BILL ANALYSIS                                                                                                                                                                                                    






           
          SENATE TRANSPORTATION & HOUSING COMMITTEE       BILL NO: AB 732
          SENATOR ALAN LOWENTHAL, CHAIRMAN               AUTHOR:  Jeffries
                                                         VERSION: 2/26/09
          Analysis by:  Jennifer Gress                   FISCAL:  yes
          Hearing date:  June 9, 2009







          SUBJECT:

          Design-sequencing

          DESCRIPTION:

          This bill extends the sunset date, from January 1, 2010 to  
          January 1, 2012, on the authority to allow the California  
          Department of Transportation (Caltrans) to use the  
          design-sequencing method of procurement for transportation  
          projects.

          BACKGROUND AND ANALYSIS:

          Design-sequencing is a method of contracting that enables the  
          sequencing of design activities to permit each construction  
          phase to commence when design for that phase is complete,  
          instead of requiring design for the entire project to be  
          completed before commencing construction, as is the case with  
          the traditional design-bid-build method of contracting.   
          Design-sequencing is different from design-build, the latter of  
          which entails the contracting of both the design and  
          construction to a single entity.  With design-sequencing, the  
          transportation agency, in this case Caltrans, retains  
          responsibility for design but is able to award a construction  
          contract prior to completing the design for the entire project.   
          Under current law, a transportation agency may award a  
          construction contract when the design is at least 30 percent  
          complete. 

          AB 405 (Knox), Chapter 378, Statutes of 1999, established the  
          Design-Sequencing Demonstration and Evaluation Program, which  
          authorized Caltrans to use design-sequencing for no more than  




          AB 732 (JEFFRIES)                                         Page 2

                                                                       


          six transportation projects.  One year later, AB 2607 (Knox),  
          Chapter 340, Statutes of 2000, was enacted to increase the  
          number of projects to 12.  This demonstration program was  
          repealed on January 1, 2005.  

          In 2004, SB 1210 (Torlakson), Chapter 795, established Phase 2  
          of the demonstration program, authorizing 12 more projects.   
          This authority is set to expire on January 1, 2010.

           This bill  extends by two years, from January 1, 2010 to January  
          1, 2012, the sunset date on Phase 2 of the Design-Sequencing  
          Demonstration and Evaluation Program. 
          


          COMMENTS:

           1.Purpose  .  To date, Caltrans, the sponsor of this measure, has  
            awarded design-sequencing contracts for only 6 of the 12  
            projects permitted under Phase 2 of the demonstration program.  
             Caltrans is seeking to extend the sunset date by two years in  
            order to enable it to award contracts on the remaining six  
            projects allowed under existing law.  Because Caltrans can  
            award a contract earlier with design-sequencing than with the  
            traditional design-bid-build method of procurement, it  
            believes that, when used appropriately, design-sequencing can  
            be a valuable tool to accelerate project delivery.

            Caltrans argues that it learned a great deal about both the  
            benefits and limitations of design-sequencing during the first  
            phase of the demonstration program.  It has not used all 12  
            slots available under current law because, based on the  
            results of Phase 1, Caltrans has refined and made more  
            selective the process by which it chooses projects for this  
            method of contracting.  Two projects identified by Caltrans as  
            strong candidates for design-sequencing are scheduled to award  
            contracts near the end of the year, just as the existing  
            authority expires.  Caltrans is concerned that if the award  
            dates were to shift by only a few weeks, it would be forced to  
            convert the projects to traditional design-bid-build, which  
            Caltrans argues would cost significant time and money.   
            Extending the authority by two years would ensure that these  
            two projects could move forward without delay and allow  
            Caltrans to utilize the remaining four slots available under  
            existing law.





          AB 732 (JEFFRIES)                                         Page 3

                                                                       


           2.Phase 1 Interim Report  .  Existing law requires Caltrans to  
            establish a peer review committee once projects under Phase 1  
            have been completed in order to evaluate the advantages and  
            disadvantages of design-sequencing.  Caltrans established this  
            committee prior in advance of project completion so that it  
            could better evaluate the program and make adjustments as  
            necessary.  It released an interim report in March 2008.

            Under Phase 1, Caltrans awarded design-sequencing contracts  
            for 10 of the available 12 slots.  The interim report included  
            6 of those 10 projects and represented 12 percent of the total  
            value of design-sequencing contracts awarded under Phase 1.

            The evaluation examined 14 criteria in 4 performance areas  
            including schedule, cost, contract administration, and  
            stakeholder satisfaction.  Caltrans compared the results of  
            these factors for the six design-sequencing projects to nine  
            "shadow projects," which Caltrans had identified as similar  
            types of projects.  What follows is a brief summary of some of  
            the major findings regarding cost and schedule.

            Capital cost:  Comparing the bid amount to the final  
            construction cost, Caltrans found that the cost for  
            design-sequencing projects increased by 30 percent on average  
            per project, compared to an average increase of 12 percent for  
            the shadow projects.

            Support cost:  The total support costs for design-sequencing  
            projects is 46 percent of their construction allotment  
            compared to 32 percent for the shadow projects.

            Change orders:  On average, the design-sequencing projects  
            generated 50 contract changes per project compared to 49 for  
            the shadow projects.  

            Impact of change orders on cost growth:  The change orders  
            increased the construction capital cost an average of 37  
            percent for design-sequencing projects and 12 percent for the  
            shadow projects.
          
            Time savings:  Time savings for each of the design-sequencing  
            projects was measured by calculating the difference between  
            the estimated contract acceptance date had the project been  
            built using design-bid-build and the actual design-sequencing  
            contract acceptance date.  The time savings on the six  
            design-sequencing projects ranged from 2 to 18 months, with an  




          AB 732 (JEFFRIES)                                         Page 4

                                                                       


            average time savings of 4 months.   

            Caltrans acknowledges that results from the evaluation are  
            mixed.  It notes, however, that design-sequencing is a new  
            contracting method and that Caltrans is the first agency in  
            the United States to use it.  Neither Caltrans nor the  
            construction community understood initially what types of  
            projects would be most appropriate for this contracting method  
            or how best to implement it.  Caltrans further argues that the  
            lessons learned from these Phase 1 projects has helped it to  
            refine its selection process and improve its procedures, and  
            it has implemented numerous changes that it believes will  
            yield more positive results in Phase 2.  Furthermore, Caltrans  
            believes that more needs to be learned in order to develop the  
            appropriate procedures, engineering mindset, and agency  
            culture to effectively implement this approach.  Extension of  
            the sunset date and the authority to utilize the remaining six  
            slots would enable Caltrans to continue improving this  
            contracting method.
          
           3.Interim report may underestimate problems  .  The interim report  
            did not include four projects, including the three largest of  
            all Phase 1 projects, either because construction had not been  
            completed on the project or because the contractor had claims  
            against Caltrans for cost increases.  Since the report was  
            released, all four projects have been completed and all four  
            involved claims.  One project not included in the report was a  
            very controversial project involving the realignment and  
            widening of I-215, SR 60, and SR 91 at the point where they  
            come together in Riverside County.  The project was  
            substantially delayed, experienced significant cost over-runs,  
            and generated substantial discontent in the region.  For this  
            reason, the final results from all Phase 1 projects may  
            indicate that design-sequencing was more problematic than was  
            presented here.
          
           4.Alternatives to extending the sunset date  .  Extending the  
            sunset date effectively expands the authority to use  
            design-sequencing.  The questions before the committee concern  
            whether it is prudent to expand the authority at this time,  
            and if so, what is the most appropriate way to do so.    
            Design-sequencing is a new contracting method and results from  
            the Phase 1 projects have been mixed.  As an alternative to  
            simply extending the sunset date, the committee may wish to  
            consider allowing Caltrans to move forward with the two  
            projects it has identified as good candidates for  




          AB 732 (JEFFRIES)                                         Page 5

                                                                       


            design-sequencing by extending the sunset date by six months  
            while also limiting the number of projects from 12 to 8.  Once  
            Caltrans completes its final evaluations of Phase 1 and Phase  
            2 projects, both Caltrans and the Legislature may re-evaluate  
            whether to expand authority for the contracting method. 
          
          Assembly Votes:
               Floor:    78-0
               Appr: 16-0
               Trans:    10-0

          POSITIONS:  (Communicated to the Committee before noon on  
          Wednesday, 
                     June 3, 2009)

               SUPPORT:  Caltrans (sponsor)
                         Automobile Club of Southern California
                         California Association of Councils of Governments
          
               OPPOSED:  None received.