BILL ANALYSIS                                                                                                                                                                                                    



                                                                  AB 64
                                                                  Page  1

          CONCURRENCE IN SENATE AMENDMENTS
          AB 64 (Krekorian)
          As Amended  September 11, 2009
          Majority vote.
           
           ----------------------------------------------------------------- 
          |ASSEMBLY:  |44-31|(June 3, 2009)  |SENATE: |     |(September 11, |
          |           |     |                |        |     |2009)          |
           ----------------------------------------------------------------- 
                                                  (vote not available)

          Original Committee Reference:    U. & C.  

           SUMMARY  :   Implements  generation and transmission siting  
          reforms and procurement reforms to help speed the deployment of  
          renewable resources in California necessary to meet a new goal  
          of having 33% of California electricity load served by renewable  
          resources. Specifically,  this bill:

           1)Requires PUC to approve an application to build new  
            transmission lines that are reasonably necessary to develop  
            renewable resources within 18 months of the filing of a  
            completed application, if the new transmission line does not  
            threaten substantial harm to the environment that necessitates  
            a longer time for review under the California Environmental  
            Quality Act (CEQA).

          2)Clarifies that an IOU shall be allowed to recover in rates the  
            costs of constructing transmission lines that will primarily  
            deliver electricity generated renewable electricity and are  
            located in existing transmission rights-of-way or in CEC  
            designated transmission corridor zones.

          3)Requires the Department of Fish and Game (DFG) to establish an  
            internal division for the purpose of performing planning and  
            streamlined environmental compliance services with a priority  
            given to the building of eligible renewable energy resources.

          4)Provides that the California Independent System Operator  
            (CAISO), Sacramento Municipal Utilities District (SMUD) and  
            the Los Angeles Department of Water and Power (LADWP) shall  
            work cooperatively to integrate and interconnect eligible  
            renewable resources to the transmission grid by the most  
            efficient means possible to minimize the impact of and need  
            for additional transmission lines.








                                                                  AB 64
                                                                  Page  2


          5)Requires PUC to set minimum levels of renewable procurement  
            all retail sellers must achieve beyond the specified targets  
            to account for the risk that some planned resources will not  
            being developed.  The minimum level could be set at zero.  

          6)Requires renewable procurement plans prepared by IOUs and  
            approved by PUC to include a process to consider the viability  
            of proposed projects when ranking project bids.

          7)Provides that AB 64 shall not become effective unless SB 14  
            (Simitian) is also enacted prior to January 1, 2010. 

           


          EXISTING LAW  :  

          1)Requires IOUs and certain other retail sellers to achieve a  
            20% RPS by 2010 and establishes a process and standards for  
            renewable procurement.  

          2)Provides that POUs are not subject to the same detailed  
            procurement process and standards as IOUs, but are required to  
            implement and enforce their own RPS programs.  

          3)Defines eligible renewable technologies to include biomass,  
            solar thermal, photovoltaic, wind, geothermal, renewable fuel  
            cells, small hydroelectric (30 MW or less), digester gas,  
            municipal solid waste conversion, landfill gas, ocean wave,  
            ocean thermal, and tidal current. 

          4)Provides that eligible renewable resources that are located  
            outside of California may count toward the California RPS if  
            the generator commences operation after January 1, 2005, and  
            the facility is directly connected to California's  
            transmission grid or the associated electricity is delivered  
            to California. 

          5)Creates a cap on above-market costs of renewable electricity  
            each IOU is required to spend under RPS.  If the cost cap is  
            reached, IOUs are not required to sign any renewable contract  
            that exceeds the market cost of electricity. 

          6)Requires PUC to develop flexible rules for compliance for RPS  








                                                                  AB 64
                                                                  Page  3

            that allows a retail seller that cannot not meet its annual  
            targets to delay compliance for up to three years and avoid  
            penalties under certain conditions.

          7)Requires the California Energy Commission (CEC) to certify  
            electric generation facilities for the construction and  
            operation of thermal powerplants of 50 MW and larger.

          8)Precludes an electrical corporation from constructing a line,  
            plant, or system without having first obtained a permit from  
            PUC that the present or future public convenience and  
            necessity require or will require such construction, a  
            certificate of public convenience and necessity (CPCN).

           FISCAL EFFECT  :   

           1)CEC  :  CEC will require $650,000 annually for two positions and  
            contract funds to expedite the siting of renewable energy  
            generation and transmission.  [Energy Resources Programs  
            Account]

            CEC would also incur annual costs of $600,000 for three  
            positions and contract funds to enforce RPS requirements for  
            POUs. [Energy Resources Programs Account]

           2)PUC  :  PUC states that meeting the 33% by 2020 goal "will  
            require an infrastructure build-out on a scale and timeline  
            perhaps unparalleled anywhere in the world."  In addition to  
            the seven staff current assigned to RPS program, the  
            commission would incur ongoing special fund costs [Public  
            Utilities Reimbursement Account] of $1.7 million for 14  
            additional positions as follows:

             a)   Five additional regulatory analyst positions to design  
               and implement the new RPS policies, manage the renewable  
               energy procurement process, coordinate procurement and  
               transmission planning, and calculate program costs for  
               purposes of applying the cost cap;

             b)   An administrative law judge and an attorney to evaluate  
               utilities' requests for flexible compliance with the  
               increased targets; and,

             c)   Seven additional positions, supplementing five existing  
               staff, associated with permitting an anticipated four to  








                                                                  AB 64
                                                                  Page  4

               six major new transmission projects and within an 18-month  
               deadline following application.

           COMMENTS  :  AB 64 is double-jointed to SB 14 (Simitian) such that  
          for either bill to become effective they both must be approved  
          by the Legislature and approved by the Governor.  The two bills  
          taken together create California's new RPS.  SB 14:

          1)Requires retail sellers of electricity to procure at least 20%  
            of electricity delivered to retail customers from renewable  
            sources by 2013, 25% by 2016, and 33% by 2020. 

          2)Modifies the definition of eligible renewable resources under  
            RPS as follows:

             a)   Requires renewable generators to deliver electrical  
               output into California by either directly interconnecting  
               with transmission lines controlled by a California  
               transmission grid operator or showing that the metered  
               output of a facility that is not directly connected to a  
               California controlled transmission grid matches hourly  
               import schedules to a California transmission grid  
               operator; and, 

             b)   The renewable facility must commence initial operation  
               after January 1, 2010, or the electricity from the facility  
               that commenced operation prior to January 1, 2010, was sold  
               to a retail seller prior to May 31, 2009. 

          3)Eliminates current rules that allow retail sellers to postpone  
            compliance with annual RPS targets for up to three years in  
            the future.  Replaces those rules with provisions that allow  
            the PUC to grant a retail seller the ability to delay  
            compliance for up to two years if PUC makes specific findings  
            that there is insufficient transmission to meet RPS or there  
            were unforeseen delays in permitting or interconnecting  
            projects.  The findings must consider whether the retail  
            seller made all reasonable efforts to construct new  
            transmission and made prudent decisions in procuring  
            resources.  The retail seller must also show that it has made  
            all reasonable efforts to procure distributed generation  
            resources and to procure Renewable Energy Credits (RECs). 

          4)Creates a cap on the potential overall cost of the RPS by:









                                                                  AB 64
                                                                  Page  5

             a)   Requiring PUC to set a Market Price Referent (MPR) to be  
               used to determine above-market costs of renewable  
               electricity.  MPR shall be set based on the value of  
               different generation products within a utility's portfolio  
               and the value of current and anticipated environmental  
               compliance costs; and,

             b)   Providing that an Investor Owned Utility (IOU) does not  
               have to procure additional renewable resources if the total  
               above-market cost of all renewable electricity procured  
               under RPS program or bilateral contracts exceeds 6% of  
               IOUs' total bundled electricity sales. 

          5)Creates a mechanism to allow PUC to approve an IOU application  
            to own its own renewable generation and then recover in rates  
            the cost of that generation plus a reasonable rate of return,  
            if PUC finds the renewable generating facility has a  
            reasonable cost and provides a comparable value to ratepayers  
            as compared to other solicitations for eligible renewable  
            resource. 

          6)Allows retail sellers and POUs to use RECs from resources that  
            do not deliver electricity into California (undelivered RECs)  
            toward their RPS obligations, but caps the total amount of  
            undelivered RECs at 25% of the retail seller's or POU's  
            renewable procurement targets.  Provides that if an IOU or POU  
            builds additional utility owned generation, they can increase  
            the allowance of undelivered RECs to up to 30%.

          7)Provides that retail sellers and POUs can count all  
            undelivered RECs from contracts executed by the retail seller  
            or POU prior to September 18, 2009, even if the total amount  
            of RECs exceeds the limits in 6) above.  However, if they  
            exceed the limits above, the retail sellers and POUs could not  
            count additional undelivered RECs toward their RPS  
            obligations.

          8)Requires POUs to comply with the same RPS mandates as retail  
            sellers and to meet specified public notice and reporting  
            requirements.  


           Background  :  In 2002, the Legislature approved SB 1078 (Sher),  
          Chapter 516, Statutes of 2002, which created RPS.  Under RPS,  
          IOUs and competitive energy service providers (ESPs) of  








                                                                  AB 64
                                                                  Page  6

          electricity were required to increase their renewable  
          procurement each year by at least 1% of total sales, so that 20%  
          of their sales are from renewable energy sources by December 31,  
          2017.  This goal was accelerated to 20% renewable power by 2010  
          by SB 107 (Simitian), Chapter 464, Statutes of 2006.  
               
          PUC reports that for 2007, IOUs have achieved varying levels of  
          progress toward the 20% goal: PG&E = 11.4%; SCE =15.7%; SDG&E =  
          5.2%.  While each IOU added renewable resources in 2007, the  
          percentage of renewables compared to the rest of the portfolio  
          declined from 2006 due to total load growth.  All agencies and  
          stakeholders agree that IOUs will not meet the 2010 deadline.   
          However, PUC reported in October 2008 that IOUs should be in  
          compliance in or around 2013.

          In a recent report providing preliminary results on the  
          feasibility and costs of achieving a 33% RPS by 2020, PUC  
          concluded that such a goal "is highly ambitious, given the  
          magnitude of the infrastructure buildout required."  Under PUC's  
          analysis, the incremental cost of moving from the current to a  
          33% RPS would result in a 7.1% increase in utility costs.  This  
          increase included the costs associated with more expensive  
          generation resources, new transmission, and other resources that  
          will be needed to provide back up generation when renewable  
          electricity is not available.  The estimate assumes the  
          utilities will continue the same balance of renewable  
          technologies, which includes a large reliance on wind and solar  
          energy, and that the direct costs of building new renewable  
          facilities remains unchanged over time, and thus does not  
          account for potential technology-related decreases in costs over  
          time.

           Cost cap  :  SB 14 provides that IOUs will not be required to  
          procure renewable resources that are above the market price of  
          all electricity (MPR) if the total above market cost of all  
          renewable procurement the IOU executed 6% of the IOUs total  
          revenue requirement for the ten year period leading to 2020.   
          This cost cap allows the Legislature to determine how much  
          impact renewable electricity should have on a retail sellers'  
          overall cost structure and then set the cost cap at that level  
          by basing it on a percentage of overall revenue.  According to  
          numbers provided by PUC, the new cost cap should allow for close  
          to $17 billion allowable above market costs for PG&E, SCE, and  
          SCE combined.  This is a roughly 20 times the amount set aside  
          for above-market costs under current law, depending on the  








                                                                  AB 64
                                                                  Page  7

          accounting method.

          The language in the bill gives PUC some flexibility to determine  
          how to calculate the cost of individual contracts that expire  
          after 20%.  The contracts could be calculated against the cost  
          cap on a pro-rata basis such that only the cost of the contract  
          associated with the years prior to 2020 would count against the  
          cap. 

           Location, deliverability, and renewable energy credits  :  To  
          count toward a retail seller's RPS obligation, the renewable  
          facility must meet several requirements including that the  
          facility deliver its electricity to California.  A resource can  
          "deliver" to California if it is either directly interconnected  
          to a California control area or is scheduled into California  
          within the same hour it is produced and from the same location  
          at which it is produced. These definitions ensure that all  
          electricity that is counted toward RPS is actually used to  
          offset the need for non-renewable generation within California. 

          This definition could make it difficult to apply electricity  
          from a solar or wind facility that is located out-of-state to  
          RPS, since many of these resources cannot be scheduled into  
          California at the same time it produced by the resource.  Some  
          of these resources do not schedule their actual output into  
          California and instead use resources from non-renewable  
          facilities to "match" the output.  Even with this inability for  
          some resources located outside of California to meet the  
          delivery requirements there are approximately 22,000 MWs worth  
          of proposed projects today that are located outside of  
          California that will be able to meet the definition of delivery.  


          SB 14 also allows a retail seller or POU to procure RECs to meet  
          a portion of their RPS obligation. The bill caps the total  
          amount of these RECs at 25% of the total RPS obligation and  
          allows utilities to meet up to 30% if the utilities invest in  
          more utility owned generation.  

          A REC represents the renewable attributes of renewable  
          generation.  A REC can remain bundled with the associated  
          energy.  In that case, the utility buys the renewable  
          electricity and uses the RECs to meet its RPS obligation and  
          uses the associated electricity to meet its own load.   RECs can  
          also be traded separate from the underlying electricity  








                                                                  AB 64
                                                                  Page  8

          (tradable RECs or tRECs).  In this case, one retail seller  
          purchases the tREC and applies it toward its RPS obligation and  
          another retail seller purchases the associated electricity to  
          meet its own load.  The second retail seller cannot count that  
          electricity toward its own RPS obligations.

          Some retail sellers and some renewable generators have advocated  
          for broader use of RECs.  They believe that RPS should not limit  
          the use of RECs or put restriction on the geographic location or  
          deliverability of the associated renewable resource. They  
          believe this broad REC market would give retail sellers more  
          procurement options and could reduce the cost of complying with  
          RPS. 

          A number of environmental groups, the Coalition of Utilities  
          Employees, and California Wind Energy Association have all  
          advocated for a very limited allowance for out-of-state RECs.   
          They fear that a wide-open REC market will lead to "paper  
          compliance with RPS" and will not result in the construction of  
          any renewable generation within California. 

           Enforcement and off Ramps  :  SB 14 provides that PUC may grant a  
          retail seller that cannot meet its RPS targets an additional two  
          years to meet compliance targets if PUC finds that there is  
          inadequate transmission capacity to meet RPS or there were  
          unanticipated permitting delays for planned eligible renewable  
          electricity projects.  The retail seller must also show that it  
          made reasonable efforts to procure cost effective distribute  
          generation resources and to procure RECs. 

           Publicly Owned Utilities  :  Current law does not require POUs to  
          meet the same RPS that other electricity providers are required  
          to meet. Rather, current law directs each POU to put in place  
          and enforce its own RPS and allows each publicly owned utility  
          to define the electricity sources that it counts as renewable.   
          No state agency enforces POU compliance or places penalties on a  
          publicly owned utility that fails to meet the renewable energy  
          goals it has set for itself.

          SB 14 requires most POUs to meet the 33% RPS by 2020  
          requirement.  The bill requires each POU to meet the same RPS  
          procurement targets as other retail sellers. The bill allows  
          POUs to comply with the same provisions allowing for up to 30%  
          undelivered RECs to meet their RPS compliance. While the bill  
          allows PUC to adopt rules for REC purchases for retail sellers,  








                                                                  AB 64
                                                                  Page  9

          POUs should be able to comply with the statutory restrictions on  
          REC purchases without PUC involvement. 

          Most of POUs do not object to creating a specific POU RPS  
          mandate.  However, while the largest POU in the state, the Los  
          Angeles Department of Water and Power, supports this bill, most  
          other POU oppose the bill due in large part to their concern  
          that the bill's delivery requirements makes it difficult to  
          procure some resources that had hope to use for RPS compliance. 
           

           Analysis Prepared by  :    Edward Randolph / U. & C. / (916)  
          319-2083 


                                                                FN: 0003195