BILL ANALYSIS                                                                                                                                                                                                              1
          1





                SENATE ENERGY, UTILITIES AND COMMUNICATIONS COMMITTEE
                                 ALEX PADILLA, CHAIR
          

          AB 435 -  De La Torre                             Hearing Date:   
          July 7, 2009               A
          As Amended:         June 25, 2009            FISCAL       B
                                                                        
                                                                        4
                                                                        3
                                                                        5

                                      DESCRIPTION
           
           Current law  requires the California Public Utilities Commission  
          (CPUC) to certify the public convenience and necessity of a  
          transmission line before an investor-owned utility (IOU) may  
          begin construction (Certificate of Public Convenience and  
          Necessity, or CPCN).  The CPCN process includes environmental  
          review of the proposed project under the California  
          Environmental Quality Act (CEQA).  The CPCN confers eminent  
          domain authority for construction of the project.

           This bill  directs the CPUC to study the efficacy of conducting  
          concurrent federal and state environmental reviews of proposed  
          transmission lines.

           This bill  requires the CPUC to approve transmission projects  
          which it determines are reasonable and necessary for grid  
          reliability or efficiency or to facilitate the requirements of  
          the Renewable Portfolio Standard (RPS).

           This bill  requires the CPUC to report annually to the  
          Legislature on the status of all pending transmission  
          applications and actions taken to streamline siting and  
          permitting.

           This bill  requires the CPUC streamline its transmission  
          permitting and siting process and expedite review of all lines.

           Current law  requires the CPUC to provide backstop cost recovery  
          in rates for the costs of transmission facilities that are not  
          approved for rate recovery by the Federal Energy Regulatory  
          Commission (FERC) but the CPUC finds were prudently incurred.












           This bill  requires the CPUC to provide backstop cost recovery in  
          rates for the costs of transmission facilities that are not  
          approved for rate recovery by FERC but the CPUC finds were  
          prudently incurred.

           Current law  requires the Independent System Operator (ISO) to  
          ensure efficient use and reliable operation of the transmission  
          grid and to adopt inspection, maintenance, repair, and  
          replacement standards for transmission facilities under its  
          control.

           This bill  requires the ISO to plan and provide for transmission  
          capacity sufficient to provide reliable service to its control  
          area and achieve its procurement requirements under the  
          Renewable Portfolio Standard (RPS).  The ISO would be required  
          to submit an annual plan to the CPUC and CEC on the transmission  
          needs in its control area for the subsequent ten years.

           Current law  requires the California Energy Commission (CEC) to  
          adopt a strategic plan for the state's electric transmission  
          grid recommending actions required to implement investments  
          needed to ensure reliability, relieve congestion and meet future  
          growth in load and generation.

           This bill  requires each investor-owned utility (IOU) to plan and  
          provide for transmission capacity sufficient to provide reliable  
          service to its customers and achieve its procurement  
          requirements under the RPS.  Each IOU would also be required to  
          submit an annual plan to the CPUC, in consultation with the ISO,  
          on its transmission needs for the subsequent ten years.

           This bill  requires all local publicly owned electric utilities  
          (POUs) to plan and provide reliable transmission service to its  
          customers.

           This bill  requires IOUs and POUs to investigate and evaluate the  
          cost and feasibility of using high-technology conductors on its  
          current and future transmission facilities and to report the  
          result to the CEC by July 1, 2011.

                                      BACKGROUND
           
           California Independent System Operator  - About 75% of the  










          state's transmission grid is owned by the IOUs.  The ISO, a  
          not-for-profit public benefit corporation, is charged with  
          operating the IOU's transmission grid and managing the flow of  
          electricity.  (The ISO also operates municipal utility's  
          transmission lines that have requested that service.)  The ISO  
          plans for and recommends transmission projects within its  
          control area by soliciting information from the transmission  
          owners.  The ISO works with a variety of stakeholders and  
          performs engineering and economic studies on proposed projects  
          to determine the potential benefits.  An annual transmission  
          plan is produced which forecasts the projects necessary to  
          maintain the grid for ten years and beyond.

          The responsibility for actually building the transmission lines  
          generally lies with the transmission-owning utilities.  Most of  
          these utilities need to obtain approval from the CPUC before  
          they can construct new transmission lines.  The CPUC conducts a  
          public hearing process and issues a CPCN if it deems the project  
          is warranted.  The utilities must then initiate a filing at the  
          FERC to request cost-recovery for both inter- and intra-state  
          transmission lines.

          A significant share of the state's transmission grid is owned by  
          municipal utilities and outside the jurisdiction of the ISO or  
          the CPUC.  Similar to IOUs, municipal utilities possess eminent  
          domain authority to acquire rights-of-way for transmission lines  
          but need no approvals from any state agencies to build new  
          transmission.

           The RETI  - A critical element of increasing the electricity  
          deliveries from renewable resources is the development of new  
          transmission to remote areas of the state rich with wind, sun  
          and geothermal renewable fuels.  In response to this need the  
          Renewable Energy Transmission Initiative (RETI) was launched  
          which is a statewide initiative to help identify the  
          transmission projects needed to accommodate these renewable  
          energy goals, support future energy policy, and facilitate  
          transmission corridor designation and transmission and  
          generation siting and permitting. RETI is intended to be an open  
          and transparent collaborative process in which all interested  
          parties are encouraged to participate. 

          RETI has assessed all competitive renewable energy zones in  
          California and some in neighboring states that can provide  










          significant electricity to California consumers by the year  
          2020. RETI has also identified those zones that can be developed  
          in the most cost effective and environmentally benign manner and  
          will prepare detailed transmission plans for those zones  
          identified for development. 

          The RETI effort is supervised by a coordinating committee  
          comprised of California entities responsible for ensuring the  
          implementation of the state's renewable energy policies and  
          development of electric infrastructure, namely: 

                 California Public Utilities Commission
                 California Energy Commission
                 California Independent System Operator
                 Publicly-Owned Utilities (SCPPA, SMUD, and NCPA) 

           Transmission Progress  - The CPUC's October 2008 RPS status  
          report indicates that two new transmission lines are necessary  
          to meet the 20 percent goal.  Three new transmission lines have  
          been approved for California or are nearing approval -  
          Tehachapi, Sunrise, Devers-Palo Verde 2.  An additional five  
          lines would be needed to achieve 33 percent by 2020.

                                       COMMENTS
           
              1.   Concurrent Environmental Reviews  - It is very difficult  
               to site a transmission line of any distance without  
               impacting federal lands.  Consequently environmental  
               reviews under the California Environmental Quality Act  
               (CEQA) and National Environmental Policy Act (NEPA) must  
               occur.  Under current practice the CPUC is the lead agency  
               for the environmental impact studies required under these  
               two laws.  When a transmission developer files an  
               application for a CPCN, the CPUC, in consultation with the  
               appropriate federal agencies conducts a joint environmental  
               review which results in the release of one document which  
               satisfies both state and federal law.  This bill requires  
               the CPUC to study the efficacy of doing a concurrent  
               environmental review which it already does.   The author and  
               committee may wish to consider  striking this provision.

              2.   Transmission Planning & Reporting  - The bill requires  
               the ISO, CPUC, and IOUs to do specified reviews of the  
               transmission facilities necessary to provide reliable  










               service to California ratepayers and meet the state's RPS  
               requirements and then produce specified reports.  This  
               planning is already done by the parties.  The need for  
               additional studies and reports is not apparent and may be  
               duplicative.  

               The ISO is required under Order 890 of the FERC to conduct  
               and release an annual transmission plan.  This process  
               involves all IOUs and some POUs which participate in the  
               ISO.  The process was mandated by FERC due to concerns that  
               a lack of coordination, openness and transparency could  
               result in opportunities to exercise undue discrimination in  
               transmission planning. The order directed the ISO to  
               develop and propose a coordinated process that complied  
               with nine planning principles, which the ISO filed with the  
               commission in December 2007.  The ISO submitted its  
               Transmission Planning Process Business Practice Manual and  
               associated tariff changes on October 31, 2008.  The result  
               is an annual transmission plan the most recent of which is  
               more than 300 pages long.  The plan is widely distributed  
               and available on the ISO's website<1> and covers a minimum  
               of ten years but can include a study horizon of as much as  
               25 years.

                The author and committee may wish to consider  striking  
               provisions which require the ISO, IOUs, and CPUC to plan  
               and report on transmission since these activities are  
               already accomplished and additional reporting requirements  
               appear to be duplicative of current activities.

              3.   Cost Recovery  - This bill requires the CPUC to allow for  
               rate recovery for increased transmission costs which are  
               not approved by FERC but the CPUC finds were prudently  
               incurred.  This provision is duplicative of existing law at  
               Public Utilities Code Section 319.2.5.   The author and  
               committee may wish to consider  striking this provision to  
               prevent redundancy and ensure clarity of current law.

              4.   Transmission Streamlining  - CPUC Commissioner Dian  
               Grueneich recently testified before this committee and  
               reported that the CPUC has 11 transmission-related  
             --------------------------
          <1> See 2009 California ISO Transmission Plan at  
          http://www.caiso.com/2354/2354f34634870.pdf.
           









               applications pending and anticipates the number to double  
               by the end of the year.

               The Commissioner additionally reported that in 2006 the  
               CPUC completed a top to bottom review of its permitting  
               process which has resulted in a well-managed and staffed  
               branch that is prepared to handle a rapidly increasing  
               workload.  The CPUC is a full participant in the RETI,  
               meets quarterly with IOU representatives to discuss further  
               streamlining and transmission progress, and earlier this  
               year established regular multi-agency meetings with federal  
               and state agencies involved in transmission line  
               permitting.

               While much has been made of the complexity and length of  
               the process of planning, permitting, and constructing  
               transmission lines, there are few concrete ideas for  
               simplifying or abbreviating that process without  
               compromising environmental review and public participation  
               standards.  Typically, transmission projects have extensive  
               land use, environmental, and economic implications which  
               necessarily take a long time to sort out.    The author and  
               the committee may wish to consider  what the CPUC may do in  
               response to this bill's direction to streamline the review  
               process and be cautious about directing the CPUC to  
               streamline its process without knowing what measures the  
               CPUC might take.

              5.   Transmission Conductors  - This bill also requires the  
               IOUs and POUs to investigate and evaluate the cost and  
               feasibility of using high-technology conductors on its  
               current and future transmission facilities and to report  
               the result to the CEC by July 1, 2011.  No background  
               information was provided and the specific term  
               "high-technology conductors" is not readily discernible.   
               Staff assumes that this term is meant to encompass new  
               technologies that can expand the capacity of existing  
               transmission lines and reduce line-losses.  Legislation has  
               been adopted by this committee to ensure that policies are  
               studied and developed for the IOUs to develop a smarter  
               electric grid for the state.  The CPUC has also initiated a  
               rulemaking to consider the elements of a smart grid, the  
               heart of which would encompass improved transmission  
               technologies.  The proceeding will consider setting  










               policies, standards and protocols to guide the development  
               of a smart grid system and facilitate integration of new  
               technologies such as distributed generation, storage,  
               demand-side technologies, and electric vehicles.   A  
               separate study of "high-technology conductors" may be  
               duplicative of the CPUC's rulemaking as well as research  
               being conducted by the CEC on the elements of a smart grid.  
                 The author and committee may wish to consider  striking  
               this provision to avoid duplication of studies by the  
               regulatory agencies.

              6.   Related Legislation  .  The following bills also affect  
               transmission siting:

                  a)        SB 14 (Simitian) - Increases RPS goals to 33  
                    percent and makes minor changes to the transmission  
                    planning and approval process.  Status: Set in  
                    Assembly Utilities and Communications Committee July  
                    6th.
                  b)        SB 460 (Wolk) - Requires POUs to participate  
                    in the ISO transmission planning process and gives the  
                    CEC permitting authority over POU high-voltage  
                    transmission lines.  Status:  Senate Appropriations  
                    Suspense File.
                  c)        AB 64 (Krekorian) - Increases RPS goals to 33  
                    percent and creates the Energy Planning Investment  
                    Committee charged with specified transmission  
                    planning.  Status: Set for hearing in this committee  
                    July 7th.
                  d)        Governor's Re-Organization (AB 33xxx,  
                    Villines) - Transfers transmission siting authority  
                    from the CPUC to the CEC.  Status:  Referred to  
                    Assembly Utilities and Communications Committee.

                                    ASSEMBLY VOTES
           
          Assembly Floor                     (77-0)*
          Assembly Appropriations Committee  (17-0)*
          Assembly Utilities and Commerce Committee                       
          (15-0)*
          *Votes on prior version of the bill

                                       POSITIONS
           










           Sponsor:
           
          Author

           Support:

           None on file

           Oppose:
           
          None on file

          
          Kellie Smith 
          AB 435 Analysis
          Hearing Date:  July 7, 2009