BILL ANALYSIS                                                                                                                                                                                                    



                                                                  AB 216
                                                                  Page 1

          Date of Hearing:  April 28, 2009

                           ASSEMBLY COMMITTEE ON JUDICIARY
                                  Mike Feuer, Chair
                   AB 216 (Beall) - As Introduced: February 3, 2009
                                           
                               As Proposed to be Amended
                                           
          SUBJECT  :  PUBLIC WORKS CONTRACT DISPUTES: LOCAL AGENCIES

           KEY ISSUE  :  SHOULD ADDITIONAL CONTROLS AND PENALTIES BE PLACED  
          ON THE DISPUTE RESOLUTION PROCESS INVOLVING PUBLIC WORKS  
          PROJECTS BY LOCAL AGENCIES?
           
          FISCAL EFFECT  :  As currently in print this bill is keyed fiscal

                                      SYNOPSIS
          
          This bill, sponsored by the Construction Employers' Association  
          (CEA), would amend the existing dispute resolution process  
          regarding local public works projects.  The sponsor contends  
          that local agencies frequently fail to schedule statutory meet  
          and confer conferences to resolve disputes when requested to do  
          so by contractors.  Because these informal dispute resolution  
          conferences do not take place, the sponsor agues, contractors  
          must resort to costly litigation in order to resolve their  
          disputed claims.  The bill seeks to reform the pre-litigation  
          claims resolution process by making the following significant  
          changes: requests for meet and confer conferences would be  
          required to be completed within 10 days of the request;  
          claimants could compel mediation if any portion of the claim is  
          unresolved after the meet and confer conference; failure of the  
          local agency to schedule the conference in a timely fashion or  
          otherwise meet the time limits would result in the claim being  
          deemed approved in its entirety; in addition, a further penalty  
          would be imposed equal to two percent of the amount due for each  
          month the claim is not paid.  The bill would not apply to claims  
          less than $50,000 or to any claims over $50,000 if the local  
          agency and the contractor have provided by contract for an  
          alternative dispute resolution process.  Opponents, representing  
          a range of public entities, claim that the bill is unnecessary  
          because existing law provides an adequate framework for the  
          resolution of disputes.  The opponents are concerned that the  
          adoption of the bill would be too costly to public entities.   
          Opponents contend that if the bill is passed, public entities  








                                                                  AB 216
                                                                  Page 2

          will revise their standard construction contracts to provide  
          that disputes with contractors shall be resolved through  
          litigation.

           SUMMARY  :  Revises the pre-litigation dispute resolution process  
          regarding local public works projects.  Specifically,  this bill  :  
           

          1)Expands the dispute resolution process to include "change  
            orders," and other relief, makes charter cities and counties  
            subject to the process, and applies the process to claims  
            against contractors by local agencies.

          2)Provides that when a claim for less than $50,000 is submitted  
            by either a contractor or a local agency, the responding party  
            to the claim has 45 days to make a written response to the  
            claim.  If the responding party wishes to make a written  
            request for additional documentation for the claim or any  
            disputed potions of the claim, this request must be made  
            within 30 days of initial submission of the claim.  The  
            request must be for information that the responding party  
            reasonably and in good faith believes is necessary to analyze  
            the claim or any portion thereof.  The responding party has 15  
            days, or the amount of time it took the claimant to respond to  
            the request if greater than 15 days, to provide a written  
            response to the further documented claim.

          3)Provides a similar process when a recipient of a claim for  
            $50,000 or more wishes to make a claim - the responding party  
            has 45 days to make a written response to the claim; if the  
            responding party wishes to make a request for additional  
            documentation, the request must be made within 30 days of  
            submission of the claim and must be a request that the  
            responding party reasonably and in good faith believes  
            supports the claim.  The responding party would then have 15  
            days, or the amount of time it took the claimant to respond to  
            the request if greater than 15 days, to provide a written  
            response to the further documented claim.  The maximum  
            allotted time that the responding party has to respond to a  
            claim is 105 days from the date of first submission of the  
            claim.

          4)Provides that when a claim for $50,000 or more remains  
            unresolved after the request for additional documentation,  
            either party may request a meet and confer conference within 5  








                                                                  AB 216
                                                                  Page 3

            days of the exhaustion of the 105 day time limit for  
            responding to a claim.  The meet and confer conference shall  
            be completed within 10 days of the request for the conference,  
            unless both parties agree to an extension of time.

          5)Provides that if any portion of the claim for $50,000 or more  
            remains unresolved after the meet and confer conference, the  
            claimant may compel mediation.  Once the claimant demands  
            mediation, the parties must mutually agree to a mediator  
            within 30 days.  If they fail to mutually agree, they must use  
            an alternative dispute resolution process to assist them in  
            the selection of a mediator. 

          6)Failure by the local agency, charter city, or charter county  
            to respond to a claim within the time periods set forth in  
            this subdivision shall result in the claim being deemed  
            approved in its entirety, and shall be processed for payment  
            within five days from the expiration of the time period in  
            which the local agency, charter city, or charter county is  
            required to act.  Failure by the contractor to respond to a  
            claim from a local agency within the time periods prescribed  
            in this subdivision shall result in the claim being approved,  
            although the bill specifies no deadlines by which the  
            contractor would be required to take any further steps.  The  
            parties may extend these time periods for response by mutual  
            agreement.

          7)Further provides that failure by the local agency to respond  
            to a claim within the time periods shall also result in a  
            penalty of 2 percent of the total amount due for every month  
            that payment is not made.  No comparable penalty is provided  
            if the contractor fails to meet deadlines.  Moreover, in any  
            action for the collection of funds wrongfully withheld, the  
            prevailing party would be entitled to reasonable attorney's  
            fees and costs.  These sanctions would be separate from, and  
            in addition to, all other remedies either civil, or  
            administrative.

          8)Exempts contractors, local agencies, charter cities, and  
            charter counties that have adopted an alternative dispute  
            resolution process by contract and by local agencies that have  
            opted for private arbitration of disputes as provided by  
            Public Contract Code section 10240. 

          9)Provides that exercising rights under this section supersedes  








                                                                  AB 216
                                                                  Page 4

            any and all notice requirements under Part 3 of Division 3.6  
            of Title 1 of the Government Code.

           EXISTING LAW:  

          1)Exempts claims resulting from a contract between a contractors  
            and a public agency, where the public agency has elected to  
            resolve any of its disputes pursuant to Article 7.1 of the  
            Public Contract Code (establishes a process for resolution of  
            disputes involving state public works by private arbitration.)  
             (Public Contract Code section 20104.) 

          2)Governs public works claims of $375,000 or less filed by  
            contractors against local agencies that are entered into on or  
            after January 1, 1991.  Claims must be for time extensions,  
            money for work done, payment that is not otherwise expressly  
            provided for, or payments that are in dispute.  Public work is  
            defined in Section 3100 and 3105 of the Civil Code, except  
            that it does not include any work or improvement contracted  
            for by the state or the Regents of the University of  
            California.  (Public Contract Code section 20104.)

          3)Provides that when claim for less than $50,000 is submitted,  
            the responding party to the claim has 45 days to make a  
            written response to the claim.  If the responding party wishes  
            to make a written request for additional documentation for the  
            claim or any disputed potions of the claim, this request must  
            be made within 30 days of initial submission of the claim.   
            The responding party has 15 days, or the amount of time it  
            took the claimant to respond to the request if greater than 15  
            days, to provide a written response to the further documented  
            claim.  (Public Contract Code section 20104.2.)

          4)Provides that when a recipient of a claim for more than  
            $50,000 wishes to make a claim, the responding party has 60  
            days to make a written response to the claim.  If the  
            responding party wishes to make a request for additional  
            documentation, the request must be made within 30 days of  
            submission of the claim.  The responding party has 30 days, or  
            the amount of time it took the claimant to respond to the  
            request if greater than 30 days, to provide a written response  
            to the further documented claim.  (Public Contract Code  
            section 20104.2.)

          5)Provides that when a claim or any portion thereof remains  








                                                                  AB 216
                                                                  Page 5

            unresolved after the request for additional documentation, or  
            the local agency fails to respond within the time prescribed,  
            the claimant has 15 days from the date of the receipt of the  
            local agency's response or from the date of the deadline to  
            respond, to provide the local agency with a written demand for  
            a meet and confer conference.  Upon demand, the local agency  
            shall schedule a meet and confer conference within 30 days for  
            settlement of the dispute.  (Public Contract Code section  
            20104.2.)

          6)Provides that following the meet and confer conference, if the  
            claim or any portion thereof remains in dispute, the claimant  
            may file a claim pursuant to Government Code Title 1, Division  
            3.6, Part 3, Chapters 1 and 2.  The statute of limitations  
            under these provisions is tolled from the time that the  
            claimant submits his or her claim until the date that the  
            claim is denied as a result of the meet and confer process.   
            (Public Contract Code section 20104.2.)
           



          COMMENTS  :  The author explains the reason for the bill as  
          follows:

               Many public entities take years to resolve building  
               contractor payment claims, often times long after work has  
               ceased and projects are occupied.  Although in some  
               instances the delayed resolution is the result of a  
               legitimate dispute, it is all too common for public  
               entities to delay resolution in order to try and  
               renegotiate previously agreed to contract terms.  Because  
               there are no lien rights on public projects, building  
               contractors have little recourse other than to take costly  
               legal action or agree to renegotiate terms and take a loss.  
                Failure to resolve legitimate construction claims in a  
               timely manner jeopardizes the financial well being of  
               contractors and subcontractors.  Delaying claims resolution  
               may also increase future project costs for public entities  
               because contractors may factor a public entities' claims  
               resolution history when submitting future bids.  

               To resolve this issue, AB 216 would create a mandatory  
               claims resolution process if a payment claim on a public  
               works project goes unresolved for 30 days.  








                                                                  AB 216
                                                                  Page 6


          The sponsor contends that the current mechanisms governing the  
          resolution of disputes lead to significant delays and costly  
          litigation.  The bill seeks to prevent these costly delays by  
          requiring that requests for additional documentation be  
          reasonable, that the meet and confer conferences be completed  
          within 10 days of the request for the conference, by allowing  
          claimants to compel mediation in the event that the meet and  
          confer conference does not fully resolve the dispute, by deeming  
          claims allowed in their entirety if a party failed to meet a  
          deadline and imposing an additional financial penalty on local  
          agencies equal to 2 % of the amount due each month for failure  
          to respond to a claim.  The bill exempts parties that have  
          adopted a separate alternative dispute resolution process

          As the supporters explain, California Public Contract Code  
          Sections 10261.5 and 20104.50 stipulate that state and local  
          public entities, respectively, shall pay a contractor within 30  
          days of submitting an undisputed claim.  If the public entity  
          fails to pay the claim, the public entity is liable for interest  
          on the claim.  The statutes do not specify what happens if a  
          public entity simply fails to pay a claim, or, how disputed  
          claims shall be resolved - presumably because these statutes are  
          addressed to the pre-litigation dispute resolution process.   
          Thus, under existing law, a local agency's failure to pay a  
          disputed claim results in either litigation or the invocation of  
          an agreed-to alternative dispute resolution process.     

          California Public Contract Code Sections 20104 through 20104.6  
          establishes a claims resolution process for construction claims  
          that are less than $375,000 in value.  However, supporters of  
          this bill state, 20104.2 (d) stipulates that only the local  
          public entity may call for a meet and confer, and does not  
          provide recourse to a contractor if a public entity simply fails  
          or refuses to call for a hearing.  

           Ten Days To Complete The Meet And Confer Conference.   Supporters  
          of the bill claim that existing law provides no recourse to a  
          contractor if a public entity fails to schedule a meet and  
          confer conference.  This informal meeting is a necessary first  
          step to the resolution of a claim and when claimants lack the  
          opportunity to meet and confer, their only other recourse is  
          litigation.  This bill requires that the conference be completed  
          within 10 days of a request.  Failure to do so would result in  
          the claim being deemed accepted in full, and subject to a  








                                                                  AB 216
                                                                  Page 7

          further penalty of 2 percent of the amount of the claim for each  
          month it was unpaid, along with attorney's fees and costs if a  
          lawsuit were filed.
           Mandatory Mediation.   The bill would establish a right to  
          mandatory mediation and set forth guidelines that will govern  
          the mediation process.  After the disputing parties engage in  
          the meet and confer conference, if the claim or part of the  
          claim remains in dispute, the claimant may demand mediation.  A  
          somewhat comparable provision in Civil Code section 929 governs  
          disputes between homeowners and builders; it imposes a maximum  
          of four hours of mandated mediation.  
           
          Penalty For Failure To Adhere To Deadlines.   The bill seeks to  
          ensure that parties face substantial consequences if they choose  
          to ignore strict deadlines for responding to deadlines on  
          claims.  The bill provides that if a party fails to respond to a  
          claim within the prescribed time periods the claim is deemed  
          approved.  In addition, failure by a local agency to meet a  
          deadline would require that the claim be processed for payment  
          five days after the expiration of the time period in which the  
          local agency is required to act and be subject to a further  
          penalty equal to 2% of the amount due for each month the claim  
          was unpaid.  If the contractor were to file suit to recover this  
          mandated claim and penalty, the contractor would also be  
          entitled to attorney's fees, in addition to the normal  
          pre-judgment interest to which all parties are entitled at the  
          rate of 10 percent.  (See Civil Code sections 3287-3289.)   
          Supporters of the bill contend that this provision provides  
          substantial incentives so that claims are not ignored.  

           Reasonableness Standard.   This bill requires that if parties  
          responding to a claim wish to request additional documentation  
          to supplement the claim, this request should be for information  
          that the party reasonably and in good faith believes is  
          necessary to analyze the claim or any portion of the claim.   
          Supporters of the bill claim that local agencies use the request  
          for documentation as a delay tactic.  The reasonableness  
          standard in the bill reflects the supporters' general concern  
          that the current procedure for dispute resolution is lengthy and  
          costly.

           Exemption For Alternative Procedures Established by Contract  .   
          Supporters of the bill argue that the bill is not overly  
          prescriptive because parties can choose to engage in a different  
          dispute resolution process if agreed to by contract.  Supporters  








                                                                  AB 216
                                                                  Page 8

          point to San Jose's dispute resolution process as a model for  
          success.  (San Jose Municipal Code Title 14 - Public Works and  
          Improvements; Chapter 14.06 - Dispute Avoidance and Dispute  
          Resolution Policy).  San Jose's dispute resolution process is  
          part of the city's municipal code.  It provides for a three-step  
          approach to resolving disputes over public works projects: 1)  
          dispute resolution through settlement conference; 2) facilitated  
          dispute resolution by a neutral facilitator; and 3) dispute  
          resolution before a dispute review board.  At no point in the  
          San Jose process is a decision rendered binding.  Costs for  
          dispute resolution are shared by the disputing parties.  The  
          dispute resolution process does not preclude parties from  
          litigating or from agreeing to a different method of dispute  
          resolution.  According to supporters of the bill, the San Jose  
          model illustrates that when parties adopt their own claims  
          resolution procedures, they reduce the need for litigation,  
          complete more projects, and complete these projects in a more  
          budget-friendly and timely manner.  Under current law, local  
          agencies can also choose to have public works contract disputes  
          arbitrated pursuant to Public Contract Code Sec. 20104(a)(2).  
           
          Outstanding Issues.   Under the bill in print, the only allowable  
          method for creating an alternative dispute resolution process is  
          by contract.  The author may wish to consider broadening this  
          provision to include dispute resolution processes established by  
          local ordinance or policy, such as the apparently successful San  
          Jose ordinance.
           
           The bill requires the meet and confer conference to be not only  
          scheduled but completed within 10 days of the day it is  
          requested.  This may prove to be an overly ambitious goal given  
          busy work schedules, or potentially encourage parties to game  
          the deadlines by strategically timing their requests.  Failure  
          to meet this deadline would result in the application of full  
          and substantial penalties under the bill.  Moreover, requiring  
          meet and confer conference to be completed within 10 days may  
          force parties may to engage in a meaningless process simply for  
          the purpose of meeting the deadline, which is unlikely to aid in  
          the resolution of the dispute. 

          The bill also imposes its penalties for each and every failure  
          to meet any time deadline, no matter how trivial or excusable.   
          With respect to penalties, it should be noted that the 2%  
          monetary penalty applies only to local agencies; contractors  
          face no comparable penalty for failure to take any further steps  








                                                                  AB 216
                                                                  Page 9

          that might be required to make good on a claim that is deemed  
          approved by the contractor's failure to respond in a timely  
          fashion.

          Finally, the bill contains no limit on the length of time the  
          parties would be compelled to participate in mediation.  Because  
          mediation is a process that can succeed only if the parties  
          voluntarily come to agreement, the imposition of mandatory  
          mediation can be controversial or inappropriate in some  
          circumstances, although there are corollaries in existing law.   
          In order to avoid the needless expense of time and money by both  
          sides when an unwilling party is involved in an unproductive  
          mediation, the author may wish to consider whether the amount of  
          time required for mediation should be limited to four hours or  
          some other realistic time period, keeping in mind that if the  
          mediation process is working at that juncture the parties can  
          voluntarily extend it.
           
          Author's Proposed Amendments.   In response to concerns about the  
          original form in which the bill was introduced, the author  
          judiciously proposes the following amendments:
           
           On page 2, line 7, insert:  (b) This article shall not apply to  
          any claims resulting from a contract between a contractor and a  
          public agency when the public agency has elected to resolve any  
          disputes pursuant to Article 7.1 (commencing with Section 10240)  
          of Chapter 1 of Part 2. 

          On page 2, line 11, strike "(b)" and insert "(c)"

          On page 3, line 10, strike "one hundred" and insert "fifty"

          On page 3, line 11, strike "($100,000)" and insert "($50,000)"

          On page 4, line 26, strike "one"

          On page 4, line 27, strike "hundred thousand dollars ($100,000)"  
          and insert: "fifty thousand dollars ($50,000)"

          On page 5, strike lines 24 through 28 inclusive

          On page 5, line 29, strike "(6)" and insert "(5)"

          On page 5, line 39, insert: (6) Failure by the local agency,  
          charter city, or charter county to respond to a claim within the  








                                                                  AB 216
                                                                  Page 10

          time periods set forth in this subdivision shall also result in  
          a penalty, payable to the contractor, of 2 percent of the amount  
          due per month for every month that payment is not made.  In any  
          action for the collection of funds wrongfully withheld, the  
                                                                                    prevailing party shall be entitled to reasonable attorney's fees  
          and costs.  The sanctions authorized under this section shall be  
          separate from, and in addition to, all other remedies either  
          civil, or administrative.

           ARGUMENTS IN OPPOSITION  :  The Regional Council of Rural Counties  
          (RCRC), the California Special Districts Association (CSDA), and  
          the California State Association of Counties (CSAC), oppose the  
          bill, even with the proposed amendments.  They state:

               The overwhelming majority of these contracts are executed  
               and fulfilled with little or no disagreements. When  
               disputes between local agencies and contractors arise,  
               these matters are currently handled in a variety of ways.   
               Some public works contracts contain clauses that specify a  
               mediation and/or alternative dispute resolution process.   
               Other contracts are silent on this point, and, as such, the  
               parties may enter superior courts to resolve disputes.   
               However, we would point out that the vast majority of  
               contracts and disputes are handled or resolved without  
               involving the superior courts. 
               Under proposed amendments, AB 216 would impose a 2% penalty  
               upon local agencies that fail to respond to a specified  
               dispute arising from a contractor.  We believe this effort  
               is unnecessary.  It would, in our view, inappropriately  
               place a new financial penalty on local agencies without  
               addressing those contractors who, in our belief, fail to  
               perform up to the standards specified in a contract. 

          Similarly, the Kern, Los Angeles, Los Rios, Rio Hondo, San  
          Jose-Evergreen, and West Kern Community College Districts argue  
          in relevant part:

               Current law already specifies the procedures for resolution  
               of public works claims disputes between contractors and  
               local public agencies for claims between $50,000 and  
               $375,000.  This bill would mandate a mediation process.   
               The legislation would deprive local agencies, including  
               community college districts, and contractors of the  
               flexibility to address major public works disputes in a  
               timely and cost effective manner.  In large, complex claim  








                                                                  AB 216
                                                                  Page 11

               disputes, mediation and arbitration often fail to provide  
               for the promised cost reductions and timely dispute  
               resolution that make the processes desirable alternatives.   
               Requiring that disputed claims be subject to such a process  
               would only increase mandated costs to community college  
               districts and other local public entities at a time when  
               local budgets are already strained.  AB 216 would drive up  
               costs for local community college districts undertaking  
               public works projects to provide classrooms and training  
               facilities for tomorrow's workforce and increase the  
               likelihood that public funds are not being spent in the  
               most efficient and effective manner. 

          The League of California Cities contends that the bill sets up a  
          system that would favor contracts who submit claims to cities,  
          counties and other public agencies.  The League also asserts  
          that the bill creates an "unreasonable deadline for public  
          agencies to respond to claims, and will result in cities having  
          to pay merit-less claims because of the public agency's  
          administrative capacity."

          The American Council of Engineering Companies of California  
          (ACEC CA) argues that the time limits in the bill are confusing  
          and too long to encourage immediate resolution of disputed  
          claims.  The group notes that time is of the essence in the  
          construction world and that any delay can slow a project down  
          and cause significant cost increases.  It also claims that the  
          time limits are unclear and that as a result, the provision that  
          imposes a penalty for failure to respond by the specified time  
          limes "may result in substantial unfairness."

          CSAC Excess Insurance Authority raises concern that the bill  
          would limit the right of public entities to litigate disputes  
          with their contractors in court.  The group also contends that  
          the bill would restrict a public entity's ability to replace  
          underperforming contractors until the ADR process is completed.   
          According to the group, this restriction could delay important  
          projects.
           
          Prior Related Legislation.   According to the sponsor, a similar  
          but not identical measure, SB 1642, was held in Senate  
          Appropriations last year because of cost concerns raised by  
          local public agencies.  Unlike SB 1642, the sponsor states, the  
          current bill does not have a mandatory arbitration provision.  









                                                                  AB 216
                                                                  Page 12

           REGISTERED SUPPORT / OPPOSITION  :   

           Support 
           
          Construction Employers' Association of California (sponsor)
          American Federation of State, County and Municipal Employees,  
          AFL-CIO
          Engineering Contractors' Association
          California Chapter of the American Fence Contractors'  
          Association
          California Fence Contractors' Association
          Flasher/Barricade Association
          Marin Builders' Association

           Opposition 
           
          American Council of Engineering Companies
          CSAS Excess Insurance Authority
          Kern, Los Angeles, Los Rios, Rio Hondo, San Jose-Evergreen, and  
          West Kern Community College Districts
          League of California Cities
          Regional Council of Rural Counties
           
          Analysis Prepared by  :  Kevin G. Baker and Neta Borshansky / JUD.  
          / (916) 319-2334