BILL ANALYSIS                                                                                                                                                                                                    



                                                                  AB 1333
                                                                  Page  1

          Date of Hearing:   April 27, 2009

                    ASSEMBLY COMMITTEE ON UTILITIES AND COMMERCE
                                Felipe Fuentes, Chair
                    AB 1333 (Hagman) - As Amended:  April 14, 2009
           
          SUBJECT  :   Electrical transmission lines.

           SUMMARY  :   Prohibits an electrical corporation from  
          reconstructing an electrical transmission line that runs through  
          a residential community unless it undertakes several  
          requirements, such as compensating residential landowners near  
          the transmission line for any reduction in property values.  

           EXISTING LAW  :   

          1)Requires the California Energy Commission (CEC) to designate  
            transmission corridor zones.

          2)Prohibits an electrical corporation from constructing a  
            transmission line without having first obtained from the  
            California Public Utilities Commission (PUC) a certificate  
            that the present or future public convenience and necessity  
            requires the construction. 

           THIS BILL  :

          1)Prohibits an electrical corporation from reconstructing an  
            electrical transmission line that runs through a residential  
            community so that the towers are increased in height by more  
            than 33 % of the height of the existing towers, unless all of  
            the following:

             a)   There is no reasonable alternative.

             b)   The electrical corporation has undertaken and will  
               continue to undertake all reasonable means to eliminate or  
               mitigate risks to the public safety.

             c)   The electrical corporation has agreed to provide just  
               compensation to all residential landowners near the  
               transmission line to compensate them for any reduction in  
               the value of their property resulting from the  
               reconstruction. 









                                                                  AB 1333
                                                                  Page  2

           FISCAL EFFECT  :   Unknown.

           COMMENTS  :   

          1)   Background:   Current law creates a renewables portfolio  
          standard (RPS) that requires utilities to procure at least 20%  
          of their electricity generation from renewable energy  
          generators.  Two bills are gaining momentum through the  
          legislative process that will increase the RPS to 33% by 2020  
          (AB 64, Krekorian, and SB 14, Simitian).

          Thirty-three percent of the combined utilities' portfolios  
          equates to about 28,000 megawatts (MW).  This goal can't be  
          attained by roof-top solar alone, which requires about 13-20  
          homes to generate just 1 MW.  (Most rooftop solar is close to  
          50-75 kW, where 1,000 kW equals 1 MW.)  As such, the utilities  
          are reaching to remote areas of the state that possess ample  
          wind, solar, and geothermal potential to contribute to the  
          majority of its RPS.

          The utilities and policy makers have identified the Tehachapi  
          Mountains as possessing some of the most wind-rich areas in the  
          state.  To access that wind, developers have proposed the  
          Tehachapi Renewable Transmission Project; a 500-kilovolt (kV)  
          transmission line that would allow access to 4,500 MW of wind  
          generation planned for the Tehachapi Mountains.  The  
          transmission line is also expected to help relieve a  
          transmission bottleneck between Northern and Southern  
          California.  

          The Tehachapi project would include new and upgraded electric  
          transmission lines and substations between eastern Kern County  
          and the city of Ontario in San Bernardino County.  The project  
          will interconnect renewable wind power generated in the  
          Tehachapi area to the existing electric transmission system to  
          meet the increasing demand of electricity in Southern  
          California.  

          The Tehachapi transmission line will use existing rights of way  
          when it can.  One existing right of way runs through the City of  
          Chino Hills. This existing right-of-way includes about 3 miles  
          of inactive 220 kV transmission lines on 98-foot towers, and  
          have been largely inactive for the past 30 years. According to  
          information provided by Chino Hills, the 3-mile portion of the  
          current line is located within 500 feet of more than 1,000  








                                                                  AB 1333
                                                                  Page  3

          homes, directly affecting approximately 3,500 people in Chino  
          Hills.  The increased line would use the same right-of-way.  

          2)   Why a high-voltage line  :  The California Independent System  
          Operator (CAISO, operates about 75% of the state's transmission  
          grid) and the PUC have determined that a high-voltage  
          transmission line is necessary to access the renewable  
          generation in the Tehachapi region.  As such, the existing 220  
          kV lines will need to be upgraded to 500 kV lines to accommodate  
          the generation.  

          High-voltage lines are like the interstate highways we use to  
          travel long distances more efficiently.  They carry large  
          amounts of power from generators that may be sited far away to  
          load centers where the power is consumed.  It is more efficient  
          to move electricity over long distances at high voltage because  
          of minimal "line loss."  Using low voltage lines to carry  
          electricity over long distances is inefficient and expensive and  
          ratepayers end up paying for electricity it never receives.  At  
          every system component through which the power flows, electrical  
          resistance occurs which creates power losses. Generally, power  
          losses increase proportionally with the current, for example,  
          twice the current produces four times the electricity losses. As  
          such, losses can be significant when energy is transmitted over  
          lengthy lower-voltage transmission lines.

          The high-voltage transmission grid includes the power lines, the  
          towers that hold them up and the switches, transformers, and  
          other equipment in substations where the power lines come  
          together.  At those substations, the power can be "stepped down"  
          to lower voltage for deliver over the local distribution system  
          that connects to homes and businesses.  

          3)   The approval process:   The CAISO develops the statewide  
          transmission plan with input from the investor-owned utilities.   
          The PUC is the primary agency that assesses transmission  
          proposals made by the utilities for their environmental impact  
          and routing.  The PUC conducts lengthy environmental review  
          processes that allow for extensive public input.  Other public  
          agencies may also be involved if the proposed route crosses  
          publicly owned land.   

          4)   The alternative-a State Park  :  The city of Chino Hills has  
          proposed an alternative route through the Chino Hills State  
          Park.  The city states that a number of active transmission  








                                                                  AB 1333
                                                                  Page  4

          lines already traverse Chino Hills State Park and this new line  
          would be consistent.  They propose to remove the inactive 220 kV  
          lines from the park, the neighborhoods, and the environmentally  
          sensitive Water Canyon Natural Preserve.  They also propose  
          relocating many of the existing 500 kV transmission lines away  
          from ridgelines and other prominent areas to protect and improve  
          the view shed within the park.  Recently, San Diego Gas and  
          Electric company proposed a high-voltage transmission project  
          through Anzo Borrego State Park to access remote renewable  
          energy generation resources.  Due to significant opposition, the  
          PUC re-routed the transmission line around the park to  
          accommodate the State Park proponents' concerns.

          5)   Just compensation  :  This bill would require the electrical  
          corporation to provide "just compensation" to residential  
          landowners for any reduction in the value of their property  
          resulting from the reconstruction.  Because there currently  
          exists a 220 kV line, it would be difficult to assess any  
          decrease in property values exclusively due to the increase in  
          height of the tower. In addition, so many other factors affect  
          property values such as interest rates, unemployment rates, the  
          price of gas, and the overall state of the economy. As such, it  
          would be difficult to isolate all other factors to calculate,  
          with any level of certainty, a quantified effect on property  
          values directly and solely attributable to the reconstruction.

          The electrical corporation that is financing the Tehachapi  
          transmission line is Southern California Edison (SCE).  SCE  
          requests rate recovery from the Federal Energy Regulatory  
          Commission (FERC) for all transmission-related costs.  If FERC  
          does not allow the costs of "just compensation" through its  
          revenue requirement (allowing just compensation for  
          reconstruction would be precedent), all ratepayers would  
          continue to pay for the project because it's currently actually  
          being paid for through the CAISO transmission revenue charge. 


           REGISTERED SUPPORT / OPPOSITION  :   

           Support 
           
          None on file.

           Opposition 
           








                                                                  AB 1333
                                                                  Page  5

          Pacific Gas and Electric Company (PG&E)
          Southern California Edison (SCE)
           
          Analysis Prepared by  :    Gina Adams / U. & C. / (916) 319-2083