BILL ANALYSIS                                                                                                                                                                                                    



                                                                  AB 405
                                                                  Page  1

          Date of Hearing:  April 1, 2009

                       ASSEMBLY COMMITTEE ON LOCAL GOVERNMENT
                             Anna Marie Caballero, Chair
                   AB 405 (Caballero) - As Amended:  March 27, 2009
           
          SUBJECT  :  Public contracts: health care districts: design-build.

           SUMMARY  :  Authorizes a health care district, upon approval of  
          its board of directors, to use a design-build procedure when  
          assigning contracts for the construction of a building or  
          improvements directly related to the construction of a hospital  
          or health facility building.  

           EXISTING LAW  : 

          1)Requires local officials, under the Local Agency Public  
            Construction Act, to invite bids for construction projects and  
            then award contracts to the lowest responsible bidder under  
            the traditional design-build project delivery system.

          2)Defines "design-build" as a procurement process in which both  
            the design and construction of a project are procured from a  
            single entity.

          3)Defines "best-value" as a value determined by objective  
            criteria related to price, features, functions, and life cycle  
            costs.

          4)Defines "project" as the construction of a building and  
            improvements directly related to the construction of a  
            building, and specifies that construction of other  
            infrastructure, including, but not limited to, streets and  
            highways, public rail transit, or water resources facilities  
            and infrastructure are not to be considered "projects."

          5)Authorizes counties to use the design-build method for  
            projects costing more than $2.5 million.  

          6)Authorizes cities to use the design-build method for projects  
            costing more than $1 million.

          7)Authorizes the Sonoma Valley Health Care District to use  
            design-build contracting for the construction of buildings and  
            improvements in excess of $2.5 million directly related to a  








                                                                  AB 405
                                                                  Page  2

            hospital or health facility building, which is required to be  
            reviewed and inspected according to the standards of the  
            Alfred E. Alquist Hospital Facilities Seismic Safety Act of  
            1983.

          8)Authorizes the Orange County Sanitation District to use  
            design-build contracting for projects, including, but not  
            limited to, public wastewater facilities, in excess of $6  
            million.

          9)Authorizes the Santa Clara Valley Water District to use  
            design-build contracting for building contracts.

          10)Requires local officials to prepare documents describing the  
            project and its specifications; to prepare a detailed request  
            for proposals that invites competitive bids; to establish a  
            detailed procedure to pre-qualify design-build entities; and  
            to establish the procedures to select the design-build entity.
          11)Requires the legislative body to establish and enforce labor  
            compliance programs.

          12)Requires local officials to collect specified types of  
            information when pre-qualifying design-build entities.

          13)Requires a prospective design-build entity to list its  
            proposed mechanical subcontractors and licenses; report past  
            worker safety violations, contracting problems, contract  
            defaults, license violations, payroll violations, and  
            bankruptcies; and verify this information under oath.

          14)Requires local officials to select the design-build entity by  
            using either a competitive bidding process in which the award  
            goes to the lowest responsible bidder or a best value  
            competition in which local officials set the criteria.

          15)Requires that price, expertise, life cycle costs, skilled  
            labor force availability, and safety records account for at  
            least 10% each of the total weight of consideration of all  
            best value factors.

          16)Requires the local agency to rank the top three responsive  
            bidders; award the contract to the responsible bidder whose  
            proposal county or city officials rank as "the most  
            advantageous;" and identify the second- and third-ranked  
            bidders after it publicly announces the award.








                                                                  AB 405
                                                                  Page  3


          17)Requires that skilled labor force availability be determined  
            by the existence of an agreement with a registered and  
            approved apprenticeship program.

          18)Requires the winning design-build entity to be bonded and  
            carry errors-and-omissions insurance to cover its design and  
            architectural services.

          19)Requires the entity to adhere to the local agency's  
            performance criteria and design standards and obtain the local  
            agency's written consent for any deviations from these  
            standards, and authorizes the local agency to hire a design  
            professional to ensure compliance.

          20)Authorizes the winning design-build entity to use  
            subcontractors not listed in its original bid, but requires  
            the entity to award these subcontracts by following a process  
            set by the local agency, including publishing notices and  
            setting deadlines.

          21)Permits the local agency to retain no more than 5% of the  
            contract if the local agency's bid request required the  
            design-build entity to carry a performance and payment bond.

          22)Requires any local agency that uses design-build contracting  
            to submit a report to the Legislative Analyst's Office (LAO)  
            containing specified information that includes, but is not  
            limited to, a description of the Labor Force Compliance  
            Program and an assessment of the project impact of "skilled  
            labor force availability."

          23)Repeals the authorization for counties, the Orange County  
            Sanitation District, the Santa Clara Valley Water District,  
            and the Sonoma Valley Health Care District to use design-build  
            contracts on January 1, 2011.  

          24)Repeals the authorization for cities to use design-build  
            contracts on January 1, 2016.

           FISCAL EFFECT  :  Unknown

           COMMENTS  :   

          1)The Local Agency Public Construction Act requires local  








                                                                  AB 405
                                                                  Page  4

            officials to invite bids for construction projects and then  
            award contracts to the lowest responsible bidder.  This  
            design-bid-build method is the traditional approach to public  
            works construction.

          2)Private companies often use the design-build method for  
            construction projects.  Under the design-build method, a  
            single contract covers the design and construction of a  
            project with a single company or consortium that acts as both  
            the project designer and builder.  The design-build entity  
            arranges all architectural, engineering, and construction  
            services, and is responsible for delivering the project at a  
            guaranteed price and schedule based upon performance criteria  
            set by the public agency.  The design-build method can be set  
            by the public agency.  The design-build method can be faster,  
            and, therefore, cheaper, than the design-bid-build method, but  
            it requires a higher level of management sophistication since  
            design and construction may occur simultaneously.

          3)Advocates for the design-build method of contracting for  
            public works contend that project schedule savings can be  
            realized because only a single request for proposals is needed  
            to select the project's designer and builder.  The more  
            traditional design-bid-build project approach requires the  
            separate selection of the design consultant or contractor,  
            completion of design, and then advertising for bids and  
            selection of the construction contractor.  Proponents add that  
            design-build allows the overlap of design and construction  
            activities, resulting in additional time savings and lower  
            project costs.  By avoiding the delays and change orders that  
            result from the traditional design-bid-build method of  
            contracting, proponents argue that officials can deliver  
            public works faster and cheaper.

          4)The design-build language in current law is based on a  
            compromise struck in 2000 among local officials, labor groups,  
            and contractors.  Local officials wanted the flexibility and  
            potential cost savings offered by design-build contracts.   
            Labor unions wanted to ensure that counties pre-qualify  
            employers to protect workers' interests.  Contractors wanted  
            to be sure they had fair access to county contracts.  Further  
            changes to the language, consistent with the principles of the  
            2000 compromise were made by SB 287 (Cox), Chapter 376,  
            Statutes of 2005; SB 416 (Ashburn), Chapter 585, Statutes  
            2007, which extended this authority to use design-build  








                                                                  AB 405
                                                                  Page  5

            contracting for the construction of buildings and directly  
            related improvements to all 58 counties in the state; SB 642  
            (Wolk), Chapter 314, Statues 2008, which extended this  
            authority to use design-build contracting for the construction  
            of buildings and directly related improvements to all cities  
            in the state; and SB 1699 (Wiggins), Chapter 415, Statutes  
            2008, which extended this authority to use design-build  
            contracting for the construction of buildings and improvements  
            in excess of $2.5 million directly related to a Sonoma Valley  
            Health Care District hospital or health facility building.

          5)The LAO issued a report to the Legislature on February 3,  
            2005, titled "Design-Build: An Alternative Construction  
            System."  After analyzing the claims of proponents and  
            opponents and reviewing the experience of counties that were  
            authorized to use design-build at the time, LAO recommended  
            "the Legislature grant design-build authority only to  
            buildings and directly related infrastructure.  There are more  
            complex issues associated with other public works projects  
            such as transportation, public transit, and water resources  
            facilities.  Evaluation of design-build as a construction  
            delivery option for these other infrastructure facilities is  
            beyond the scope of this report."

          6)California currently has 75 health care districts.  Health  
            care districts were known as hospital districts prior to 1994.  
             Health care districts are formed to "establish, maintain, and  
            operate health care facilities," including, but not limited  
            to, hospitals.  Health care districts are governed by elected  
            boards of directors.  Health care districts throughout the  
            state need to retrofit existing buildings or build new  
            facilities in order to comply with the state's seismic safety  
            law.  These districts are faced with escalating construction  
            costs and are looking for the most cost-efficient ways to meet  
            seismic standards and provide well-designed and -built  
            state-of-the-art facilities to provide health care to the  
            people of the state.  One of these is design-build  
            contracting.

          7)AB 405 extends the design-build authorization currently  
            granted to the Sonoma Valley Health Care District to all  
            health care districts.  Because this authorization only  
            extends to the construction of buildings and directly related  
            improvements, it does not exceed the scope recommended by the  
            LAO report.  There appears to be no logical policy reason why  








                                                                  AB 405
                                                                  Page  6

            this authorization, which has been thoroughly examined and  
            refined through a long series of compromises, studies, and  
            bills, should not be extended to all health care districts,  
            and there are significant economic reasons for encouraging it.  


           REGISTERED SUPPORT / OPPOSITION  :   

           Support 
           
          Association of CA Healthcare Districts [CO-SPONSOR]
          CA Special Districts Association [CO-SPONSOR]
          CA Hospital Association
          Coalinga Regional Medical Center
          North-Kern South Tulare Hospital District
          North Sonoma County Hospital District

           Opposition 
           
          American Federation of State, County and Municipal Employees  
          (AFSCME) (unless amended)
          Associated Builders and Contractors (ABC) of CA (unless amended)
          Professional Engineers in CA Government
          Service Employees International Union
           
          Analysis Prepared by  :    Jennifer R. Klein / L. GOV. / (916)  
          319-3958