BILL ANALYSIS                                                                                                                                                                                                    




                   Senate Appropriations Committee Fiscal Summary
                           Senator Christine Kehoe, Chair

                                           732 (Jeffries)
          
          Hearing Date:  08/27/2009           Amended: 06/16/2009
          Consultant: Mark McKenzie       Policy Vote: T&H 11-0
          _________________________________________________________________ 
          ____
          BILL SUMMARY:  AB 732 would extend the sunset date for a pilot  
          project that allows the Department of Transportation (Caltrans)  
          to use the design-sequencing method of procurement for  
          transportation projects to July 1, 2010, and would limit the  
          total number of projects for which design-sequencing may be used  
          from 12 to 9.
          _________________________________________________________________ 
          ____
                            Fiscal Impact (in thousands)

           Major Provisions         2009-10      2010-11       2011-12     Fund
           Project delivery impactunknown costs related to using  
          design-Special*
                                 sequencing rather than design-bid-build,
                                 potentially offset by savings from  
          accelerated 
                                 schedule (see staff comments)

          Rebidding of projects  potential avoided costs related to  
          rebidding              Special*
                                 projects that may not be awarded before
                                 current sunset date (see staff comments)
          ____________
          *State Highway Account
          _________________________________________________________________ 
          ____

          STAFF COMMENTS:  SUSPENSE FILE.
          
          The vast majority of Caltrans-administered projects are  
          implemented using the traditional design-bid-build approach,  
          whereby complete plans and specifications are prepared prior to  
          the advertising, bidding, and awarding of any construction  
          contracts.  Design-sequencing enables the staging of design  
          activities to permit each construction phase to commence when  
          design for that phase is complete, instead of requiring the  
          entire project design to be complete before construction starts.  










           The contract for the entire project is awarded to one  
          contractor with a minimum of 30 percent complete plans.  The  
          remainder of the design is delivered to the contractor by  
          predetermined dates after start of construction.   
          Design-sequencing is intended to provide an opportunity for  
          efficiencies by allowing collaboration between the contractor  
          and designers to improve and expedite project delivery.

          Current law has authorized Caltrans to undertake a two-phase  
          design-sequencing pilot program.  Phase I of the program  
          authorized 12 projects, but ultimately included 10 projects, and  
          SB 1210 (Torlakson), Chapter 795 of 2004, established Phase II  
          of the pilot program, authorizing 12 additional projects until  
          January 1, 2010.  To date only six contracts have been award  
          under the Phase II pilot program.  Caltrans indicates that two  
          more projects are scheduled to be awarded by the end of the  
          year.  If the contract award dates are delayed even a few weeks,  
          however, Caltrans would be required to convert the projects to  
          traditional design-bid-build.
          Page 2
          AB 732 (Jeffries)

          AB 732 would extend the sunset of phase II of the  
          design-sequencing program from January 1, 2010 to July 1, 2010  
          and reduce the total number of authorized projects from 12 to  
          nine to allow Caltrans to use this procurement method for  
          several more projects.

          Based on Caltrans' March 2008 interim report on the pilot  
          program, results thus far have been mixed in terms of the impact  
          on project schedules, construction and support cost, and change  
          orders.  The interim report only analyzes 12 percent of the  
          total estimated contract costs of the Phase I pilot program.   
          While this amount of data is insufficient to fully assess the  
          success of the pilot program, the report includes the following  
          findings, based on the sample of projects analyzed compared to  
          shadow projects delivered using design-bid-build:
           The impact on completion times ranged from 2 months delay to  
            18 months saved with an average time savings of 4 months.
           Support cost is about 13% greater on design-sequencing  
            projects.
           Design-Sequencing has not resulted in an increase in capital  
            construction costs when compared to traditional delivery  
            methods.
           Design-sequencing projects produced an average of 50  
            change-orders per project, at an average cost of $88,654 each,  










            compared to 49 change-orders, at an average cost of $34,203  
            each, for the shadow projects.  Total change-order costs were  
            $4.4 million per project (30 percent average cost escalation)  
            for design-sequencing, and $1.7 million (12 percent average  
            cost escalation) for a shadow project.
           The low bid on design-sequencing projects is on average 19%  
            lower that the Engineer's Estimate compared to 11% lower for  
            the shadow projects.

          Staff notes that some of the larger and more complicated  
          projects that were not evaluated in this report experienced  
          significant delays, cost over-runs, and have outstanding  
          contractor claims.  Therefore, the data in the report is  
          insufficient to determine whether design-sequencing is  
          ultimately more economical as a delivery method than  
          design-bid-build.  Caltrans acknowledges the mixed results of  
          the pilot program to date, including cost escalations, but  
          indicates that the time savings alone can result in cost savings  
          as a result of construction cost escalation avoidance.   
          Furthermore, Caltrans argues that the lessons learned from Phase  
          I have resulted in the adoption of procedures to assess which  
          projects are best suited for design-sequencing, and the  
          implementation of numerous changes that will yield more positive  
          results in Phase II.  This bill would allow the following  
          projects to be evaluated as part of Phase II of the pilot  
          program:  (1) realignment and expansion of SR 76 in San Diego  
          County; (2) rehabilitation of approximately 11 miles of SR 101  
          in San Luis Obispo County; and (3) interchange improvements at  
          I-805 connection to new roadway on SR 905 near the Otay Mesa  
          Port of Entry in San Diego County.

          Two of these projects may be awarded by the end of this year,  
          just as the existing authority to use design-sequencing expires.  
           By extending the sunset for six months, this bill would ensure  
          that Caltrans can use design-sequencing on these projects,  
          resulting in potential cost avoidance related to re-packaging  
          these projects for bid using the design-bid-build procurement  
          method.