of nonrenewable fuels in  
               order to improve public health.
             c)   Stimulate sustainable economic development.
             d)   Decrease California's reliance on imported sources of  
               energy.
             e)   Increasing fuel diversity. 

          5)Provides that electricity from an out-of-state renewable  
            facilities is not eligible for the California RPS unless the  
            electricity is scheduled into California simultaneous to its  
            generation.  

          6)Requires that a utility's renewable procurement plan asses the  
            viability of proposed renewable products based on the  
            developer's experience, the feasibility of the technology, and  
            risk of delay of construction. 

          7)Allows a retail seller or POU to use RECs from any renewable  
            facility in the Western Electricity Coordinating Council  
            (WECC) territory toward its RPS obligation, but provides that  
            a retail seller or POUs may meet no more than 10% of its PRS  
            obligation using RECs from facilities that do not deliver  
            their electricity into California. 

          8)Replaces the current Market Price Referent calculation and  
            instead requires the PUC to develop a benchmark price for  
            renewable electricity, which will be used to determine if an  
            individual contract is above general market values of  
            electricity, that takes into account the price of all fixed  
            price contracts, the value of deliverability characteristics  
            of different contracts, the value of carbon reductions from  
            renewable resources, and the value of any other emission  
            reductions. 

          9)Requires the PUC to establish a cost cap for total above  
            market costs (costs that exceeded the benchmark price)  
            expended by each IOU. Provides that the cap shall not exceed  
            an unspecified percentage of the IOUs revenue requirement. If  
            the cost cap is exceeded the IOU shall be allowed to limit  
            renewable procurement to renewable resources that can be  
            procured below the benchmark price. 










                                                                  AB 64
                                                                  Page D
          10)Provides that the PUC MAY waive existing penalty provisions  
            for non-compliance with the 20% RPS mandate if the PUC finds  
            that the retail seller has made "commercially reasonable  
            efforts to procure eligible renewable energy recourses."  

          11)Eliminates the requirement that the PUC create flexible rules  
            of compliance for renewable procurement requirement beyond  
            20%. 

          12)Requires the PUC to expand an existing feed-in-tariff program  
            for generation units smaller than 1.5 MW to include all  
            renewable generation up to 5 MW. 

          13)Requires the PUC to provide a preference for energy resources  
            that come from a California supplier in developing the IOUs'  
            procurement plans.

          14)Creates the Renewable Infrastructure Authority (RIA) with the  
            powers to establish, finance, purchase, lease, own, operate,  
            acquire, or construct generating facilities that are eligible  
            renewable energy resources and other projects that further the  
            state's renewable energy goals.

             a)   Provides the RIA to be governed by a 9-member board,  
               consisting of the secretaries and chairs of state agencies  
               that affect electricity planning, siting, regulating and/or  
               constructing.

             b)   Requires the RIA to certify all sites and related  
               facilities for all renewable generation facilities with a  
               minimum generating capacity of 5 megawatts (MW).

             c)   Permits the RIA to identify suitable zones for renewable  
               energy generation, conduct studies, perform as the lead  
               agency for California Environmental Quality Act (CEQA)  
               compliance for all generation projects proposed in the  
               designation zone, and issue a proposed decision for siting  
               the facility within 180 days after the date the generator's  
               application was deemed complete.

             d)   Permits the RIA to request proposals from qualified  
               participating parties to develop generation facilities, and  
               if after 45 days the RIA determines it is necessary and  
               feasible, the RIA shall exercise its authority to build,  
               own, and operate generation facilities as part of a  









                                                                  AB 64
                                                                  Page E
               least-cost electrical supply policy.

             e)   On or after January 1, 2011, provides the RIA with  
               exclusive power to certify all electric transmission lines,  
               remote resource interconnection lines, electric  
               transmission facilities, and facilities appurtenant  
               thereto, and related facilities in the state.

               i)     Exempts facilities for which the PUC has issued a  
                 CPCN.

               ii)    Exempts electric transmission lines that connect  
                 generation facilities to the high-voltage transmission  
                 grid that are under the siting authority of the CEC  
                 (gen-tie lines).

             f)   Permits the RIA to identify suitable sites for the  
               construction of electric transmission lines, on its own  
               motion or a motion by the CEC, or by an applicant who plans  
               to construct an electric transmission line within the  
               state, and allows the RIA to conduct studies, perform as  
               the lead agency for CEQA compliance, use bond authority,  
               and request proposals from qualified participating parties.  


             g)   Requires the RIA, by January 1, 2011, and annually  
               thereafter, and in consultation with the CEC and CAISO, to  
               develop a Renewables Investment Plan that shall take into  
               account the state's electric generation and transmission  
               needs over the next decade, and outlines a strategy for  
               cost-effective investments, and requires all investments  
               made by the RIA to be consistent with the strategy outlined  
               in the Renewables Investment Plan. 

          15)Permits the RIA to issue bonds in an amount not to exceed  
            $6.4 billion to finance activities associated with renewable  
            energy generation projects.

          16)Precludes the RIA from financing or approving any new  
            program, enterprise, or project on or after December 31, 2020.


          FISCAL EFFECT  :   Unknown.

           COMMENTS  :   According to the authors, the purpose of this bill  









                                                                  AB 64
                                                                  Page F
          is to increase the amount of electricity procured from renewable  
          generation sources to reduce greenhouse gas emissions, improve  
          public health and air quality, stimulate economic development by  
          encouraging innovation in energy technologies and creating new  
          employment opportunities in California, and increase fuel  
          diversity to promote greater stability and predictability in  
          electricity process for consumers.  In addition, this bill is  
          intended to provide developers with an over-arching authority  
          that includes the number of disparate and often conflicting  
          state agencies to establish consistency, cohesion, and a single  
          point of contact. 

           Background  :  In 2002, the Legislature approved SB 1078 (Sher),  
          Chapter 516, Statutes of 2002, which created the RPS.  Under SB  
          1078, all retail sellers of electricity were required to  
          increase their renewable procurement each year by at least 1% of  
          total sales, so that 20% of their sales are from renewable  
          energy sources by December 31, 2017.  This goal was accelerated  
          to 20% renewable power by 2010 by SB 107 (Simitian), Chapter  
          464, Statutes of 2006.  
               
          The PUC reports that, for 2007, the IOUs have achieved varying  
          levels of progress toward the 20% goal: PG&E = 11.4%; SCE  
          =15.7%; SDG&E = 5.2%.  While each IOU added renewable resources  
          in 2007, the percentage of renewables compared to the rest of  
          the portfolio declined from 2006 due to total load growth. All  
          agencies and stakeholders agree that the IOUs will not meet the  
          2010 deadline.  However, the PUC reported in October 2008 that  
          the IOUs should be in compliance in or around 2013.

          1)  Eligible Resources  :  Current law defines renewable  
          electricity as electricity that comes from biomass, solar  
          thermal, photovoltaic, wind, geothermal, fuel cells using  
          renewable fuels, small hydroelectric generation of 30 MW or  
          less, digester gas, municipal solid waste conversion, landfill  
          gas, ocean wave, ocean thermal, or tidal current can count  
          toward a retail seller's RPS.   To count toward a retail  
          seller's RPS obligation, the facility must meet several other  
          requirements including that the facility be located in  
          California or deliver its electricity to California. 

          The definition of "delivered" in current law was written to  
          allow an out-of-state renewable generator that wants to serve  
          California load to comply with California Independent System  
          Operator (CAISO) rules that require out-of-state electricity to  









                                                                  AB 64
                                                                  Page G
          be scheduled into California at specific times and amounts.  
          Since renewable resources like wind and solar are intermittent,  
          they cannot be scheduled at specific times and amounts. The  
          intent of the language was for the renewable energy to come to  
          California at some point and then offset the need for fossil  
          fuel generation within California. However, the CEC, which sets  
          the eligibility rules, interpreted the statutory language to  
          allow for transactions where the renewable electricity never  
          comes to California to count toward the RPS.  

          The definitions of renewable resources are generally accepted  
          except the definition of what types and size of hydroelectricity  
          facilities can count toward the RPS. Current law provides that a  
          hydroelectric facility must have a capacity of 30 MW or less and  
          must meet other specified streamflow standards to count toward  
          the RPS.<1>  Most of the POUs would like to have this definition  
          changed to increase the allowable capacity to 50 MW.   
          Additionally, PG&E has requested that small hydroelectric  
          facilities in British Columbia count toward its RPS obligation  
          if the facilities comply with British Columbia's environmental  
          standards but not California standards. 

          AB 64 changes the current definition of "delivered" so that the  
          renewable energy from an out-of-state facility must be scheduled  
          into California at the same time it was produced by the  
          out-of-state facility. Additionally, AB 64 changes specific  
          restrictions on the use of municipal solid waste so that  
          electricity from new solid waste conversion facilities may count  
          toward the RPS if the facility meets specific environmental  
          standards.

          2)  Renewable Energy Credits  : A Renewable Energy Credit (REC)  
          represents the renewable attributes of renewable generation. A  
          REC can remain bundled with the associated energy.  In that  
          case, the utility buys the renewable power and uses the RECs to  
          meet its RPS obligation and uses the associated electricity to  
          meet its own load.  RECs can also be traded separate from the  
          underlying electricity (tradable RECs or tRECs).  In this case,  
          one retail seller purchases the tREC and applies it toward its  
          RPS obligation and another retail seller purchases the  
          associated electricity to meet its own load. The second retail  
          ---------------------------
          <1> Current law also allows all electric generation that is the  
          result of efficiency improvements to existing hydroelectric  
          facilities to count toward the RPS, regardless of the size of  
          the original output of the facility. 








                                                                  AB 64
                                                                  Page H
          seller cannot count that electricity toward its own RPS  
          obligations.

          California law allows the use of tRECs to meet RPS obligations,  
          but the tRECs must come from a facility that meets all of the  
          requirements to be an eligible renewable resource. The tREC must  
          come from a facility that is located in state or from an  
          out-of-state facility that is built after 2005 and delivers the  
          associated electricity into California. While current law allows  
          for tRECs, it also requires the PUC to develop specific rules on  
          tREC eligibility before retail sellers can count tRECs toward  
          their RPS obligations. A decision to implement the tREC rules is  
          pending at the PUC. 

          Most retail sellers and some renewable generators have advocated  
          for broader use of RECs. The retail sellers and the Clean Power  
          Campaign state that the RPS should not limit the use of RECs or  
          put restriction on the geographic location or deliverability of  
          the associated renewable resource. They believe this broad REC  
          market would give retail sellers more procurement options and  
          could reduce the cost of complying with the RPS. 

          A number of environmental groups, the Coalition of Utilities  
          Employees, the Large Solar Association, and California Wind  
          Energy Association have all advocated for a very limited  
          allowance for out-of-state RECs. They fear that a wide-open REC  
          market will lead to "paper compliance with the RPS" and will not  
          result in the construction of any renewable generation within  
          California. 

          The determination of what the allowance of non-delivered  
          out-of-state RECs will be comes down to the question of what are  
          the goals of the RPS program. The author and the intent language  
          state that the goals of AB 64 are: 1) reduction of greenhouse  
          gases, 2) increased air quality and public health in California  
          through the reduction of fossil fuel generation within  
          California, 3) increased fuel diversity and reduced reliance on  
          imported energy, and 4) economic development within California. 

          A renewable facility constructed in California would meet all  
          four of these goals. 

          A wind farm in Oregon that sells its RECs to a California retail  
          seller meets the first goal since it generally offsets the need  
          for electricity from a carbon emitting resource. This Oregon REC  









                                                                  AB 64
                                                                  Page I
          transaction only meets the second and third goal if the  
          transaction also requires that electricity is delivered into  
          California since that electricity will offset the need for  
          in-state generation. The wind farm in Oregon does not help meet  
          the fourth goal. 

          AB 64 allows for a limited amount of non-delivered tRECs to  
          count toward the California RPS. The bill provides that a retail  
          seller or POU can use tRECs from out-of-state renewable  
          generation that is not delivered into California to meet up to  
          10% of their RPS obligation.

          3)  Cost containment  : Current law limits the amount of renewable  
          electricity an IOU is required to acquire under the RPS,  
          regardless of the annual RPS targets that apply to the IOU.  The  
          limit is based on the valuation of how much has been spent on  
          renewable procurement that exceeds the forecasted market price  
          of electricity. 

          The PUC determines the forecasted market price of electricity on  
          an annual basis based on the estimated cost of running a natural  
          gas fired power plant plus the cost of carbon emissions from a  
          natural gas facility. The market price is referred to as the  
          market price referent (MPR).  The cost estimates also include  
          adders that increase the value for electricity that is delivered  
          at times of peak demand when electricity is generally more  
          expensive. These adders have the impact of creating a higher MPR  
          for solar which generates more electricity during peak demand  
          time than wind, which is generated mostly at night. 

          An IOU must purchase renewable electricity even when the  
          contract cost exceeds the MPR. However, an IOU is required to  
          acquire this higher-cost renewable electricity only to the  
          extent that the above-market costs are less than the cost cap.  
          If the above-market costs exceed the cost cap, then the IOUs are  
          not required to sign any additional contracts that exceed the  
          MPR. However, if there are suitable contracts with costs less  
          than the MPR the IOU would still be required to procure power  
          under those contracts. 

          The MPR was intended to be tool a to identify any approved  
          above-market costs of a specific renewable contract. Some  
          renewable developers and most environmental groups believe that  
          the MPR has actually become the de-facto price of renewable  
          power and that they are forced to bid into the IOUs procurement  









                                                                  AB 64
                                                                  Page J
          requests at the MPR. If this is the case, the MPR could limit  
          the number of developers willing to bid into the RPS since the  
          MPR can be lower than the actual generation costs. The limited  
          amount of publicly available data from the IOUs procurement  
          process does not completely support this position. The IOUs have  
          signed a number of contracts that exceed the MPR. 

          The cost cap itself was not established based on a determination  
          of the perceived reasonable cost of renewables, ratepayer  
          benefits, or tolerable ratepayer impacts.  Instead, it was based  
          on the amount of funds that were to be collected for prior  
          renewable electricity grant program.  Consequently, it is  
          possible that the cap was set at a level that makes achieving a  
          20% RPS or a 33% RPS impossible. While the current cost cap has  
          not been reached, the PUC testified at a hearing of the Select  
          Committee on Renewable resources that is likely that a  
          determination will be made in the next month that the cap has  
          been reached.

          This cost cap process only applies to renewable contracts that  
          are signed through an annual Request for Proposal (RFP) process  
          conducted by the IOUs.  The IOUs have signed bi-lateral  
          contracts that were negotiated outside of the RFP process that  
          exceed the MPR, but those above-market costs do not count  
          against the cost caps. ESPs are required to meet the RPS but  
          they have no cost cap.

          Many renewable developers, the IOUs, TURN, and the Union of  
          Concerned Scientists have all stated that they believe some cost  
          containment mechanism is needed as part of the RPS so that the  
                                                 program does not become a "renewables at any cost" program which  
          could lead to massive rate increases to fund renewable  
          procurement. These groups do not agree on what is the best form  
          of cost containment. The options include leaving the current  
          cost containment in place but increasing the cost caps to better  
          reflect the estimated cost of achieving a 33% RPS, eliminating  
          the MPR but then capping the amount of money each retail seller  
          is expected to spend on the total cost of renewable power (not  
          just the above-market costs), or creating an Alternative  
          Compliance Payment System (ACPs). 
           
          AB 64 modifies and renames the MPR process so that it takes into  
          account more factors and will not be based solely on natural  
          gas. The bill also sets the cost cap at an unspecified  
          percentage of the retail sellers' gross revenue. The intent of  









                                                                  AB 64
                                                                  Page K
          this provision is to determine how much impact renewable  
          electricity should have on a retail sellers' overall cost  
          structure and then set the cost cap at that level by basing it  
          on a percentage of overall revenue. 

          The authors had initially not specified the actually cost cap in  
          the introduced version of AB 64 in order to solicit input from  
          stakeholders on where the cap should be set. While a number of  
          impacted parties have not offered any input on where the cap  
          should be set, the groups that did all suggested 5% of the  
          retail gross revenue is the appropriate level.   The committee  
          and the author may wish to consider amending the bill to remove  
          the unspecified cost cap and provide that the cap is set at 5%  
          of gross revenue. 
           
          4)  Enforcement and Off Ramps  : Current law requires the PUC to  
          enforce IOU and ESP compliance with the RPS.  The PUC may fine  
          an IOU or an ESP that fails to meet its year-to-year RPS target.  
          The PUC has set the penalties at 5 cents per kilowatt hour by  
          which the retail seller falls short of its RPS target. The PUC  
          has capped the total amount of penalties that can be charged in  
          a year at $25 million. Current law does not direct the use of  
          these penalty monies, which will be deposited in the state  
          General Fund.

          Current law also requires the PUC to develop rules of flexible  
          compliance that would allow retail sellers to avoid penalties  
          for non-compliance under certain conditions. The flexible  
          compliance rules allow retail sellers to miss RPS goals in one  
          year provided that it meets that goal within three years. This  
          means that a retail seller will not be penalized for failing to  
          meet the 20% by 2010 goal if it actually procures 20% of its  
          power from renewable resources by 2013. 

          A second flexible compliance rule allows the PUC to waive  
          penalties for a retail seller if the PUC finds that there was  
          insufficient transmission to meet the RPS goals and the retail  
          seller has made all reasonable efforts to ensure that the  
          necessary transmission would be available. 

          There is currently no penalty or enforcement mechanism in place  
          for POUs since there is no specific RPS mandate in statute for  
          the POUs. AB 64 provides that CARB may enforce penalties on the  
          POUs if they fail to meet their RPS targets.










                                                                  AB 64
                                                                  Page L
          AB 64 replaces the existing rules for flexible compliance and  
          instead allows the PUC to waive all penalties for failing to  
          meet the 20% RPS requirement if the PUC finds that retail seller  
          made "a commercially reasonable effort to procure eligible  
          renewable resources" in an amount sufficient to meet its RPS  
          obligations. AB 64 provides that the PUC may fine retail sellers  
          for failure to meet the 2015 target of 25% renewable resources  
          and the 2020 target of 33% renewable resources but does not  
          provide for any flexibility to waive or delay those penalties. 

          While AB 64 allows for the imposition of penalties on both POUs  
          and retail sellers, the bill provides that different agencies  
          impose the fines. This could lead to an uneven application of  
          penalties if the PUC and CARB do not act in concert. 

          5)  Publicly Owned Utilities  : Current law does not require POUs  
          to meet the same RPS that other electricity providers are  
          required to meet. Rather, current law directs each publicly  
          owned utility to put in place and enforce its own RPS and allows  
          each publicly owned utility to define the electricity sources  
          that it counts as renewable.  No state agency enforces POU  
          compliance or places penalties on a publicly owned utility that  
          fails to meet the renewable energy goals it has set for itself.

          AB 64 requires the POUs to meet the 33% RPS by 2020 requirement.  
          The bill also increases public accountability for POUs by  
          requiring that the RPS be established in a public meeting and by  
          requiring the POUs to report some additional information on  
          their renewable procurement to their customers and to the CEC. 

          Most of the POUs do not object to creating a specific POU RPS  
          mandate. They have argued that requiring a state agency to  
          impose penalties is both unfair and unnecessary. The POUs argue  
          that all penalty costs would simply result in a rate increase  
          for their customers and would not result in helping that POU  
          actually procure renewable resources. Additionally, the POUs  
          believe that since their boards are directly accountable to  
          voters, their voters would remove the board members from office  
          if the POU was not in compliance with the RPS. 

          Trinity Public Utilities District argues that because it serves  
          customers using only electricity from a large hydroelectric  
          facility and it has contractual access to that same resource to  
          meet all of their load growth, an RPS requirement for them would  
          be costly and counterproductive. They have asked to be  









                                                                  AB 64
                                                                  Page M
          specifically exempted from the bill. 

          6)  Feed-in-tariffs  : California's RPS was designed to force  
          renewable generators to compete against each other by bidding  
          into an IOU solicitation for renewable resources. This  
          competition should allow the utilities to pick the best  
          available technologies and the best price. However, the  
          competitive process in place can be too expensive for smaller  
          generators to participate. These smaller generators can provide  
          benefits to the electricity grid by placing their renewable  
          generation closer to load centers and thus alleviating the need  
          for additional transmission. A number of parties have suggested  
          that the best way to promote the construction of these small  
          distributed generation resources is through a feed-in-tariff  
          that provides the generators a set price for their generation.  
          This set price means they would not have to negotiate an  
          individual contract with a utility and instead would simply  
          interconnect with the utility and the utility must take their  
          output. The CEC has recommended that the Legislature pursue a  
          feed-in-tariff for renewable generation under 20 MW in capacity  
          to promote the development of these smaller generators and the  
          PUC recently released a staff proposal to expand their current  
          feed-in-tariff program so that is encompasses more resources.  

          AB 64 contains a feed-in-tariff for generation units smaller  
          than 5 MW in capacity. While 47 of approved contracts from the  
          IOUs renewable solicitations are for generation units under 20  
          MW in capacity, less than 3.5% of all expected capacity from the  
          current renewable contracts is associated with generation units  
          under 5 MW.   

          While there appears to be broad support for feed-in-tariffs  
          there is no consensus on the size of the allowable generation in  
          the program or the price a generator should be paid. Given the  
          magnitude of the debate, every party that has commented on the  
          feed-in-tariff provisions in the bill have asked that the  
          language be removed and the issue be addressed in a separate  
          bill.  

          7)  Multi-jurisdictional utilities  : Two IOUs that serve  
          electricity customers in California also serve customers in  
          other states. In fact, for both Sierra Pacific and PacifiCorp  
          the vast majority of their customers are located outside of  
          California. Currently law requires these companies to meet a 20%  
          RPS by 2010 for their California load, but provides for a number  









                                                                  AB 64
                                                                  Page N
          of exceptions for where the generation units can be located and  
          how it is procured to account for the multi-state nature of  
          these companies. PacifiCorp has expressed concern that AB 64  
          does not carry these exceptions forward for the 33% RPS goal.  
          Without these exceptions they believe compliance with the 33%  
          mandate will be impossible. 


          8)  Siting transmission and generation:   Current law provides the  
          CEC authority to site electric generation facilities with a  
          capacity of greater than 50 MW.  As part of the CEQA compliance,  
          other state agencies provide input, such as the Coastal  
          Commission and/or the Department of Fish and Game.  Most  
          renewable generators are less than 50 MW, and therefore, are  
          approved and sited by local jurisdictions.  Any needed  
          transmission must be included in the utilities' transmission  
          plans and included in the CAISO transmission plan.  Prior to  
          building any needed transmission, the PUC must issue a CPCN  
          (which can take 3 to 4 years), and the transmission owner must  
          request cost-recovery for the transmission line from the Federal  
          Energy Regulatory Commission (FERC).

          Some developers have had their projects delayed by a state  
          agency.  In San Luis Obispo, a large solar project has been  
          indefinitely delayed due to a Department of Fish and Game field  
          office review.  Others state that local jurisdictions don't  
          often possess the experience or the resources to expeditiously  
          site electric generation facilities.

          In 2006, the PUC recommended that solutions be developed that  
          would allow cost recovery mechanisms to mitigate transmission  
          owners' risk and renewable developers' "transmission financing  
          hurdles and uncertainties."  The PUC also recommended  
          streamlining the permitting process, and evaluating the  
          interconnection process and its coordination with procurement  
          and transmission expansion. 

          AB 64 establishes the RIA to provide a comprehensive and  
          integrative process to facilitate integrating increasing amounts  
          of electricity generated by renewable sources into the state's  
          energy portfolio.  The RIA provides the authority to plan for,  
          site, and if needed, finance generation facilities.  It also  
          sites all in-state transmission facilities.  

          With regard to generation, AB 64 provides RIA with siting  









                                                                  AB 64
                                                                  Page O
          authority for all renewable energy generation facilities greater  
          than 5 MW.  Any facility proposing to locate in a designated  
          renewable energy designation zone will fall under the RIA's  
          programmatic environmental impact report and can use the RIA's  
          report to comply with CEQA.  The RIA, after designating an  
          application complete, must render a decision on the siting of  
          the facility within 180 days.  

          By allowing the RIA to designate a renewable energy designation  
          zone by a motion by the CEC, the authors intend to build upon  
          the established Renewable Energy Transmission Initiative (RETI)  
          process that was initiated at the staff level by contractors  
          through the CEC and PUC.  The RETI identifies optimal renewable  
          energy designation zones and the transmission corridors  
          necessary to access the renewable generation.  

          AB 64 provides the RIA with siting authority for transmission.   
          According to the PUC 2008 RPS report, in order to attain a 33%  
          renewable energy portfolio by 2020, the state needs 7 new major  
          transmission lines (15,900 MW) at a cost of $6.4 billion.   
          Developers site a lack of reasonably priced financing as an  
          impediment to facilitating the RPS.  AB 64 provides RIA with  
          bonding authority of $6.4 billion to fund or guarantee renewable  
          energy generation and/or transmission projects, if deemed  
          feasible and in order to encourage in-state development of  
          renewable generation facilities.

          A common concern with transmission siting has been coordination  
          with the federal government, and encouraging the federal  
          agencies to work on California applications.  AB 64 permits the  
          chief executive officer to designate a liaison to the federal  
          government to facilitate when necessary the ability for the RIA  
          to site generation and transmission.  

          Some parties are concerned that the RIA powers are too broad,  
          including the powers of eminent domain and siting authority over  
          local jurisdictions.  The Sierra Club is concerned about the  
          expedited 6-month siting process for renewable facilities that  
          are located within a renewable energy designation zone.  The  
          Sierra Club recommends that any authority to permit transmission  
          should be subject to the Garamendi Principles, which require  
          considering upgrading existing transmission lines and building  
          on existing rights of way prior to constructing new transmission  
          lines using new corridors. 










                                                                  AB 64
                                                                  Page P
          Some renewable developers are concerned that because the RIA has  
          authority to purchase, lease, own, operate, or construct  
          renewable generation, the RIA may compete with viable  
          businesses.  The Clean Power Campaign encourages existing state,  
          local, and federal entities to work and communicate with each  
          other.

          The Sierra Club strongly endorses the use of public bonds to  
          finance renewable energy generation facilities.  However, it  
          recommends involving the CEC to provide guidance on how to get  
          the most benefits from bonds, and that the CEC work with the  
          State Treasurer and bond authority.

          9)  Another state agency?   AB 64 transfers certain  
          responsibilities from the CEC and PUC to the RIA.  The RIA Board  
          of Directors is comprised of the Secretaries of the Resources  
          and Environmental Protection agencies, the Chairs of the Energy  
          and Public Utilities commissions, the President of the Board of  
          the California Independent System Operator, and others.  The RIA  
          Board is provided overarching authority over the regulations  
          that govern the departments under the agencies if it deems a  
          project as a statewide priority.  The Board could conceivably  
          weigh the concerns of the different state agencies and determine  
          either a compromise, or render a decision that would encompass  
          overarching statewide needs.

          The PUC states that the PUC has existing constitutional  
          authority that provides only the PUC jurisdiction over  
          transmission siting and approval.  The PUC regulates the  
          investor-owned utilities, which comprise about 74% of  
          California's ratepayers.  The PUC ensures that public  
          convenience would be achieved by the utility building its own  
          generation and/or transmission.  The PUC states that its staff  
          plays a leading role in the RETI process to prioritize renewable  
          energy zones.  However, the PUC does not site generation  
          facilities, just only transmission facilities.  The transmission  
          owners must apply to the Federal Energy Regulatory Commission to  
          recover costs. 

          If all comprehensive planning and siting functions were  
          transferred to the PUC, the PUC's role would be greatly expanded  
          and possibly create concern over the PUC's regulatory and  
          rate-recovery role over the investor-owned utilities.  In  
          addition, the PUC is an appointed body with tremendous latitude.  
           Although the Legislature has constitutional authority over the  









                                                                  AB 64
                                                                  Page Q
          PUC, the PUC has issued decisions that may contradict  
          legislative directives or statutory requirements.  Nevertheless,  
          AB 64 retains the PUC's issuance of an IOU's certificate of  
          public convenience and necessity for IOU-owned generation and  
          transmission.  The RIA would be the lead agency for siting  
          purposes. 

          If the CEC's role was expanded to include planning and siting  
          for all generation facilities over 5 MW, the generator could  
          still be stymied by other state departments.  This may not  
          improve the current process, or alleviate some of the  
          impediments currently experienced by having numerous disparate  
          agencies having to provide certification.  

          Most letters in opposition pose overarching concerns with  
          establishing yet another state agency.  

          10)  Technical Amendments  : The Committee and the Author may want  
          to consider the following technical amendments to AB 64:  

             1)   On page 24, line 6, and on line 15, after "digester  
               gas," insert "municipal solid waste conversion,".  This  
               phrase was inadvertently removed from the current  
               definition of eligible renewable resource when it the  
               definition was redrafted into a new code section. 
             2)   On page 23, line 34, after "use" insert "and that meets  
               the requirements of Section 953". This change insures that  
               the AB 64 is consistent with existing law that provides  
               that conduit hydro electric facilities meet all eligibility  
               requirements. 
             3)   On page 37, line 21, after "retail sellers" insert "and  
               local publicly owned electric utilities". This clarifies  
               that the current system to track RECs should be used by  
               both the IOUs and the POUs. 
             4)   On page 28, line 26, replace "combustion" with  
               "conversion"
             5)   On page 34, line 3, strike "and other retail sellers".  
               This particular section only applies to IOUs and does not  
               apply to other retail sellers. 
             6)   On page 33, line 35, delete "annual". This is  
               contradictory to other provision of the bill since the bill  
               replaces annual procurement targets with new targets on  
               specified years. 

           REGISTERED SUPPORT / OPPOSITION  :   









                                                                  AB 64
                                                                  Page R

           Support 
           
          American Federation of State, County and Municipal Employees  
          (AFSCME)
          Clean Power Campaign (if amended)
          Environment California (if amended)
          First Solar (if amended)
          National Parks Conservation Association
          Northern California Power Agency (NCPA) (if amended)
          Oakland City Council
          Sierra Club California (if amended)
          Solar Alliance (if amended)
          Southern California Public Power Authority (SCPPA) (if amended)

           Opposition 
           

          Alliance for Retail Energy Markets (AReM)
          BP America Inc. (unless amended)
          California Chamber of Commerce
          California Coalition of Utility Employees (CUE) (unless amended)
          California Farm Bureau Federation (unless amended)
          California Manufacturers & Technology Association (CMTA) 
          California Public Utility Commission (CPUC) (unless amended)
          California State Association of Electrical Workers (unless  
          amended)
          California State Pipe Trades Council (unless amended)
          Imperial Irrigation District (IID) (unless amended)
          Pacific Gas and Electric Company (PG&E) (unless amended)
          Sempra Energy (unless amended)
          Southern California Edison (SCE) 
          Trinity Public Utility District (TPUD) (unless amended)
          Western States Council of Sheet Metal Workers (unless amended)
          Western States Petroleum Association (WSPA) (unless amended)


          
          Analysis Prepared by  :    Edward Randolph and Gina Adams / U. &  
          C. / (916) 319-2083